6654 EC Company signed.pdf
PDF 342 KB Posted
- Attached to
- 2023 Crack Seal Project
- Solicitation number
- S-KN0040-00007352
- Issued by
- Union County, Oregon
About this file
This is a signed Public Improvement Agreement between the State of Oregon, Department of Corrections (Owner) and EC Company dba EC Electric (Contractor) for the OSP Secure Perimeter project under Contract Number #6654. The agreement covers work as described in Invitation to Bid No. S-29100-00007353 and incorporates specifications, plans, and general requirements through various exhibits and attachments. The project start date is 10 days after notice to proceed, with substantial completion required by July 1, 2024, and final completion by August 1, 2024. The contract documents constitute the entire agreement and include a pricing submittal form, performance and payment bonds, general conditions for public improvement contracts, supplemental general conditions, specifications, plans, general requirements, and bidder's qualifications documentation. Jason Bruster serves as the Owner's Authorized Representative, while Steve Babcock represents the Contractor.
The total contract price is $3,811,911.00, comprised of a base bid of $3,599,709.00 and four alternates (ALT #1: $48,834.00; ALT #2: $48,834.00; ALT #3: $104,888.00; ALT #4: $9,646.00). Liquidated damages of $1,200.00 per calendar day apply for failures to meet both substantial and final completion dates. The Contractor, located at 32758 Old Hwy 34 SE, Albany, Oregon 97321, holds CCB# 49737. The agreement requires the Contractor to maintain compliance with House Bill 3060 (2017), including policies preventing sexual harassment, sexual assault, and discrimination against protected class employees. The contract was executed on October 18, 2023, with a CCB expiration date of October 13, 2023.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum No. 1~2.pdf | ||
| Bid documents~10.pdf | ||
| Bid tabulation~6.pdf | ||
| NOIA-Interested parties~3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF OREGON PUBLIC IMPROVEMENT AGREEMENT
for
OSP Secure Perimeter
Contract Number: #6654
This Agreement for the OSP Secure Perimeter (the "Agreement"), made by and between the State of Oregon, acting by and through the Department of Corrections, hereinafter called OWNER, and EC Compnay dba EC
Electric hereinafter called the CONTRACTOR (collectively the "Parties"), is effective on the date this Agreement has been signed by all the Parties and all required State of Oregon governmental approvals have been obtained.
Unless otherwise defined in the Invitation to Bid or in this Agreement, the capitalized terms used herein are defined in Section A 1 of the State of Oregon General Conditions for Public Improvement Contracts.
WITNESSETH:
1. Contract Price, Contract Documents and Work.
The CONTRACTOR, in consideration of the sum of $3,811,911.00 (the "Contract Price"), to be paid to the
CONTRACTOR by OWNER in the manner and at the time hereinafter provided, and subject to the terms and conditions provided for in the Invitation to Bid, this Public Improvement Agreement and other Contract
Documents, all of which are incorporated herein by reference, hereby agrees to perform all Work described and reasonably inferred from the Contract Documents.
The Contract Price includes the following items:
Base Bid: $3,599,709.00; ALT #1: $48,834.00, ALT #2: $48,834.00, ALT #3: $104,888.00, ALT #4: $9,646.00(As Detailed in Exhibit lr, Pricing Submittal Form)
CONTRACTOR shall perform the Work for the Contract Price pursuant to Invitation to Bid No. S-29100-00007353 and all Addenda thereto) and the following Exhibits and Attachments which are incorporated herein by this reference, whether or not physically attached to this Agreement:
EXHIBIT 1 PRICING SUBMITTAL FORM
EXHIBIT 2 [RESERVED]
EXHIBIT 3 PERFORMANCE BOND FORM
EXHIBIT 4 PAYMENT BOND FORM
EXHIBIT 5 [RESERVED]
EXHIBIT 6 GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS
EXHIBIT 7 SUPPLEMENTAL GENERAL CONDITIONS
ATTACHMENT B SPECIFICATIONS
ATTACHMENT C PLANS
ATTACHMENT D GENERAL REQUIREMENTS BIDDER'S QUALIFICATIONS
ATTACHMENT E SECURITY FORM (LEDS)
2. Representatives.
Unless otherwise specified in the Contract Documents, the OWNER designates Jason Bruster as its Authorized
Representative in the administration of this Contract. The above-named individual shall be the initial point of contact for matters related to performance, payment, authorization, and to carry out the responsibilities of the
OWNER. CONTRACTOR has named Steve Babcok as its Authorized Representative to act on its behalf.
3. Contract Dates.
PROJECT START DATE:
SUBSTANTIAL COMPLETION:
FINAL COMPLETION:
4. Liquidated Damages.
10 Davs After Notice to Proceed
07/01/24
08/01/24
Liquidated damages of $1,200.00 will apply to the contract resulting from this 1TB. Failure to substantially complete the Project by the, date of Substantial Completion, as specified in the Contract, will result in damage to the State of Oregon.
Moreover, failure to fully complete the Project by the date of Final Completion, as specified in the Contract, will also result indamage to the State of Oregon Since actual damage will be difficult to determine, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $1,200.00 per calendar day elapsed in excess of the Substantial Completion date stated in Section 3 of this Agreement.
Moreover, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $1,200.00 per calendar day elapsed in excess of the Final Completion date stated in Section 3 of this Agreement.
5. Certification - Non-Discrimination
Contractor certifies, in accordance with House Bill 3060 (2017 Oregon Laws, chapter 212)("HB 3060"), that it has in place a policy and practice of preventing sexual harassment, sexual assault, and discrimination against employees who are members of a "protected class," as that term is defined by subsection 2(1)(b) of HB 3060. As a material term and condition of this Agreement, Contractor must maintain, throughout the duration of this Agreement, a policy and practice that complies with HB 3060, including, but not limited to, giving employees written notice of the Contractor's policy and practice.
6. Integration THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE
PARTIES. NO WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THIS CONTRACT SHALL
BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT, MODIFICATION OR CHANGE, IF MADE, SHALL BE EFFECTIVE ONLY IN THE SPECIFIC INSTANCE AND FOR
THE SPECIFIC PURPOSE GIVEN. THERE ARE NO OTHER UNDERSTANDINGS, AGREEMENTS, OR
REPRESENTATIONS, ORAL OR WRITTEN, NOT SPECIFIED HEREIN REGARDING THIS CONTRACT.
CONTRACTOR, BY THE SIGNATURE BELOW OF ITS AUTHORIZED REPRESENTATIVE, HEREBY
ACKNOWLEDGES THAT IT HAS READ THIS CONTRACT, UNDERSTANDS IT, AND AGREES TO BE BOUND BY
ITS TERMS AND CONDITIONS.
In witness whereof, the STATE OF OREGON, acting by and through the Department of Corrections executes this Agreement and the CONTRACTOR does execute the same as of the day and year of this Agreement first above written.
CONTRACTOR DATA
CONTRACTOR NAME:
CONTRACTOR ADDRESS:
CONTRACTOR EMAIL ADDRESS:
49737
EC Company dba EC Electric
32758 Old Hwy 34 SE, Albany OR 97321 marketing@ecpowerslife.com
CONTRACTOR'S CCB#
.l:_ONTRAC!"OR'S SIGNATURE I odd J. Henne, CFO
Review by Facilities Administrator
State of Oregon by and through its
DEPARTMENT OF CORRECTIONS
01/15/2024
EXPIRATION DATE
10/13/23
DATE
DATE
DATE
18Oct23
10/18/2023
| 2023-10-18T07:56:39-0700 | |
| Ryan Kirtley |
File details come from the government source that posted it. Updated .