This document is Addendum #1 for a federal contract opportunity to construct a new campus chiller plant in Marion, Illinois (Project Number 657A5-21-401). The addendum provides RFI responses, updated drawings, and specification modifications to the original solicitation.
The drawing modifications span multiple sheets and address site utilities, infrastructure alignments, and building systems. Key changes include: modifications to site demolition limits for chilled water lines on Sheet C210; addition of valve installation keynotes and stationing for 12-inch ductile iron chilled water lines on Sheet C500; creation of a new profile sheet (C502) showing vertical alignments for chilled water lines, storm drainage lines (8-inch and 12-inch), sanitary lines (6-inch), and water lines (4-inch/6-inch); updates to roofing specifications from standard to TPO systems on architectural sheets; modifications to exterior wall panel dimensions to meet minimum wythe thickness requirements; adjustments to drilled pier lengths and masonry anchor testing requirements; updates to lintel schedules, electric unit heater voltages, and water-cooled chiller efficiency data; and clarification of electrical connections and pole light catalog numbers.
The specification modifications address multiple divisions and require contractors to: incorporate Schedule of Special Inspections and Statement of Special Inspections documents; change precast concrete panel finishes to "As-Cast Surface Finish"; delete references to stainless steel metal wall panels and correct colors; apply spray-applied fireproofing only to structural steel within 2-hour rated rooms per UL standards; delete acoustic level requirements for chillers; delete sound testing requirements for HVAC systems; modify seismic and wind load requirements for cooling towers; specify ECMs with N-1 redundancy for air-handling unit fan motors; and delete references to unused foundation systems and caisson load testing requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
08/20/2026
Construct New Campus Chiller Plant
Marion, IL
PROJECT NUMBER: 657A5-21-401
RFI RESPONSES, UPDATED DRAWINGS, AND SPECIFICATIONS
FOR ADDENDUM #1
REQUEST FOR INFORMATION
See RFI log attached.
DRAWING MODIFICATIONS
GI000:
1. MODIFY Sheet Index to include Revisions.
C210:
1. MODIFY site demolition keynote #7 to change existing chilled water supply and return line removal limits to new valve install location rather than back to the main line tie-in location.
C500:
1. ADD Site utility keynotes 19 and 20 to show installation of new valves on the proposed 12” ductile iron chilled water supply and return lines and on the existing chilled water supply and return lines to the current plant location. Valves are required on the existing lines to meet phasing requirements. Valves were added to the plan view with keynotes identifying their locations.
2. ADD Stationing for the proposed 12” chilled water lines.
C501:
1. ADD stationing for the proposed 12” chilled water lines, 8” storm line from Catch Basin 4 to the new plant, 12” storm line from Catch Basin 4 to Catch Basin 7, 6” sanitary line from the main line to the plant, and 4”/6” water line from the main line to the plant.
2. ADD a profile showing the vertical alignment of the 12” storm line from Catch Basins 0 to 5.
C502:
1. ADD New sheet added to the drawing set, including profiles for the proposed 12” chilled water lines, 8” storm line from Catch Basin 4 to the new plant, 12” storm line from Catch Basin 4 to Catch Basin 7, 6” sanitary line from the main line to the plant, and 4”/6” water line from the main line to the plant
AE102:
1 MODIFY Drawing Notes to reflect TPO roofing.
2 MODIFY General Notes to accurately point to AE401 and AE431 for roof details.
AE202:
1. MODIFY 2/AE202 Exterior Wall Panel Section (Typical) with updated dimensions to meet minimum wythe thickness requirement.
AE301:
1. MODIFY Drawing Notes to reflect TPO roof system.
2. MODIFY General Notes to reflect spray applied fireproofing on structural members only within the 2-hour rated Electrical Room.
AE310:
1. MODIFY precast insulated concrete wall panel profile in section.
S001:
1. MODIFY The drilled pier length to account for the socket in the Deep Foundations, Installation section of the general notes.
2. MODIFY The note in the Masonry Anchors, Testing section to include a qualified testing agency provided by the contractor.
SB101:
1. MODIFY The drilled pier length to 18’ plus the socket depth.
SF701:
1. MODIFY The lintel schedule to provide maximum lengths for L1 and update the sizes of L1 and L2.
M601:
1. MODIFY The electric unit heater schedule to show updated voltage.
MP201:
1. DELETE General Note B.
MP203:
1. MODIFY General Note B to only include heat trace on CDWS, CDWR, and EQ piping.
MP302:
1. MODIFY General Note C to only include heat trace on CDWS, CDWR, and EQ piping.
MP701:
1. MODIFY the Water-Cooled Chiller Schedule to include updated efficiency data for the chillers.
E001:
1. ADD a phasing plan for the required 12KV feeder work.
ES100:
1. MODIFY site plan to clarify the connection from Manhole No. 10 to the Building 7 transformer.
E500:
1. MODIFY motor starter schedule to update two motors that were originally showing a 0 load.
E600:
1. MODIFY luminaire schedule to add the pole catalog numbers for pole lights PL1–
PL4.
SPECIFICATION MODIFICATIONS
01 45 35 - SPECIAL INSPECTIONS:
1. ADD The Schedule of Special Inspections document to the specification.
2. ADD The Statement of Special Inspections document to the specification.
03 45 00 - PRECAST ARCHITECTURAL CONCRETE:
1. MODIFY Finish of precast architectural concrete panels to be 'As-Cast Surface Finish' (03 45 00 Section 3.7.A.1).
2. DELETE unused finish clauses.
07 42 13.02 – METAL WALL PANELS
1. DELETE Section 2.3.C referring to stainless steel panels.
2. MODIFY Section 2.1, removing irrelevant system descriptions.
3. MODIFY Section 2.4.D.2, correcting color to 179 Regal White.
07 81 00 – APPLIED FIREPROOFING
1. ADD Section 3.5.B and Section 1.1.B: Provide 2-hour spray-applied fire-resistive material (SFRM) only on structural steel members located within 2-hour rated rooms identified on the drawings, which is designed as a 2-hour fire-resistance–rated enclosure. Columns shall comply with UL N501.
Beams shall comply with UL N602. Where the rated enclosure includes the floor/ceiling assembly, apply SFRM per UL D902. Fireproofing is not required on structural steel outside this room.
23 64 00 - PACKAGED WATER CHILLERS:
1. DELETE Section 2.1.E related to required acoustic levels for centrifugal water-cooled chillers.
23 05 93 - TESTING, ADJUSTING, AND BALANCING FOR HVAC:
1. DELETE sound testing requirements.
23 65 00 - COOLING TOWERS:
1. MODIFY seismic and wind load requirements.
23 05 41 - NOISE AND VIBRATION CONTROL FOR HVAC:
1. DELETE sound testing requirements.
23 73 00 - INDOOR CENTRAL-STATION AIR-HANDLING UNITS:
1. MODIFY Section 2.1.F.3, fan motors to be ECMs with N-1 redundancy.
31 20 00 - EARTHWORK:
1. DELETE References to foundation systems not used on the project.
31 63 26 – DRILLED CAISSONS
1. MODIFY all sections regarding safety to reference Division 1 Specifications.
2. DELETE section requiring load testing of caissons.