TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
SECTION 01010 - SUMMARY OF WORK ............................................................................................................................ TS-1
SECTION 01019 - CONTRACT CONSIDERATIONS .......................................................................................................... TS-4
SECTION 01039 - COORDINATION AND MEETINGS ...................................................................................................... TS-7
SECTION 01300 - SUBMITTALS ............................................................................................................................................ TS-9
SECTION 01400 - QUALITY CONTROL ............................................................................................................................ TS-12
SECTION 01500 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS ................................................ TS-14
SECTION 01600 - MATERIAL AND EQUIPMENT ........................................................................................................... TS-16
SECTION 01700 - CONTRACT CLOSEOUT ...................................................................................................................... TS-18
SECTION 02200 – EXCAVATION AND EARTHWORK................................................................................................... TS-19
SECTION 02225 - TRENCHING, BACKFILLING, AND COMPACTING ...................................................................... TS-24
SECTION 02510 - BITUMINOUS CONCRETE PAVING .................................................................................................. TS-30
SECTION 02515 - ASPHALT JOINT AND CRACK SEALING ........................................................................................ TS-34
SECTION 02602 - STORM SEWER INLETS ....................................................................................................................... TS-37
SECTION 02720 - STORM SEWER PIPE ............................................................................................................................ TS-39
SECTION 02813 - PLAIN CEMENT CONCRETE CURB, SIDEWALK & RAMPS ...................................................... TS-41
SECTION 02923 - LANDSCAPE GRADING ........................................................................................................................ TS-46
SECTION 02936 - SEEDING .................................................................................................................................................. TS-48
SECTION 03303 - CONCRETE FOR UTILITY CONSTRUCTION ................................................................................. TS-52
5th Street from West Church Street towards Franklin Street Slatington Borough – 2023 CDBG
August, 2025 TS-1 LEA #7081
SECTION 01010 - SUMMARY OF WORK
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Statement of Work B. Description of Work C. Special Conditions D. Work Sequence
1.2 STATEMENT OF WORK
The Work included in this Contract consists of furnishing all plant, new materials, equipment, supplies, labor, transportation, fuel and power and performing all Work as required by the Contract, in strict accordance with the Specifications, Schedules and Drawings, and Pennsylvania Department of Transportation Publication 408 specifications, latest revision, all of which are made a part hereof;
and including such detail Drawings as may be furnished by the ENGINEER from time to time during the construction in interpretation of said Drawings. PennDOT Publication 408 shall be adhered to regarding construction methods and materials. Contract administration and measurement and payment basis shall be as specified in these Contract Documents. The Work shall be complete and all Work, materials, and services not expressly called for in the Specifications, or specially indicated on the Drawings, which may be necessary for complete and proper construction to carry out the Contract in good faith, shall be performed, furnished and installed by the CONTRACTOR at no additional cost to the OWNER. The Work shall be executed in the best and most workmanlike manner by qualified, careful and experienced workers.
1.3 DESCRIPTION OF WORK
The Work shall include, but not necessarily be limited to, furnishing all materials, performing all labor and constructing the following:
A. Contract No. ?: 5th Street Slatington Borough 2023 CDBG (Willow Avenue 432’ +/ - to North 2nd Street.)
Approximate dimensions for paving: Length - 290' +/ - Width – 30' +/-
1. Mobilization and demobilization, including all equipment needed for the project.
This will be paid 40% with first application for payment, 40% upon substantial completion, and 20% with final application for payment.
2. Protect existing curb and sidewalk during construction activities. Curb and sidewalk damaged or displaced by operations of the Contractor shall be replaced by the Contractor at no additional expense to OWNER.
3. Construct new concrete curb, sidewalk, down spout, and ADA ramps as indicated on the Contract Drawings and as directed by Engineer.
4. Milling at limits of work for placement of the wearing course and tie in to existing pavement. Mill isolated high points along curb lines, utilities, inlets within street cartways as necessary and sweep all surfaces to be paved. Mill depth shall be as indicated in the Bill Form & Contract Drawings.
5. CONTRACTOR shall supply and install risers for valve boxes and manholes as necessary to complete the paving overlay. CONTRACTOR shall verify appropriate
August, 2025 TS-2 LEA #7081 riser size. Only solid castings shall be used; Split ring types shall not be used.
6. Furnish and construct six (6") inch Subbase (NO.2A stone) to the limits shown on the drawings.
7. Furnish and construct four (4") inch Superpave Base Course, <0.3 Million ESALs, 25.0mm to the limits shown on the drawings.
8. Furnish and place bituminous tack coat and furnish and construct two (2") inch Superpave 9.5mm wearing course, SRL-M, <0.3 million ESALs to the limits shown on the drawings.
9. Seal all joints with rubberized bituminous sealing material.
10. Grade, seed and stabilize all disturbed areas behind curb line and unpaved areas.
11. Provide CS4171 Forms and certs for all used stone and pavement material.
12. Confirm to conditions as set forth in the PennDOT HOP Permit No.: 05064934, 05064935, 05064936
1.4 SPECIAL CONDITIONS
A. Measurement and payment will be made only for Work that has been acceptably performed within the limits shown on the plans, or authorized by the ENGINEER.
B. All excavation, including bulk excavation, excavation for subgrade, base repair, and storm sewer facilities, is unclassified and includes excavation and removal of all soil, shale, rock, boulders, fill, and all other materials encountered, of whatever nature.
C. The estimated quantities in these Contract Documents shall not be exceeded. It shall be the responsibility of the CONTRACTOR to maintain records of quantities used. If, in the CONTRACTOR'S opinion, the quantities stated will be exceeded, due to unforeseen field conditions, the CONTRACTOR shall contact the ENGINEER before proceeding with any additional Work. All quantities shall be subject to final field verification.
D. Cutting of pavement for patching shall be performed in a clean and neat manner. All excess materials shall be removed from the project site and disposed of properly by the CONTRACTOR.
E. The CONTRACTOR shall use caution so as not to disturb property corners located within the project area. The CONTRACTOR shall be responsible for notifying the ENGINEER of any property corners found, so that the ENGINEER can re-establish the property corner.
F. The CONTRACTOR shall relocate and/or reconstruct mailboxes, signs, fences and appurtenances located within Borough right-of-way as required by the ENGINEER. Any appurtenances disturbed shall be relocated or reconstructed to the property owner's satisfaction, to a condition equal to the existing condition prior to the start of construction.
These relocations shall be considered incidental to the Work specified in these Contract Documents unless otherwise noted.
G. When the bituminous wearing course is placed adjacent to curbs to form a bituminous gutter, upon or abutting existing bituminous material, or adjacent to structures, utilities, etc., it shall be sealed with bituminous material of the class and type designated for the surface course for a distance of twelve inches (12") from curb structures, utilities, etc., in order to prevent accelerated deterioration caused by natural elements.
August, 2025 TS-3 LEA #7081
H. The CONTRACTOR is required to provide traffic control for all Work in accordance with PennDOT Publication 213.
I. Erosion and sedimentation controls shall be installed during the work, as required. All Erosion and Sedimentation controls shall be in conformance with the requirements of the Pennsylvania Department of Environmental Protection. Erosion and sedimentation controls shall not be paid for directly, but be included in the unit prices as incidental to the items of Work.
1.5 WORK SEQUENCE
A. The CONTRACTOR shall submit a proposed sequence and schedule of work at the Preconstruction Conference.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
August, 2025 TS-4 LEA #7081
SECTION 01019 - CONTRACT CONSIDERATIONS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Acceptance of Proposal B. Pennsylvania Department of Transportation Approval C. Start of Work D. Escalator Clause E. Application for Payment F. Change Procedures G. Completion Date H. Liquidated Damages
1.2 ACCEPTANCE OF PROPOSAL
The OWNER reserves the right to delete item(s), portions of item(s) and/or adjust quantities from the Proposal at its discretion.
1.3 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION APPROVAL
In accordance with Pennsylvania Department of Transportation guidelines, upon receipt by the OWNER of the Agreement, required bonds, and Workmen's Compensation Affidavit executed by the CONTRACTOR, the OWNER shall forward same to the Pennsylvania Department of Transportation, Municipal Services Division for approval. The start of Work shall be contingent upon notification of approval granted by the Municipal Services Division and receipt by the CONTRACTOR of written Notice to Proceed provided by the ENGINEER. The OWNER shall obtain all necessary PennDOT permits, if necessary.
1.4 START OF WORK
Notification shall be given by the CONTRACTOR to the OWNER/ENGINEER a minimum of seventy-two (72) hours prior to the start of any Work.
1.5 ESCALATOR CLAUSE
A. The CONTRACTOR/Supplier shall have the right to increase the Contract Unit Price of the item(s) specified in an amount equal to the CONTRACTOR/Supplier's increase in costs of such bituminous material occurring subsequent to the date of the bid opening (hereinafter referred to as "base date"). Any increase/decrease in the CONTRACTOR/Supplier's cost of such item(s) after the base date shall be verified by proper documents from the CONTRACTOR/Supplier's source of supply.
B. Upon receipt of the Notice of Award, the successful bidder shall submit the following information which establishes the Unit Cost of asphalt on the base date.
1. The price per ton of asphalt as of the base date from the source of supply. A letter from the refinery signed by a company official will suffice for this documentation.
2. The asphalt content of the mix design to be used by the CONTRACTOR expressed in percent by weight. (A range of asphalt content is not adequate.) The CONTRACTOR shall submit the
August, 2025 TS-5 LEA #7081
PennDOT Approved Job Mix Formula Report (PennDOT Form TR-448A) indicating the asphalt content in the approved mix design for each type of bituminous concrete to be supplied.
C. Should the CONTRACTOR/Supplier's allocation of any bituminous materials be materially reduced by the CONTRACTOR/Supplier's source of supply, the CONTRACTOR/Supplier may reduce, proportionately, the quantity of such bituminous materials to be delivered in accordance with the Contract.
D. The municipality may withdraw or reduce the quantity of any item(s) or terminate or reduce the scope of the contract:
1. If the Unit Cost of any item(s) covered by these escalator provisions is increased more than ten percent (10%) above the base price, or,
2. If, because of an increase in the Unit Cost of one or more items covered by these escalator provisions, the total estimated cost of the Contract is increased more than twenty percent (20%) above the base price.
E. Payments on Contracts containing an escalation clause must be documented from the actual source of supply. A letter from the Supplier's actual source of material and signed by a company official will suffice for this documentation. The letter shall contain the following:
1. The posted price on date of bid.
2. The posted price on date of delivery.
3. Price computation based on the documented price change.
F. All price changes must relate directly to the increase/decrease in cost of material and may not allow for increased profit.
1.6 APPLICATIONS FOR PAYMENT
A. Submit three (3) copies of each Application for Payment; A Standard form included within this project manual is preferred.
B. Content and Format: Utilize Bid Form for listing items and unit prices in Application for Payment. Additional information may be requested by ENGINEER upon review.
C. Submit at intervals of no less than one month.
1.7 CHANGE PROCEDURES
A. The ENGINEER will advise of minor changes in the Work not involving an adjustment to Contract Price or Contract Time as authorized by section 9.05 of the General Conditions by issuing supplemental instructions.
B. The ENGINEER may issue a Notice of Change which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. CONTRACTOR will prepare and submit an estimate within ten (10) days.
C. The CONTRACTOR may propose a change by submitting request for change to the ENGINEER, August, 2025 TS-6 LEA #7081 describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Lump Sum/Unit Price and Contract Time with full documentation. Document any requested substitutions in accordance with Section 01600.
D. Lump Sum Price Change Order: Based on Notice of Change and CONTRACTOR'S fixed price quotation or CONTRACTOR'S request for a Change Order as recommended by ENGINEER.
E. Unit Price Change Order: For predetermined unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, execute Work under a Work Directive Change. Changes in Contract Price or Contract Time will be computed as specified for Time and Material Change Order.
F. Work Change Directive: ENGINEER may issue a directive, on EJCDC 1910-8-F Work Directive Change, signed by the OWNER, instructing the CONTRACTOR to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.
G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. ENGINEER will determine the change allowable in Contract Price and Contract Time as provided in the Contract documents.
H. Maintain detailed records of work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.
I. Change Orders shall be submitted on the form included within this specification.
J. Execution of Change Orders: ENGINEER will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.
1.8 COMPLETION DATE
The entire project shall be substantially completed within sixty (60) calendar days of receipt of the Notice to Proceed with final completion within thirty (30) calendar days of Substantial Completion.
1.9 LIQUIDATED DAMAGES
If all Work is not completed on time, liquidated damages will be assessed at a rate per additional calendar day, as indicated in the Agreement.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
August, 2025 TS-7 LEA #7081
SECTION 01039 - COORDINATION AND MEETINGS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Coordination and project conditions B. Field engineering C. Preconstruction meeting D. Progress meetings
1.2 COORDINATION
A. Coordinate scheduling, submittals, and all Work to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later to ensure the construction is completed within the specified Contract Time.
B. Coordinate completion and clean-up of Work in preparation for Substantial Completion as well as portions of Work designated for OWNER partial occupancy.
C. After OWNER occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of OWNER activities.
1.3 FIELD ENGINEERING
A. CONTRACTOR shall locate and protect survey control and reference points.
B. Control datum for survey will be provided by ENGINEER.
C. Verify rights-of way and easements; confirm drawing dimensions and elevations.
D. Establish elevations, lines, and levels, utilizing recognized engineering survey practices and in accordance with construction stakeout provided by ENGINEER.
1.4 PRECONSTRUCTION MEETING
A. ENGINEER will schedule a meeting after Notice of Award.
B. Attendance Required: OWNER, ENGINEER, and CONTRACTORS.
C. Agenda:
1. Distribution of Contract Documents.
2. Submittal of list of Subcontractors, list of products, schedule of values, and progress schedule.
3. Designation of personnel representing the parties in Contract, and the ENGINEER.
4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.
5. Scheduling.
6. Use of premises by OWNER and CONTRACTOR.
7. OWNER requirements and partial occupancy.
8. Construction facilities and controls provided by OWNER.
August, 2025 TS-8 LEA #7081
9. Temporary utilities provided by OWNER.
10. Survey and construction layout.
11. Security and housekeeping procedures.
12. Application for payment procedures.
13. Procedures for testing.
14. Procedures for maintaining record documents.
15. Requirements for start-up of equipment.
16. Inspection and acceptance of equipment put into service during construction period.
1.5 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. ENGINEER will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.
C. Attendance Required: Job superintendent, major Subcontractors and suppliers, OWNER, ENGINEER, as appropriate to agenda topics for each meeting.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Field observations, problems, and decisions.
4. Identification of problems which impede planned progress.
5. Review of submittals, schedule and status of submittals.
6. Review of offsite fabrication and delivery schedules.
7. Maintenance of progress schedule.
8. Corrective measures to regain projected schedules.
9. Planned progress during succeeding Work period.
10. Coordination of projected progress.
11. Effect of proposed changes on progress schedule and coordination.
12. Other business relating to Work.
E. ENGINEER to record minutes and distribute copies within two (2) days after meeting to participants, OWNER, and those affected by decisions made.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
August, 2025 TS-9 LEA #7081
SECTION 01300 - SUBMITTALS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Submittal procedures
B. Construction progress schedules
C. Proposed Products list
D. Product Data
E. Shop Drawings
F. Design data
G. Test reports
H. Certificates
I. Manufacturers' instructions
1.2 REFERENCES
A. AGC (Associated General CONTRACTORS of America) publication 'The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry".
1.3 SUBMITTAL PROCEDURES
A. Transmit four (4) copies of each submittal with ENGINEER accepted form.
B. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.
C. Identify project, CONTRACTOR, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.
D. Apply CONTRACTOR'S stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
E. Schedule submittals to expedite the project, and deliver to ENGINEER at business address.
Coordinate submittal of related items.
F. For each submittal for review, allow fifteen (15) days excluding delivery time to and from the
CONTRACTOR.
G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.
H. Provide space for CONTRACTOR and ENGINEER review stamps.
I. When revised for resubmittal, identify all changes made since previous submittal.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
August, 2025 TS-10 LEA #7081
1.4 CONSTRUCTION PROGRESS SCHEDULES
A. Submit initial schedule in duplicate within fifteen (15) days after date of OWNER/CONTRACTOR Agreement.
B. Revise and resubmit as required.
C. Submit revised schedules with each Application for Payment, identifying changes since previous version.
D. Submit a horizontal bar chart with separate line for each major portion of Work or operation identifying first work day of each week.
E. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.
F. Indicate estimated percentage of completion for each item of Work at each submittal.
G. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by OWNER and required by Allowances.
1.5 PROPOSED PRODUCTS LIST
A. Within ten (10) days after date of OWNER/CONTRACTOR Agreement submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1.6 PRODUCT DATA
A. Product Data For Review:
1. Submit to ENGINEER for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, provide copies and distribute in accordance with submittal procedures article above and for record documents purposes described in Section 01700 Contract Closeout.
B. Product Data For Information:
1. Submit for the ENGINEER'S knowledge as contract administrator or for the OWNER.
C. Product Data For Project Closeout:
1. Submit for the OWNER's benefit during and after project completion.
2. Submit up to five (5) copies; two (2) copies will be retained by the ENGINEER.
3. Mark each copy to identify applicable products, models, options, and other data;
Supplement manufacturer's standard data to provide information specific to this Project.
4. After review distribute in accordance with the Submittal Procedures article above and provide copies for record documents described in Section 01700 Contract Closeout.
August, 2025 TS-11 LEA #7081
1.7 SHOP DRAWINGS
A. Shop Drawings For Review:
1. Submit to ENGINEER for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01700 - Contract Closeout.
B. Shop Drawings For Information:
1. Submit for the ENGINEER'S knowledge as contract administrator or for the OWNER.
C. Shop Drawings For Project Closeout:
1. Submitted for the OWNER's benefit during and after project completion.
D. Submit in the form of one reproducible transparency and one opaque reproduction.
1.8 DESIGN DATA, TEST REPORTS & CERTIFICATES
A. Submit for the ENGINEERS knowledge as contract administrator or for the OWNER.
B. Submit for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
C. When specified in individual sections of this specification, submit certification by the manufacturer, installation/application subcontractor, or the CONTRACTOR to ENGINEER, in quantities specified for Product Data.
D. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
E. Certificates may be recent or previous test results on material or Product, but must be acceptable to ENGINEER.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
August, 2025 TS-12 LEA #7081
SECTION 01400 - QUALITY CONTROL
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Quality assurance - control of installation
B. References and standards
C. Inspecting and testing services
1.2 QUALITY ASSURANCE - CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.
B. Comply with manufacturers' instructions, including each step-in sequence.
C. Should manufacturers' instructions conflict with Contract Documents, request clarification from ENGINEER before proceeding.
D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Perform Work by persons qualified to produce required and specified quality.
F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.
1.3 REFERENCES AND STANDARDS
A. For Products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Conform to reference standard by date of issue current on date of Contract Documents, except where a specific date is established by code.
C. Obtain copies of standards where required by product specification sections.
D. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of the ENGINEER shall be altered from the Contract Documents by mention or inference otherwise in any reference document.
1.4 TESTING AND INSPECTION SERVICES
A. OWNER will select an independent firm to perform testing and inspection from list of firms supplied by CONTRACTOR. CONTRACTOR shall include payment of required inspection services within the prices bid for individual items of Work.
B. The independent firm will perform tests, inspections, and other services specified, in individual specification sections and as required by the ENGINEER.
C. Testing and source quality control may occur on or off the project site. Perform off-site testing
August, 2025 TS-13 LEA #7081 as required by the ENGINEER or the OWNER.
D. Reports will be submitted by the independent firm to the ENGINEER in duplicate, indicating observations and results of tests and indicating compliance or noncompliance with Contract Documents.
E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.
1. Notify ENGINEER and independent firm twenty-four (24) hours prior to expected time for operations requiring services.
2. Make arrangements with independent firm and pay for additional samples and tests required for CONTRACTOR'S use.
F. Testing does not relieve CONTRACTOR to perform Work in accordance with Contract requirements.
G. Retesting required because of nonconformance to specified requirements shall be performed by the same independent firm on instructions by the ENGINEER. Payment for retesting will be charged to the CONTRACTOR by deducting testing charges from the Contract Price.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
August, 2025 TS-14 LEA #7081
SECTION 01500 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Temporary Controls: Barriers, enclosures and fencing, protection of the work, and water control.
B. Construction Facilities: Progress cleaning, project signage.
1.2 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to allow for OWNER'S use of site, and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide barricades required by governing authorities for public rights-of-way.
C. Provide protection for plants to remain. Replace damaged plants.
D. Protect vehicular traffic, stored materials, site, and structures from damage.
1.3 WATER CONTROL
A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.
B. Protect site from puddling or running water. Provide water barriers as required to protect site from soil erosion.
1.4 DUST CONTROL
A. Execute Work by methods to minimize raising dust from construction operations.
B. Provide positive means to prevent air-borne dust from dispersing into atmosphere.
1.5 PROTECTION OF INSTALLED WORK
A. Protect installed Work and provide special protection where indicated in individual Sections of this specification.
B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to minimize damage.
C. Prohibit traffic from landscaped areas.
1.6 SECURITY
A. Provide security and facilities to protect Work, and existing facilities, and OWNERS operations from unauthorized entry, vandalism, or theft.
1.7 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
B. Collect and remove waste materials, debris, and rubbish from site periodically and dispose off-
August, 2025 TS-15 LEA #7081 site.
1.8 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary above grade or buried utilities, equipment, facilities, materials, prior to Substantial Completion inspection.
B. Clean and repair damage caused by installation or use of temporary work.
C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
August, 2025 TS-16 LEA #7081
SECTION 01600 - MATERIAL AND EQUIPMENT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Products
B. Transportation and handling
C. Storage and protection
D. Product options
E. Substitutions
1.2 PRODUCTS
A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.
B. Provide interchangeable components of the same manufacture for components being replaced.
1.3 TRANSPORTATION AND HANDLING
A. Transport and handle products in accordance with manufacturer's instructions.
B. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.
C. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage.
1.4 STORAGE AND PROTECTION
A. Store and protect products in accordance with manufacturers' instructions.
B. Store with seals and labels intact and legible.
C. Store sensitive products in weather tight, climate-controlled enclosures in an environment favorable to Product.
D. For exterior storage of fabricated products, place on sloped supports above ground.
E. Provide off-site storage and protection when site does not permit on-site storage or protection.
F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.
G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.
H. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
I. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.
1.5 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.
August, 2025 TS-17 LEA #7081
B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:
Submit a request for substitution for any manufacturer not named in accordance with the following article.
1.6 SUBSTITUTIONS
A. ENGINEER will consider requests for Substitutions only within fifteen (15) days after date of OWNER/CONTRACTOR Agreement.
B. Substitutions may be considered when a Product becomes unavailable through no fault of the
CONTRACTOR.
C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.
D. A request constitutes a representation that the CONTRACTOR:
1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.
2. Will provide the same warranty for the Substitution as for the specified Product.
3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to OWNER.
4. Waives claims for additional costs or time extension which may subsequently become apparent.
5. Will reimburse OWNER and ENGINEER for review or redesign services associated with re-approval by authorities.
E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.
F. Substitution Submittal Procedure:
1. Submit three (3) copies of Request for Substitution for consideration. Limit each request to one proposed substitution.
2. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.
3. Indicate advantage to OWNER if substitution is allowed, including cost and/or time savings.
4. The ENGINEER will notify CONTRACTOR in writing of decision to accept or reject request.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
August, 2025 TS-18 LEA #7081
SECTION 01700 - CONTRACT CLOSEOUT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Closeout procedures
B. Final cleaning
C. Adjusting
D. Project record documents
E. Warranties and bonds
1.2 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for ENGINEER'S review.
B. Provide submittals to ENGINEER that are required by governing or other authorities.
C. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and sum remaining due.
1.3 FINAL CLEANING
A. Execute final cleaning prior to final project assessment.
B. Clean site sweep paved areas, rake clean landscaped surfaces.
C. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.4 WARRANTIES AND BONDS
A. Provide notarized copies, in duplicate.
B. Execute and assemble transferable warranty documents from Subcontractors, suppliers, and manufacturers.
C. Provide Table of Contents and assemble in three D side ring binder with durable plastic cover.
D. Submit prior to final Application for Payment.
E. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within ten (10) days after acceptance, listing date of acceptance as start of warranty period.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
August, 2025 TS-19 LEA #7081
SECTION 02200 – EXCAVATION AND EARTHWORK
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Clearing and Grubbing
B. Stripping and Stockpiling Topsoil
C. Rock Excavation
D. Excavation
E. Subgrade Preparation
F. Filling
G. Backfilling
H. Rough grading
I. Shoring, Bracing and Sheeting
J. Underpinning
1.2 REFERENCES
A. ANSI/ASTM C 136 Sieve Analysis of Fine and Coarse Aggregates
B. ANSI/ASTM D 1556 Density of Soil in Place by the Sand Cone Method
C. ANSI/ASTM D 1557 Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10 Pound Rammer and 18-inch drop
D. ANSI/ASTM D 2167 Density of Soil in Place by the Rubber Balloon Method
E. ANSI/ASTM D 2922 Density of Soil & Soil Aggregate in place by Nuclear Methods
1.3 QUALITY ASSURANCE
A. Filling and backfilling and subgrade preparation will be tested to verify compaction requirements.
B. Testing will be performed in accordance with Section 01400 – Quality Control.
1.4 REGULATORY REQUIREMENTS
A. Due to the proximity of work to existing homes, blasting will not be allowed.
B. Conform to local code requirements for disposal of debris; Burning of debris will not be allowed.
C. Obtain permits from authorities having jurisdiction before drilling is started.
D. Rules and regulations of the various utility companies and other authorities having jurisdiction over such Work shall be observed in the performance of all earthwork operations.
1.5 PROTECTION
A. Protect existing monuments, bench marks, structures, fences, sidewalks, paving and curbs and other markers before and during the Work. Restore any damaged items to original condition or repair as directed.
August, 2025 TS-20 LEA #7081
B. Protect any trees or shrubs shown or designated to be saved by boxing or wire fencing staked securely in place or other approved means, maintained until completion of Work.
C. Protect and maintain above and below grade utilities that are to remain.
D. Protect excavations and adjacent property and structures by shoring, bracing, sheet piling, underpinning or other methods as required to prevent cave-in, damage, and/or loose soil from falling into the excavation.
E. Underpin adjacent structures and utilities which may be damaged by excavation work.
F. OWNER shall be notified immediately if any unexpected subsurface condition, such as buried structures or utility lines is encountered, and discontinue work in that area until notified to proceed. OWNER will determine the disposition of the obstruction. CONTRACTOR shall adequately protect and support the obstruction until a determination is made and relocated, realign or dispose of the obstruction as authorized by OWNER.
G. Protect the bottom of excavations and soil adjacent to and beneath foundations from frost.
H. The top of the excavation shall be mounded or graded to prevent surface water from entering the excavation.
I. Erect and maintain guide rails, fences, warning lights or other protection as required for the safety of all persons at the excavations.
1.5 SUBMITTALS
A. Submit samples of each type of fill and backfill material to be used in accordance with Section 01400 – Quality Control. Each sample shall be sealed in an air-tight container and delivered to the designated testing laboratory, as directed.
PART 2 PRODUCTS
2.1 TOPSOIL: Excavated material, graded free of roots, rocks larger than one (1”) inch, subsoil, debris and weeds.
2.2 SUBSOIL: Excavated material, graded free of lumps larger than six (6”) inches, rocks larger than three (3”) inches and debris.
2.3 ROCK: Solid mineral material in boulders measuring one-half (1/2) cubic yard or more in volume, or solid material in ledges, bedded deposits and unstratified masses, which cannot be removed without systematic drilling and blasting.
2.4 BURIED STRUCTURES: Concrete and masonry structures not shown on the drawings and encountered during the excavation and requiring removal shall be classified as rock.
2.5 SELECT FILL MATERIALS
A. Crushed Stone or Gravel: free of shale, clay, friable materials, debris and organic materials graded in accordance with PennDOT No. 2A.
2.6 COMMON FILL MATERIALS: Subsoil; either reused or imported free of lumps larger than six (6”) inches, rocks larger than three (3”) inches, roots, organic material and debris.
2.7 ACCESSORIES:
A. Silt Barrier Fence – PennDOT Class 3, Type B.
B. Separation Fabric – PennDOT Class 4.
August, 2025 TS-21 LEA #7081
PART 3 EXECUTION
3.1 CLEARING AND GRUBBING
A. Clear and grub all areas required for access to the site and execution of the Work. Remove all trees and shrubs within the marked areas designated for removal.
B. Protect all trees and shrubs designated to be maintained or relocated.
C. Grub out all stumps and roots to a minimum of three (3’) feet below finished grade. Clear undergrowth and dead wood without disturbing the subsoil.
D. Remove and dispose of all perishable and objectionable material including, but not limited to, trees, brush, vines, shrubs, bushes, logs, stumps, roots, weeds, rubbish and other organic material.
3.2 PREPARATION
A. Identify required lines, levels, contours and datum. Coordinate with Section 1039.
B. Identify all utilities and mark locations.
C. Maintain and protect existing utilities that pass through the work area and are to remain in service.
D. Notify utility companies to remove and/or relocate utilities as required.
E. Upon discovery of unknown utility or concealed conditions, discontinue work in the affected area and notify OWNER.
F. Implement all procedures as required by PA Department of Environmental Protection for Erosion and Sediment Control.
3.3 STRIPPING TOPSOIL
A. Before starting excavation, remove topsoil to its full depth, from all areas that are to be further excavated, re-landscaped or re-graded. Do not excavate saturated topsoil.
B. Topsoil shall be stockpiled at the site, as directed, for use in further finish grading. All stockpiles shall receive temporary seeding and silt barrier fence installed downgrade of the pile.
3.4 ROCK EXCAVATION
A. CONTRACTOR shall excavate and remove rock by mechanical methods to the dimensions and elevations as required for the work. Due to the proximity of work to existing houses, blasting will not be allowed.
B. Cut away rock at excavation bottom to form a sound level bearing surface. Shattered, fractured, or otherwise unsound shale layers shall be removed.
C. All excavated material shall be removed from the site and disposed of in a proper manner by the CONTRACTOR.
3.5 EXCAVATION
A. All excavation Work performed under this contract is UNCLASSIFIED, and includes excavation and removal of all soil, shale, rock, boulders, fill, and all other materials encountered of whatever nature.
B. CONTRACTOR shall perform all excavation required to construct all structures, roadways, paved areas, and Work incidental thereto. Excavation shall extend a sufficient distance to allow for working space and inspection, except where concrete is to be deposited directly against excavated surfaces. All loose material shall be removed from excavations, and bottoms
August, 2025 TS-22 LEA #7081 shall be carefully leveled to grade.
C. None of the above provisions shall be construed to relieve the bidder of their responsibility to make a careful personal examination of the site in order to satisfy themselves as to the nature and location of the Work required, the conformation of the ground, the soil and rock conditions and the character, quality, and quantity of the materials.
D. Excavated materials to be used for backfill or other purposes shall be piled away from the edge of the excavated area a sufficient distance to prevent overloading the bank, and graded to prevent surface water from entering the excavated area. Excess material from excavation not suitable nor required for backfill or other purposes shall be adequately disposed of by the
CONTRACTOR.
E. Excavation shall not be carried below existing structure foundations until underpinning and/or shoring, to be performed by the CONTRACTOR, has been completed.
F. Do not excavate to full depth when rain or freezing conditions are imminent. Completed foundation soil surfaces shall be protected from frost. Where foundation soil surfaces are damaged by water, mud, or otherwise disturbed, all loose mud or other materials shall be removed and the surface re-graded and restored to plan grade with the same strength concrete as that specified for the footing above or compacted select backfill, as directed.
G. CONTRACTOR shall furnish adequate advance notification to OWNER of times when footing excavations are to be completed so that the bearing quality of the bottoms may be inspected and/or tested before forms are constructed or concrete placed.
H. Should the bearing at the levels indicated be found by OWNER to be inadequate, they may order the excavation carried down to sound bearing. Such excavation shall be classed as additional work and payment made of the basis of unit prices agreed upon by CONTRACTOR and OWNER. Should suitable bearing be found at a lesser depth than indicated, OWNER may order the reduction of excavation specified or shown on the Drawings and the CONTRACTOR shall allow a credit for excavation thus omitted on the same basis.
I. CONTRACTOR shall pump or otherwise remove any water which may be found in the excavation, and shall provide drainage ditches, underdrains, flumes, well points, pumping equipment or other materials as necessary to keep the excavation free of water so that all work can be performed in dry conditions. CONTRACTOR may be required to utilize a pumped water filter bag for any pumped water, as required by PA DEP.
3.6 SUBGRADE PREPARATION
A. After excavating and/or stripping topsoil in the areas of buildings, roads and other structures, the existing subgrade shall be proofrolled with at least ten (10) complete coverages of a ten
(10) ton static capacity roller, to obtain a firm, unyielding subgrade. CONTRACTOR shall notify OWNER at least twenty-four (24) hours in advance of the proofrolling operation, so that OWNER’s representative can observe the process.
B. If during the proofrolling operations any soft, unstable or yielding areas are found, they shall be overexcavated to a depth and width as authorized by OWNER and backfilled with select fill compacted to an in-place density of ninety-eight (98) percent of the maximum dry density or otherwise stabilized or modified as authorized by OWNER. Work performed to correct these irregularities shall be paid as an extra item of work based on established Contract unit prices.
3.7 FILLING, BACKFILLING AND ROUGH GRADING
A. Filling and backfilling shall be performed to the rough grades and compaction percentages as indicated in the schedule below by placing and compacting select fill or approved common fill in continuous layers not exceeding eight (8”) inches loose depth.
August, 2025 TS-23 LEA #7081
B. The fill or backfill material shall be maintained at +/-3% of the optimum moisture content, as determined by testing, to ensure proper compaction.
C. No backfill shall be placed on frozen, wet, spongy or unstable subgrade surfaces. No frozen materials shall be used for fill.
D. CONTRACTOR shall employ a placement method to avoid damage to foundation walls, dampproofing, buried piping and accessories.
E. Foundation walls shall be completely cured, tested for watertightness and braced prior to backfilling.
F. When walls are to be backfilled on both sides, the backfilling shall be done simultaneously, never exceeding a differential fill height of two (2’) feet.
3.8 BACKFILL SCHEDULE
A. The paragraphs below identify location, fill material to be used in layer from the prepared existing subgrade up to the proposed rough grade or base elevation and compaction as a percentage of the maximum density as determined by testing.
B. Compaction testing will be performed in accordance with Section 01400 of these specifications.
If tests indicate work does not meet the specified requirements, it shall be removed, replaced and retested until compliance is achieved.
C. Schedule:
1. Slabs on grade – Approved common fill compacted to 95% with a six (6”) inch thick cover of select fill compacted to 98%.
2. Building and equipment foundations, Sidewalk and ramp areas – Approved common fill compacted to 98% with a four (4”) inch thick cover of select fill compacted to 98%.
3. Grassed areas – Subsoil to four (4”) inches below finished grade compacted to 85%.
D. All areas disturbed during construction shall be rough graded to the elevations as indicated on the Drawings. Slope away from the building a minimum of two (2”) in ten (10’) feet unless noted otherwise on the Drawings. Changes in grade shall be gradual and slopes shall be blended into level areas.
E. Clean stockpile areas of excess fill material and remove and properly dispose of surplus from the site. Any paved area (new or existing) over which hauling operations or other equipment moving are conducted shall be kept clean and any soil or other material left on paved surfaces shall be promptly removed by CONTRACTOR.
F. Any areas damaged or disturbed during the course of the work shall be restored to their original condition, as authorized by OWNER.
A…