614090 - Bid Tabulations.pdf

PDF 881 KB Posted

Attached to
614090 FALL RIVER Bridge Preservation, F-02-065, Fourth Street over I-195
Solicitation number
BD-27-1030-0H100-0H002-130747
Issued by
Bristol County, Massachusetts

About this file

Bid Tabulation Summary

This bid tabulation document from the Massachusetts Department of Transportation (MassDOT) presents the results of competitive bidding for Project 614090, a bridge preservation contract for the Fourth Street bridge over Interstate 195 in Fall River, Massachusetts. The project encompasses comprehensive bridge work including partial demolition of the superstructure, excavation, grading, drainage adjustments, bridge pavement milling, asphalt surface course installation, curb and sidewalk work, electrical conduit and lighting installation, traffic signal relocation, safety signage and temporary traffic management, and structural steel cleaning and painting. Bids were opened on July 28, 2026, with the project assigned Contract Number 134822 under District 5. The scope of work includes numerous line items ranging from miscellaneous structural steel (1,450 pounds) to temporary protective shielding (1,800 square feet), with quantities specified for each work category.

Eight contractors submitted sealed bids for the project, with total bid amounts ranging from $2,385,000 (New England Infrastructure Inc., the lowest bidder) to $3,726,335.40 (S&R Corporation, the highest bidder). Additional bidders included SW Construction Enterprises LLC at $2,455,315, NEL Corporation at $2,468,545.90, MIG Corporation at $2,827,564.25, SPS New England Inc. at $3,311,455, and Aetna Bridge Company at $3,393,800. The office estimate was established at $1,884,510. Bid pricing shows significant variation across contractors for individual line items, particularly for major work categories such as partial demolition of the superstructure (ranging from $230,000 to $900,000), truck-mounted attenuators (ranging from $48,000 to $144,000), and structural steel cleaning and painting (ranging from $467,500 to $1,072,500). The contract is subject to Massachusetts prevailing wage requirements and price adjustment provisions for materials including hot mix asphalt, Portland cement, diesel fuel, gasoline, and structural steel.

View the file

Other files

File Type Posted
614090 Bid Items List.txt TXT text file
A00808-614090.pdf PDF
BIDS OPENED - Tuesday - July 28-2026~1.pdf PDF
A00875-614090.pdf PDF
Link to Bid Opening 7-28-2026~2.pdf PDF
614090 - Plan Holders List 7-27-2026.pdf PDF
A00803-614090.pdf PDF
A00804-614090.pdf PDF
FALL RIVER-614090-134822-A-1.pdf PDF
A00801-614090.pdf PDF
614090 - Notice to Contractors.pdf PDF
A00820-614090.pdf PDF
614090 - Plan Holders List 7-15-2026.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prelims Unit

Bid Tabulations

Project # : 614090 Bids Open Date : 28 Jul 2026 Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

Office Estimate NEW ENGLAND INFRASTRUCTURE INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

107.18 1,450.000 LB MISCELLANEOUS STRUCTURAL STEEL $40.00 $58,000.00 $75.00 $108,750.00

114.11 1.000 LS PARTIAL DEMOLITION OF SUPERSTRUCTURE OF

BRIDGE NO. F-02-065 (3XJ)

$226,000.00 $226,000.00 $550,000.00 $550,000.00

120.1 65.000 CY UNCLASSIFIED EXCAVATION $80.00 $5,200.00 $150.00 $9,750.00

141.1 8.000 CY TEST PIT FOR EXPLORATION $120.00 $960.00 $150.00 $1,200.00

151.01 30.000 CY GRAVEL BORROW - TYPE C $150.00 $4,500.00 $150.00 $4,500.00

170. 40.000 SY FINE GRADING AND COMPACTING - SUBGRADE

AREA

$20.00 $800.00 $30.00 $1,200.00

220. 2.000 EA DRAINAGE STRUCTURE ADJUSTED $1,000.00 $2,000.00 $1,500.00 $3,000.00

415.4 1,325.000 SY BRIDGE PAVEMENT MILLING $25.00 $33,125.00 $25.00 $33,125.00

450.60 115.000 TON SUPERPAVE BRIDGE SURFACE COURSE - 9.5 (SSC-

B - 9.5)

$225.00 $25,875.00 $400.00 $46,000.00

451. 35.000 TON HMA FOR PATCHING $400.00 $14,000.00 $200.00 $7,000.00

452. 105.000 GAL ASPHALT EMULSION FOR TACK COAT $13.00 $1,365.00 $30.00 $3,150.00

453. 885.000 FT HMA JOINT ADHESIVE $2.50 $2,212.50 $4.00 $3,540.00

472. 45.000 TON TEMPORARY ASPHALT PATCHING $310.00 $13,950.00 $200.00 $9,000.00

503. 25.000 FT GRANITE CURB TYPE VA3 - STRAIGHT $120.00 $3,000.00 $140.00 $3,500.00

503.1 6.000 FT GRANITE CURB TYPE VA3 - CURVED $140.00 $840.00 $150.00 $900.00

507. 2.000 EA GRANITE TRANSITION CURB - SLOPED TO

VERTICAL - STRAIGHT

$750.00 $1,500.00 $900.00 $1,800.00

509.1 18.000 FT GRANITE TRANSITION CURB FOR PEDESTRIAN

CURB RAMPS - CURVED

$85.00 $1,530.00 $150.00 $2,700.00

594. 55.000 FT CURB REMOVED AND DISCARDED $25.00 $1,375.00 $20.00 $1,100.00

628.304 1.000 EA TEMPORARY IMPACT ATTENUATOR, NON-

REDIRECTIVE, TL-2

$6,500.00 $6,500.00 $10,000.00 $10,000.00

645.072 200.000 FT 72 INCH CHAIN LINK FENCE (PIPE TOP RAIL) (LINE

POST OPTION)

$75.00 $15,000.00 $80.00 $16,000.00

652.072 1.000 EA 72 INCH CHAIN LINK FENCE END POST $450.00 $450.00 $500.00 $500.00

653.072 2.000 EA 72 INCH CHAIN LINK FENCE CORNER OR

INTERMEDIATE BRACE POST

$550.00 $1,100.00 $600.00 $1,200.00

657. 85.000 FT TEMPORARY FENCE $37.00 $3,145.00 $50.00 $4,250.00

669.1 215.000 FT FENCE REMOVED AND DISCARDED $15.00 $3,225.00 $30.00 $6,450.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 1 of 12

Project # : 614090 Bids Open Date : 28 Jul 2026 Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

Office Estimate NEW ENGLAND INFRASTRUCTURE INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

697.1 5.000 EA SILT SACK $250.00 $1,250.00 $500.00 $2,500.00

701. 30.000 SY CEMENT CONCRETE SIDEWALK $110.00 $3,300.00 $180.00 $5,400.00

701.2 15.000 SY CEMENT CONCRETE PEDESTRIAN CURB RAMP $150.00 $2,250.00 $240.00 $3,600.00

722.3 1.000 LS SCHEDULE OF OPERATIONS (TYPE C) - FIXED

PRICE $9,500

$9,500.00 $9,500.00 $9,500.00 $9,500.00

740. 18.000 MO ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE

A)

$3,450.00 $62,100.00 $3,000.00 $54,000.00

748. 1.000 LS MOBILIZATION $52,805.00 $52,805.00 $70,000.00 $70,000.00

767.6 3.000 CY AGED PINE BARK MULCH $75.00 $225.00 $200.00 $600.00

804.2 40.000 FT 2 INCH ELECTRICAL CONDUIT TYPE NM - PLASTIC

(UL)

$65.00 $2,600.00 $35.00 $1,400.00

811.22 1.000 EA ELECTRIC HANDHOLE - SD2.022 $2,400.00 $2,400.00 $3,000.00 $3,000.00

811.31 1.000 EA PULL BOX 12 X 12 INCHES - SD2.031 $2,000.00 $2,000.00 $700.00 $700.00

811.35 2.000 EA PULL BOX ADJUSTED $650.00 $1,300.00 $300.00 $600.00

812.13 1.000 EA LIGHT STANDARD FOUNDATION SD3.013 $3,500.00 $3,500.00 $5,200.00 $5,200.00

812.31 1.000 EA PEDESTAL SIGNAL POST FOUNDATION SD3.031 $2,250.00 $2,250.00 $2,400.00 $2,400.00

816. 1.000 LS TRAFFIC SIGNAL REMOVED AND RESET $4,000.00 $4,000.00 $7,700.00 $7,700.00

821.13 1.000 EA HIGHWAY LIGHTING POLE (ANCHOR BASE) 10 FOOT

BRACKET

$11,500.00 $11,500.00 $8,400.00 $8,400.00

823.111 1.000 EA HIGHWAY LIGHTING LUMINAIRE - TYPE 3, 60F, 139W

LED

$5,000.00 $5,000.00 $1,700.00 $1,700.00

823.71 1.000 EA HIGHWAY LIGHTING POLE AND LUMINAIRE

REMOVED AND STACKED

$2,500.00 $2,500.00 $1,600.00 $1,600.00

832. 20.000 SF WARNING-REGULATORY AND ROUTE MARKER -

ALUMINUM PANEL (TYPE A)

$25.00 $500.00 $16.00 $320.00

850.41 25.000 HR ROADWAY FLAGGER $90.00 $2,250.00 $90.00 $2,250.00

851.1 110.000 DAY TRAFFIC CONES FOR TRAFFIC MANAGEMENT $200.00 $22,000.00 $150.00 $16,500.00

852. 1,900.000 SF SAFETY SIGNING FOR TRAFFIC MANAGEMENT $22.00 $41,800.00 $30.00 $57,000.00

853.1 10.000 EA PORTABLE BREAKAWAY BARRICADE TYPE III $200.00 $2,000.00 $150.00 $1,500.00

853.2 250.000 FT TEMPORARY BARRIER (TL-2) $50.00 $12,500.00 $95.00 $23,750.00

853.403 320.000 DAY TRUCK MOUNTED ATTENUATOR $250.00 $80,000.00 $150.00 $48,000.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 2 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

Office Estimate NEW ENGLAND INFRASTRUCTURE INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

853.8 110.000 DAY TEMPORARY ILLUMINATION FOR WORK ZONE $200.00 $22,000.00 $150.00 $16,500.00

854.016 625.000 FT TEMPORARY PAVING MARKINGS - 6 INCH

(PAINTED)

$0.85 $531.25 $1.00 $625.00

854.036 30.000 FT TEMPORARY PAVING MARKINGS - 6 INCH (TAPE) $2.25 $67.50 $12.00 $360.00

854.1 170.000 SF PAVEMENT MARKING REMOVAL $3.50 $595.00 $9.00 $1,530.00

854.6 210.000 DAY TEMPORARY PORTABLE RUMBLE STRIP $30.00 $6,300.00 $30.00 $6,300.00

856.096 150.000 DAY ARROW BOARD (TYPE C) $14.00 $2,100.00 $20.00 $3,000.00

856.12 150.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN $25.00 $3,750.00 $30.00 $4,500.00

859. 825.000 DAY REFLECTORIZED DRUM $0.45 $371.25 $1.00 $825.00

859.1 180.000 DAY REFLECTORIZED DRUMS WITH SEQUENTIAL

FLASHING WARNING LIGHTS

$5.00 $900.00 $10.00 $1,800.00

862.506 475.000 FT 6-IN. RECESSED WHITE LINE (MC, FD, WR) $4.50 $2,137.50 $12.00 $5,700.00

862.512 355.000 FT 12-IN. RECESSED WHITE LINE (MC, FD, WR) $10.00 $3,550.00 $19.00 $6,745.00

863.506 240.000 FT 6-IN. RECESSED YELLOW LINE (MC, FD, WR) $5.00 $1,200.00 $12.00 $2,880.00

863.512 160.000 FT 12-IN. RECESSED YELLOW LINE (MC, FD, WR) $10.00 $1,600.00 $19.00 $3,040.00

864.11 3.000 EA LEGENDS (PF) $625.00 $1,875.00 $600.00 $1,800.00

864.13 3.000 EA ARROWS (PF) $500.00 $1,500.00 $500.00 $1,500.00

874.2 4.000 EA TRAFFIC SIGN REMOVED AND RESET $300.00 $1,200.00 $400.00 $1,600.00

901.3 2.000 CY 4000 PSI, 1.5 INCH, 565 CEMENT CONCRETE FOR

POST FOUNDATION

$1,000.00 $2,000.00 $1,900.00 $3,800.00

961.2 2,750.000 SF CLEAN (FULL REMOVAL) AND PAINT STRUCTURAL

STEEL

$175.00 $481,250.00 $180.00 $495,000.00

971.2 160.000 FT MODIFIED ASPHALTIC BRIDGE JOINT SYSTEM $365.00 $58,400.00 $350.00 $56,000.00

992.11 1.000 LS ALTERATION TO BRIDGE STRUCTURE NO. F-02-065

(3XJ)

$511,000.00 $511,000.00 $588,260.00 $588,260.00

994.1 1,800.000 SF TEMPORARY PROTECTIVE SHIELDING $15.00 $27,000.00 $15.00 $27,000.00

Total : $1,884,510.00 Total : $2,385,000.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 3 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

SW CONSTRUCTION ENTERPRISES LLC NEL CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

107.18 1,450.000 LB MISCELLANEOUS STRUCTURAL STEEL $56.00 $81,200.00 $58.00 $84,100.00

114.11 1.000 LS PARTIAL DEMOLITION OF SUPERSTRUCTURE OF

BRIDGE NO. F-02-065 (3XJ)

$230,000.00 $230,000.00 $520,105.00 $520,105.00

120.1 65.000 CY UNCLASSIFIED EXCAVATION $100.00 $6,500.00 $139.00 $9,035.00

141.1 8.000 CY TEST PIT FOR EXPLORATION $1,000.00 $8,000.00 $250.00 $2,000.00

151.01 30.000 CY GRAVEL BORROW - TYPE C $100.00 $3,000.00 $67.00 $2,010.00

170. 40.000 SY FINE GRADING AND COMPACTING - SUBGRADE

AREA

$100.00 $4,000.00 $23.00 $920.00

220. 2.000 EA DRAINAGE STRUCTURE ADJUSTED $2,000.00 $4,000.00 $1,265.00 $2,530.00

415.4 1,325.000 SY BRIDGE PAVEMENT MILLING $40.00 $53,000.00 $22.00 $29,150.00

450.60 115.000 TON SUPERPAVE BRIDGE SURFACE COURSE - 9.5 (SSC-

B - 9.5)

$600.00 $69,000.00 $439.00 $50,485.00

451. 35.000 TON HMA FOR PATCHING $500.00 $17,500.00 $354.00 $12,390.00

452. 105.000 GAL ASPHALT EMULSION FOR TACK COAT $6.00 $630.00 $8.00 $840.00

453. 885.000 FT HMA JOINT ADHESIVE $4.00 $3,540.00 $2.28 $2,017.80

472. 45.000 TON TEMPORARY ASPHALT PATCHING $1,000.00 $45,000.00 $301.00 $13,545.00

503. 25.000 FT GRANITE CURB TYPE VA3 - STRAIGHT $75.00 $1,875.00 $94.00 $2,350.00

503.1 6.000 FT GRANITE CURB TYPE VA3 - CURVED $200.00 $1,200.00 $115.00 $690.00

507. 2.000 EA GRANITE TRANSITION CURB - SLOPED TO

VERTICAL - STRAIGHT

$300.00 $600.00 $1,134.00 $2,268.00

509.1 18.000 FT GRANITE TRANSITION CURB FOR PEDESTRIAN

CURB RAMPS - CURVED

$200.00 $3,600.00 $138.00 $2,484.00

594. 55.000 FT CURB REMOVED AND DISCARDED $11.00 $605.00 $30.00 $1,650.00

628.304 1.000 EA TEMPORARY IMPACT ATTENUATOR, NON-

REDIRECTIVE, TL-2

$10,000.00 $10,000.00 $9,921.00 $9,921.00

645.072 200.000 FT 72 INCH CHAIN LINK FENCE (PIPE TOP RAIL) (LINE

POST OPTION)

$60.00 $12,000.00 $46.00 $9,200.00

652.072 1.000 EA 72 INCH CHAIN LINK FENCE END POST $500.00 $500.00 $251.00 $251.00

653.072 2.000 EA 72 INCH CHAIN LINK FENCE CORNER OR

INTERMEDIATE BRACE POST

$500.00 $1,000.00 $274.00 $548.00

657. 85.000 FT TEMPORARY FENCE $30.00 $2,550.00 $25.00 $2,125.00

669.1 215.000 FT FENCE REMOVED AND DISCARDED $20.00 $4,300.00 $9.00 $1,935.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 4 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

SW CONSTRUCTION ENTERPRISES LLC NEL CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

697.1 5.000 EA SILT SACK $100.00 $500.00 $307.00 $1,535.00

701. 30.000 SY CEMENT CONCRETE SIDEWALK $500.00 $15,000.00 $189.00 $5,670.00

701.2 15.000 SY CEMENT CONCRETE PEDESTRIAN CURB RAMP $200.00 $3,000.00 $224.00 $3,360.00

722.3 1.000 LS SCHEDULE OF OPERATIONS (TYPE C) - FIXED

PRICE $9,500

$9,500.00 $9,500.00 $9,500.00 $9,500.00

740. 18.000 MO ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE

A)

$4,000.00 $72,000.00 $3,114.00 $56,052.00

748. 1.000 LS MOBILIZATION $100,000.00 $100,000.00 $73,613.00 $73,613.00

767.6 3.000 CY AGED PINE BARK MULCH $100.00 $300.00 $164.00 $492.00

804.2 40.000 FT 2 INCH ELECTRICAL CONDUIT TYPE NM - PLASTIC

(UL)

$70.00 $2,800.00 $62.00 $2,480.00

811.22 1.000 EA ELECTRIC HANDHOLE - SD2.022 $5,000.00 $5,000.00 $2,222.00 $2,222.00

811.31 1.000 EA PULL BOX 12 X 12 INCHES - SD2.031 $5,000.00 $5,000.00 $1,751.00 $1,751.00

811.35 2.000 EA PULL BOX ADJUSTED $2,500.00 $5,000.00 $478.00 $956.00

812.13 1.000 EA LIGHT STANDARD FOUNDATION SD3.013 $5,000.00 $5,000.00 $4,025.00 $4,025.00

812.31 1.000 EA PEDESTAL SIGNAL POST FOUNDATION SD3.031 $5,000.00 $5,000.00 $2,429.00 $2,429.00

816. 1.000 LS TRAFFIC SIGNAL REMOVED AND RESET $7,000.00 $7,000.00 $7,820.00 $7,820.00

821.13 1.000 EA HIGHWAY LIGHTING POLE (ANCHOR BASE) 10 FOOT

BRACKET

$7,000.00 $7,000.00 $7,342.00 $7,342.00

823.111 1.000 EA HIGHWAY LIGHTING LUMINAIRE - TYPE 3, 60F, 139W

LED

$2,000.00 $2,000.00 $1,564.00 $1,564.00

823.71 1.000 EA HIGHWAY LIGHTING POLE AND LUMINAIRE

REMOVED AND STACKED

$2,000.00 $2,000.00 $1,414.00 $1,414.00

832. 20.000 SF WARNING-REGULATORY AND ROUTE MARKER -

ALUMINUM PANEL (TYPE A)

$90.00 $1,800.00 $56.00 $1,120.00

850.41 25.000 HR ROADWAY FLAGGER $100.00 $2,500.00 $88.00 $2,200.00

851.1 110.000 DAY TRAFFIC CONES FOR TRAFFIC MANAGEMENT $150.00 $16,500.00 $250.00 $27,500.00

852. 1,900.000 SF SAFETY SIGNING FOR TRAFFIC MANAGEMENT $25.00 $47,500.00 $22.50 $42,750.00

853.1 10.000 EA PORTABLE BREAKAWAY BARRICADE TYPE III $300.00 $3,000.00 $216.00 $2,160.00

853.2 250.000 FT TEMPORARY BARRIER (TL-2) $100.00 $25,000.00 $85.00 $21,250.00

853.403 320.000 DAY TRUCK MOUNTED ATTENUATOR $250.00 $80,000.00 $150.00 $48,000.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 5 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

SW CONSTRUCTION ENTERPRISES LLC NEL CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

853.8 110.000 DAY TEMPORARY ILLUMINATION FOR WORK ZONE $300.00 $33,000.00 $30.00 $3,300.00

854.016 625.000 FT TEMPORARY PAVING MARKINGS - 6 INCH

(PAINTED)

$6.00 $3,750.00 $2.00 $1,250.00

854.036 30.000 FT TEMPORARY PAVING MARKINGS - 6 INCH (TAPE) $50.00 $1,500.00 $8.00 $240.00

854.1 170.000 SF PAVEMENT MARKING REMOVAL $5.00 $850.00 $8.50 $1,445.00

854.6 210.000 DAY TEMPORARY PORTABLE RUMBLE STRIP $50.00 $10,500.00 $5.00 $1,050.00

856.096 150.000 DAY ARROW BOARD (TYPE C) $100.00 $15,000.00 $29.00 $4,350.00

856.12 150.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN $85.00 $12,750.00 $23.00 $3,450.00

859. 825.000 DAY REFLECTORIZED DRUM $50.00 $41,250.00 $1.00 $825.00

859.1 180.000 DAY REFLECTORIZED DRUMS WITH SEQUENTIAL

FLASHING WARNING LIGHTS

$100.00 $18,000.00 $16.00 $2,880.00

862.506 475.000 FT 6-IN. RECESSED WHITE LINE (MC, FD, WR) $9.00 $4,275.00 $2.80 $1,330.00

862.512 355.000 FT 12-IN. RECESSED WHITE LINE (MC, FD, WR) $12.00 $4,260.00 $11.34 $4,025.70

863.506 240.000 FT 6-IN. RECESSED YELLOW LINE (MC, FD, WR) $9.00 $2,160.00 $2.80 $672.00

863.512 160.000 FT 12-IN. RECESSED YELLOW LINE (MC, FD, WR) $12.00 $1,920.00 $11.34 $1,814.40

864.11 3.000 EA LEGENDS (PF) $500.00 $1,500.00 $556.00 $1,668.00

864.13 3.000 EA ARROWS (PF) $500.00 $1,500.00 $391.00 $1,173.00

874.2 4.000 EA TRAFFIC SIGN REMOVED AND RESET $500.00 $2,000.00 $622.00 $2,488.00

901.3 2.000 CY 4000 PSI, 1.5 INCH, 565 CEMENT CONCRETE FOR

POST FOUNDATION

$4,000.00 $8,000.00 $564.00 $1,128.00

961.2 2,750.000 SF CLEAN (FULL REMOVAL) AND PAINT STRUCTURAL

STEEL

$170.00 $467,500.00 $171.00 $470,250.00

971.2 160.000 FT MODIFIED ASPHALTIC BRIDGE JOINT SYSTEM $310.00 $49,600.00 $317.00 $50,720.00

992.11 1.000 LS ALTERATION TO BRIDGE STRUCTURE NO. F-02-065

(3XJ)

$700,000.00 $700,000.00 $795,932.00 $795,932.00

994.1 1,800.000 SF TEMPORARY PROTECTIVE SHIELDING $50.00 $90,000.00 $16.00 $28,800.00

Total : $2,455,315.00 Total : $2,468,545.90

CMS105 - Report Date: 7/28/2026 2:23 PM Page 6 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

MIG CORPORATION SPS NEW ENGLAND INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

107.18 1,450.000 LB MISCELLANEOUS STRUCTURAL STEEL $55.00 $79,750.00 $45.00 $65,250.00

114.11 1.000 LS PARTIAL DEMOLITION OF SUPERSTRUCTURE OF

BRIDGE NO. F-02-065 (3XJ)

$602,400.00 $602,400.00 $600,000.00 $600,000.00

120.1 65.000 CY UNCLASSIFIED EXCAVATION $188.00 $12,220.00 $420.00 $27,300.00

141.1 8.000 CY TEST PIT FOR EXPLORATION $333.00 $2,664.00 $650.00 $5,200.00

151.01 30.000 CY GRAVEL BORROW - TYPE C $144.00 $4,320.00 $285.00 $8,550.00

170. 40.000 SY FINE GRADING AND COMPACTING - SUBGRADE

AREA

$15.00 $600.00 $8.00 $320.00

220. 2.000 EA DRAINAGE STRUCTURE ADJUSTED $1,220.00 $2,440.00 $1,200.00 $2,400.00

415.4 1,325.000 SY BRIDGE PAVEMENT MILLING $31.00 $41,075.00 $20.00 $26,500.00

450.60 115.000 TON SUPERPAVE BRIDGE SURFACE COURSE - 9.5 (SSC-

B - 9.5)

$485.00 $55,775.00 $450.00 $51,750.00

451. 35.000 TON HMA FOR PATCHING $455.00 $15,925.00 $425.00 $14,875.00

452. 105.000 GAL ASPHALT EMULSION FOR TACK COAT $28.00 $2,940.00 $10.00 $1,050.00

453. 885.000 FT HMA JOINT ADHESIVE $5.00 $4,425.00 $1.50 $1,327.50

472. 45.000 TON TEMPORARY ASPHALT PATCHING $455.00 $20,475.00 $300.00 $13,500.00

503. 25.000 FT GRANITE CURB TYPE VA3 - STRAIGHT $125.00 $3,125.00 $200.00 $5,000.00

503.1 6.000 FT GRANITE CURB TYPE VA3 - CURVED $155.00 $930.00 $225.00 $1,350.00

507. 2.000 EA GRANITE TRANSITION CURB - SLOPED TO

VERTICAL - STRAIGHT

$822.00 $1,644.00 $1,700.00 $3,400.00

509.1 18.000 FT GRANITE TRANSITION CURB FOR PEDESTRIAN

CURB RAMPS - CURVED

$135.00 $2,430.00 $225.00 $4,050.00

594. 55.000 FT CURB REMOVED AND DISCARDED $30.00 $1,650.00 $35.00 $1,925.00

628.304 1.000 EA TEMPORARY IMPACT ATTENUATOR, NON-

REDIRECTIVE, TL-2

$8,500.00 $8,500.00 $10,500.00 $10,500.00

645.072 200.000 FT 72 INCH CHAIN LINK FENCE (PIPE TOP RAIL) (LINE

POST OPTION)

$55.00 $11,000.00 $120.00 $24,000.00

652.072 1.000 EA 72 INCH CHAIN LINK FENCE END POST $275.00 $275.00 $580.00 $580.00

653.072 2.000 EA 72 INCH CHAIN LINK FENCE CORNER OR

INTERMEDIATE BRACE POST

$300.00 $600.00 $750.00 $1,500.00

657. 85.000 FT TEMPORARY FENCE $35.00 $2,975.00 $60.00 $5,100.00

669.1 215.000 FT FENCE REMOVED AND DISCARDED $10.00 $2,150.00 $20.00 $4,300.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 7 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

MIG CORPORATION SPS NEW ENGLAND INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

697.1 5.000 EA SILT SACK $335.00 $1,675.00 $300.00 $1,500.00

701. 30.000 SY CEMENT CONCRETE SIDEWALK $77.00 $2,310.00 $300.00 $9,000.00

701.2 15.000 SY CEMENT CONCRETE PEDESTRIAN CURB RAMP $135.00 $2,025.00 $375.00 $5,625.00

722.3 1.000 LS SCHEDULE OF OPERATIONS (TYPE C) - FIXED

PRICE $9,500

$9,500.00 $9,500.00 $9,500.00 $9,500.00

740. 18.000 MO ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE

A)

$4,222.00 $75,996.00 $4,800.00 $86,400.00

748. 1.000 LS MOBILIZATION $83,000.00 $83,000.00 $75,000.00 $75,000.00

767.6 3.000 CY AGED PINE BARK MULCH $288.00 $864.00 $400.00 $1,200.00

804.2 40.000 FT 2 INCH ELECTRICAL CONDUIT TYPE NM - PLASTIC

(UL)

$140.00 $5,600.00 $35.00 $1,400.00

811.22 1.000 EA ELECTRIC HANDHOLE - SD2.022 $3,030.00 $3,030.00 $1,600.00 $1,600.00

811.31 1.000 EA PULL BOX 12 X 12 INCHES - SD2.031 $1,955.00 $1,955.00 $1,600.00 $1,600.00

811.35 2.000 EA PULL BOX ADJUSTED $444.00 $888.00 $800.00 $1,600.00

812.13 1.000 EA LIGHT STANDARD FOUNDATION SD3.013 $6,440.00 $6,440.00 $5,000.00 $5,000.00

812.31 1.000 EA PEDESTAL SIGNAL POST FOUNDATION SD3.031 $2,885.00 $2,885.00 $2,500.00 $2,500.00

816. 1.000 LS TRAFFIC SIGNAL REMOVED AND RESET $7,550.00 $7,550.00 $8,000.00 $8,000.00

821.13 1.000 EA HIGHWAY LIGHTING POLE (ANCHOR BASE) 10 FOOT

BRACKET

$8,220.00 $8,220.00 $8,000.00 $8,000.00

823.111 1.000 EA HIGHWAY LIGHTING LUMINAIRE - TYPE 3, 60F, 139W

LED

$1,557.00 $1,557.00 $2,500.00 $2,500.00

823.71 1.000 EA HIGHWAY LIGHTING POLE AND LUMINAIRE

REMOVED AND STACKED

$1,440.00 $1,440.00 $800.00 $800.00

832. 20.000 SF WARNING-REGULATORY AND ROUTE MARKER -

ALUMINUM PANEL (TYPE A)

$62.00 $1,240.00 $65.00 $1,300.00

850.41 25.000 HR ROADWAY FLAGGER $80.00 $2,000.00 $150.00 $3,750.00

851.1 110.000 DAY TRAFFIC CONES FOR TRAFFIC MANAGEMENT $2,555.00 $281,050.00 $1,000.00 $110,000.00

852. 1,900.000 SF SAFETY SIGNING FOR TRAFFIC MANAGEMENT $30.00 $57,000.00 $45.00 $85,500.00

853.1 10.000 EA PORTABLE BREAKAWAY BARRICADE TYPE III $180.00 $1,800.00 $300.00 $3,000.00

853.2 250.000 FT TEMPORARY BARRIER (TL-2) $72.00 $18,000.00 $150.00 $37,500.00

853.403 320.000 DAY TRUCK MOUNTED ATTENUATOR $163.00 $52,160.00 $200.00 $64,000.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 8 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

MIG CORPORATION SPS NEW ENGLAND INC

Item # Quantity Units Description Unit Price Amount Unit Price Amount

853.8 110.000 DAY TEMPORARY ILLUMINATION FOR WORK ZONE $55.00 $6,050.00 $20.00 $2,200.00

854.016 625.000 FT TEMPORARY PAVING MARKINGS - 6 INCH

(PAINTED)

$3.25 $2,031.25 $2.50 $1,562.50

854.036 30.000 FT TEMPORARY PAVING MARKINGS - 6 INCH (TAPE) $5.00 $150.00 $10.00 $300.00

854.1 170.000 SF PAVEMENT MARKING REMOVAL $3.75 $637.50 $6.00 $1,020.00

854.6 210.000 DAY TEMPORARY PORTABLE RUMBLE STRIP $5.00 $1,050.00 $50.00 $10,500.00

856.096 150.000 DAY ARROW BOARD (TYPE C) $50.00 $7,500.00 $12.00 $1,800.00

856.12 150.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN $27.00 $4,050.00 $50.00 $7,500.00

859. 825.000 DAY REFLECTORIZED DRUM $0.50 $412.50 $1.00 $825.00

859.1 180.000 DAY REFLECTORIZED DRUMS WITH SEQUENTIAL

FLASHING WARNING LIGHTS

$6.00 $1,080.00 $6.00 $1,080.00

862.506 475.000 FT 6-IN. RECESSED WHITE LINE (MC, FD, WR) $8.00 $3,800.00 $4.00 $1,900.00

862.512 355.000 FT 12-IN. RECESSED WHITE LINE (MC, FD, WR) $12.00 $4,260.00 $12.00 $4,260.00

863.506 240.000 FT 6-IN. RECESSED YELLOW LINE (MC, FD, WR) $8.00 $1,920.00 $4.00 $960.00

863.512 160.000 FT 12-IN. RECESSED YELLOW LINE (MC, FD, WR) $12.00 $1,920.00 $12.00 $1,920.00

864.11 3.000 EA LEGENDS (PF) $388.00 $1,164.00 $775.00 $2,325.00

864.13 3.000 EA ARROWS (PF) $288.00 $864.00 $550.00 $1,650.00

874.2 4.000 EA TRAFFIC SIGN REMOVED AND RESET $313.00 $1,252.00 $475.00 $1,900.00

901.3 2.000 CY 4000 PSI, 1.5 INCH, 565 CEMENT CONCRETE FOR

POST FOUNDATION

$655.00 $1,310.00 $1,500.00 $3,000.00

961.2 2,750.000 SF CLEAN (FULL REMOVAL) AND PAINT STRUCTURAL

STEEL

$198.00 $544,500.00 $325.00 $893,750.00

971.2 160.000 FT MODIFIED ASPHALTIC BRIDGE JOINT SYSTEM $364.00 $58,240.00 $425.00 $68,000.00

992.11 1.000 LS ALTERATION TO BRIDGE STRUCTURE NO. F-02-065

(3XJ)

$617,500.00 $617,500.00 $800,000.00 $800,000.00

994.1 1,800.000 SF TEMPORARY PROTECTIVE SHIELDING $33.00 $59,400.00 $55.00 $99,000.00

Total : $2,827,564.25 Total : $3,311,455.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 9 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

AETNA BRIDGE COMPANY S&R CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

107.18 1,450.000 LB MISCELLANEOUS STRUCTURAL STEEL $60.00 $87,000.00 $123.00 $178,350.00

114.11 1.000 LS PARTIAL DEMOLITION OF SUPERSTRUCTURE OF

BRIDGE NO. F-02-065 (3XJ)

$900,000.00 $900,000.00 $413,450.00 $413,450.00

120.1 65.000 CY UNCLASSIFIED EXCAVATION $100.00 $6,500.00 $62.00 $4,030.00

141.1 8.000 CY TEST PIT FOR EXPLORATION $250.00 $2,000.00 $165.00 $1,320.00

151.01 30.000 CY GRAVEL BORROW - TYPE C $150.00 $4,500.00 $75.00 $2,250.00

170. 40.000 SY FINE GRADING AND COMPACTING - SUBGRADE

AREA

$25.00 $1,000.00 $10.00 $400.00

220. 2.000 EA DRAINAGE STRUCTURE ADJUSTED $1,200.00 $2,400.00 $760.00 $1,520.00

415.4 1,325.000 SY BRIDGE PAVEMENT MILLING $20.00 $26,500.00 $33.00 $43,725.00

450.60 115.000 TON SUPERPAVE BRIDGE SURFACE COURSE - 9.5 (SSC-

B - 9.5)

$400.00 $46,000.00 $725.00 $83,375.00

451. 35.000 TON HMA FOR PATCHING $600.00 $21,000.00 $230.00 $8,050.00

452. 105.000 GAL ASPHALT EMULSION FOR TACK COAT $24.00 $2,520.00 $25.00 $2,625.00

453. 885.000 FT HMA JOINT ADHESIVE $5.00 $4,425.00 $3.50 $3,097.50

472. 45.000 TON TEMPORARY ASPHALT PATCHING $600.00 $27,000.00 $230.00 $10,350.00

503. 25.000 FT GRANITE CURB TYPE VA3 - STRAIGHT $100.00 $2,500.00 $73.00 $1,825.00

503.1 6.000 FT GRANITE CURB TYPE VA3 - CURVED $150.00 $900.00 $77.00 $462.00

507. 2.000 EA GRANITE TRANSITION CURB - SLOPED TO

VERTICAL - STRAIGHT

$500.00 $1,000.00 $350.00 $700.00

509.1 18.000 FT GRANITE TRANSITION CURB FOR PEDESTRIAN

CURB RAMPS - CURVED

$150.00 $2,700.00 $81.00 $1,458.00

594. 55.000 FT CURB REMOVED AND DISCARDED $20.00 $1,100.00 $7.50 $412.50

628.304 1.000 EA TEMPORARY IMPACT ATTENUATOR, NON-

REDIRECTIVE, TL-2

$2,500.00 $2,500.00 $14,000.00 $14,000.00

645.072 200.000 FT 72 INCH CHAIN LINK FENCE (PIPE TOP RAIL) (LINE

POST OPTION)

$40.00 $8,000.00 $76.00 $15,200.00

652.072 1.000 EA 72 INCH CHAIN LINK FENCE END POST $220.00 $220.00 $365.00 $365.00

653.072 2.000 EA 72 INCH CHAIN LINK FENCE CORNER OR

INTERMEDIATE BRACE POST

$240.00 $480.00 $485.00 $970.00

657. 85.000 FT TEMPORARY FENCE $22.00 $1,870.00 $40.00 $3,400.00

669.1 215.000 FT FENCE REMOVED AND DISCARDED $8.00 $1,720.00 $12.00 $2,580.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 10 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

AETNA BRIDGE COMPANY S&R CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

697.1 5.000 EA SILT SACK $300.00 $1,500.00 $190.00 $950.00

701. 30.000 SY CEMENT CONCRETE SIDEWALK $150.00 $4,500.00 $98.00 $2,940.00

701.2 15.000 SY CEMENT CONCRETE PEDESTRIAN CURB RAMP $250.00 $3,750.00 $117.00 $1,755.00

722.3 1.000 LS SCHEDULE OF OPERATIONS (TYPE C) - FIXED

PRICE $9,500

$9,500.00 $9,500.00 $9,500.00 $9,500.00

740. 18.000 MO ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE

A)

$4,000.00 $72,000.00 $3,500.00 $63,000.00

748. 1.000 LS MOBILIZATION $100,000.00 $100,000.00 $105,000.00 $105,000.00

767.6 3.000 CY AGED PINE BARK MULCH $250.00 $750.00 $100.00 $300.00

804.2 40.000 FT 2 INCH ELECTRICAL CONDUIT TYPE NM - PLASTIC

(UL)

$100.00 $4,000.00 $81.00 $3,240.00

811.22 1.000 EA ELECTRIC HANDHOLE - SD2.022 $3,000.00 $3,000.00 $675.00 $675.00

811.31 1.000 EA PULL BOX 12 X 12 INCHES - SD2.031 $2,000.00 $2,000.00 $420.00 $420.00

811.35 2.000 EA PULL BOX ADJUSTED $500.00 $1,000.00 $310.00 $620.00

812.13 1.000 EA LIGHT STANDARD FOUNDATION SD3.013 $5,000.00 $5,000.00 $2,155.00 $2,155.00

812.31 1.000 EA PEDESTAL SIGNAL POST FOUNDATION SD3.031 $4,000.00 $4,000.00 $15,500.00 $15,500.00

816. 1.000 LS TRAFFIC SIGNAL REMOVED AND RESET $20,000.00 $20,000.00 $10,000.00 $10,000.00

821.13 1.000 EA HIGHWAY LIGHTING POLE (ANCHOR BASE) 10 FOOT

BRACKET

$7,000.00 $7,000.00 $7,500.00 $7,500.00

823.111 1.000 EA HIGHWAY LIGHTING LUMINAIRE - TYPE 3, 60F, 139W

LED

$1,500.00 $1,500.00 $1,500.00 $1,500.00

823.71 1.000 EA HIGHWAY LIGHTING POLE AND LUMINAIRE

REMOVED AND STACKED

$1,500.00 $1,500.00 $3,500.00 $3,500.00

832. 20.000 SF WARNING-REGULATORY AND ROUTE MARKER -

ALUMINUM PANEL (TYPE A)

$20.00 $400.00 $25.00 $500.00

850.41 25.000 HR ROADWAY FLAGGER $80.00 $2,000.00 $48.00 $1,200.00

851.1 110.000 DAY TRAFFIC CONES FOR TRAFFIC MANAGEMENT $800.00 $88,000.00 $722.00 $79,420.00

852. 1,900.000 SF SAFETY SIGNING FOR TRAFFIC MANAGEMENT $35.00 $66,500.00 $45.00 $85,500.00

853.1 10.000 EA PORTABLE BREAKAWAY BARRICADE TYPE III $100.00 $1,000.00 $195.00 $1,950.00

853.2 250.000 FT TEMPORARY BARRIER (TL-2) $50.00 $12,500.00 $170.00 $42,500.00

853.403 320.000 DAY TRUCK MOUNTED ATTENUATOR $450.00 $144,000.00 $390.00 $124,800.00

CMS105 - Report Date: 7/28/2026 2:23 PM Page 11 of 12

Location : FALL RIVER Contract # : 134822 District : 5 Description : FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195

AETNA BRIDGE COMPANY S&R CORPORATION

Item # Quantity Units Description Unit Price Amount Unit Price Amount

853.8 110.000 DAY TEMPORARY ILLUMINATION FOR WORK ZONE $200.00 $22,000.00 $520.00 $57,200.00

854.016 625.000 FT TEMPORARY PAVING MARKINGS - 6 INCH

(PAINTED)

$2.00 $1,250.00 $2.00 $1,250.00

854.036 30.000 FT TEMPORARY PAVING MARKINGS - 6 INCH (TAPE) $10.00 $300.00 $3.00 $90.00

854.1 170.000 SF PAVEMENT MARKING REMOVAL $10.00 $1,700.00 $8.00 $1,360.00

854.6 210.000 DAY TEMPORARY PORTABLE RUMBLE STRIP $100.00 $21,000.00 $1,250.24 $262,550.40

856.096 150.000 DAY ARROW BOARD (TYPE C) $40.00 $6,000.00 $35.00 $5,250.00

856.12 150.000 DAY PORTABLE CHANGEABLE MESSAGE SIGN $40.00 $6,000.00 $40.00 $6,000.00

859. 825.000 DAY REFLECTORIZED DRUM $1.00 $825.00 $5.00 $4,125.00

859.1 180.000 DAY REFLECTORIZED DRUMS WITH SEQUENTIAL

FLASHING WARNING LIGHTS

$3.00 $540.00 $10.00 $1,800.00

862.506 475.000 FT 6-IN. RECESSED WHITE LINE (MC, FD, WR) $10.00 $4,750.00 $14.00 $6,650.00

862.512 355.000 FT 12-IN. RECESSED WHITE LINE (MC, FD, WR) $20.00 $7,100.00 $24.00 $8,520.00

863.506 240.000 FT 6-IN. RECESSED YELLOW LINE (MC, FD, WR) $10.00 $2,400.00 $14.00 $3,360.00

863.512 160.000 FT 12-IN. RECESSED YELLOW LINE (MC, FD, WR) $20.00 $3,200.00 $20.00 $3,200.00

864.11 3.000 EA LEGENDS (PF) $500.00 $1,500.00 $700.00 $2,100.00

864.13 3.000 EA ARROWS (PF) $400.00 $1,200.00 $600.00 $1,800.00

874.2 4.000 EA TRAFFIC SIGN REMOVED AND RESET $200.00 $800.00 $225.00 $900.00

901.3 2.000 CY 4000 PSI, 1.5 INCH, 565 CEMENT CONCRETE FOR

POST FOUNDATION

$500.00 $1,000.00 $4,070.00 $8,140.00

961.2 2,750.000 SF CLEAN (FULL REMOVAL) AND PAINT STRUCTURAL

STEEL

$200.00 $550,000.00 $390.00 $1,072,500.00

971.2 160.000 FT MODIFIED ASPHALTIC BRIDGE JOINT SYSTEM $350.00 $56,000.00 $445.00 $71,200.00

992.11 1.000 LS ALTERATION TO BRIDGE STRUCTURE NO. F-02-065

(3XJ)

$907,000.00 $907,000.00 $805,000.00 $805,000.00

994.1 1,800.000 SF TEMPORARY PROTECTIVE SHIELDING $50.00 $90,000.00 $25.00 $45,000.00

Total : $3,393,800.00 Total : $3,726,335.40