3c-Statement of Work.pdf

PDF 198 KB Posted

Download PDF, 198 KB

Attached to
UPDATE SOW**** USCG TRACEN PETALUMA MONTHLY BOILER MAINTENANCE
Solicitation number
61200PR270000061
Issued by
Not on record

About this file

This is a Statement of Work (SOW) for monthly boiler chemical testing services at the U.S. Coast Guard Training Center (TRACEN) Petaluma, located at 599 Tomales Road, Petaluma, California. The contract covers a two-year base period (January 1, 2027 through December 31, 2028) with four one-year option periods extending through December 31, 2032. The contractor must furnish all labor, tools, materials, equipment, supplies, vehicles, and services necessary to provide comprehensive boiler chemical testing, preventative water treatment, and scale/corrosion control on eleven hot water loops across multiple facility buildings.

The primary deliverables include five core tasks: (1) one monthly onsite service visit per calendar month to conduct testing, monitoring, and chemical servicing of all eleven boiler systems, including standard chemical testing of boiler water, feedwater, condensate, and closed loop systems, with access to an online portal for digital service reporting and data trending; (2) furnishing and applying scale and corrosion inhibitor chemical products, including supplemental corrosion inhibitors to treat system water loss up to 10% of total system capacity annually at no additional cost; (3) checking, cleaning, calibrating, and servicing all chemical control, dosing, and feeding equipment, including monitoring probes; (4) maintaining strict inventory control of chemical reserves and promptly removing and legally disposing of empty containers; and (5) providing certified laboratory analyses for diagnostic support, conducting chemical safety training for facility maintenance personnel, and participating in annual management reviews. The contractor must guarantee maintenance of current heating system efficiency and bears responsibility for cleaning affected systems at no additional cost if fouling or efficiency loss occurs due to chemical treatment failure. Work is generally performed Monday through Friday, 0800–1500 PST, except federal holidays, though occasional extended hours may be required. The contractor must furnish all facilities, materials, and equipment, with no government-furnished resources provided. Contractor employees must comply with all security, safety, and conduct requirements, including wearing valid identification badges at USCG facilities.

View the file

Other files

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR # 61200PR270000061

STATEMENT OF WORK

LAST UPDATED: 11/18/2026

STATEMENT OF WORK (SOW)

FOR

MONTHLY BOILER CHEMICAL TESTING

1.0 GENERAL

1.1 BACKGROUND

U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road Petaluma; CA 94952 is the Coast Guard’s largest West Coast Training Center. Our graduates are the latest chefs, medics, storekeepers, yeoman, information systems technicians, electronics technicians, operations specialists, and aviation survival technicians (AST). We are also home to the Coast Guard Leadership Development Center’s Chief Petty Officer Academy.

1.2 SCOPE

The requirement of this contract is for the contractor to furnish all labor, tools, materials, equipment, supplies, services, supervision, and all other items necessary to provide comprehensive boiler chemical testing, preventative water treatment, and scale/corrosion control on eleven (11) hot water loops located at USCG TRACEN Petaluma. The contractor is responsible for all phases of chemical water treatment, system monitoring, periodic inspections, inventory control, and waterside efficiency assurance.

1.3 OBJECTIVE

The service provider shall provide all labor, equipment, materials, vehicles, and appliances necessary to perform all operations in connection with routine water testing, scale and corrosion mitigation, equipment calibration, and chemical water treatment across facility heating loops at U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road, Petaluma, CA 94952-4154.

1.4 APPLICABLE DOCUMENTS

1.4.1 Reference Documents

The following documents may be helpful to the Contractor in performing the work described in this document:

• 29 CFR Part 1910 - Occupational Safety and Health Standards (General Industry)

• 29 CFR Part 1910.1200 - Hazard Communication Standard (Safety Data Sheets /

Chemical Safety)

• Federal Acquisition Regulation (FAR) 4.1103 - System for Award Management

2.0 SPECIFIC REQUIREMENTS/TASKS

2.1 TASK ONE. ROUTINE MONTHLY ONSITE SERVICE AND WATER TESTING

• Provide one (1) onsite service visit per calendar month to conduct testing, monitoring, and chemical servicing of eleven (11) hot water loops.

• Perform standard chemical testing on boiler water, feedwater, condensate, and closed loop systems (evaluating pH, conductivity, dissolved solids, inhibitor levels, and alkalinity).

• Provide and maintain access to an online portal for digital service reporting, data trending, and continuous operational logging.

Distasio, Amanda L CIV I bulleted this.

List of boilers locations:

Boiler Model Serial # Location

KN Series 10 0101423561 Steadman Hall Bldg. 550 KN Series 10 0101423560 Steadman Hall Bldg. 550 KN Series 4 0101423474 Facilities ENG Bldg. 160 KN Series 10 0101423559 Club Bldg. 134 KN Series 6 0101423558 Motor Pool Bldg. 170 KN Series 4 0101423473 Supply Bldg. 165 Lochinvar CHN0991 K10H00229967 Gym Bldg. 251 Lochinvar FTX400N 2019119201701 Theater Bldg. 261 KN Series 10 0101423563 Mace Hall Bldg. 130 Lochinvar CHL1801 C11H00231789 Upper Galley Bldg. 126 Lochinvar CHL1801 C11H00231788 Upper Galley Bldg. 126 Smith GS110-W-7-H GSS110-7-H-

080024 Housing Bldg. 408 (Outside)

2.2 TASK TWO. SCALE AND CORROSION INHIBITOR APPLICATION

• Furnish and apply chemical water treatment products engineered to retard scale and corrosion in the boilers.

• Furnish and apply corrosion inhibitor to closed hydronic loops should water loss occur from the systems.

• Provide supplemental corrosion inhibitors to treat system water loss up to a maximum volume of 10% total system capacity per calendar year at no additional cost to the Government.

2.3 TASK THREE. FEED EQUIPMENT CALIBRATION AND MAINTENANCE

• Check, clean, calibrate, and service all chemical control, dosing, and feeding equipment.

• Check, inspect, and verify the operational integrity of all associated water treatment control hardware and monitoring probes.

2.4 TASK FOUR. INVENTORY CONTROL AND CONTAINER DISPOSAL

• Maintain strict inventory control of all onsite chemical reserves, ensuring adequate supplies are always maintained.

• Promptly remove all empty chemical drums, containers, and packaging from Government property and dispose of them legally in full compliance with applicable environmental regulations.

2.5 TASK FIVE. LABORATORY ANALYSIS AND TECHNICAL SAFETY TRAINING

• Provide certified laboratory analyses for backup diagnostic support whenever anomalous conditions, severe contamination, or baseline verification is required.

• Conduct chemical safety and operational handling training for onsite USCG facility maintenance personnel.

• Participate in annual management reviews conducted at the discretion of TRACEN Petaluma facility engineering personnel.

• Guarantee that the present degree of operating efficiency of the heating systems will be maintained while under the contractor's program; should fouling or loss of efficiency occur as a result of chemical treatment failure, the contractor shall clean the affected systems at no additional cost to the Government.

3.0 CONTRACTOR PERSONNEL

3.1 QUALIFIED PERSONNEL

The Contractor shall provide qualified personnel to perform all requirements specified in this

SOW.

3.2 CONTINUITY OF SUPPORT

The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Government Technical Representative prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.

3.3 EMPLOYEE IDENTIFICATION

3.3.1 Contractor employees visiting Government facilities must wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times. Due to heightened security at USCG facilities, all contractor employees performing tasks related to this SOW shall have a valid Federal or State identification while onboard a Coast Guard facility. Vehicles shall have current registration and insurance, and drivers shall have a valid driver’s license. Time spent undergoing entrance screening to USCG facilities will not be considered a government delay of work or differing site condition.

3.4 EMPLOYEE CONDUCT

Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.

3.5 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS

The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.

Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.

4.0 OTHER APPLICABLE CONDITIONS

4.1 SECURITY

Contractor access to classified information is not currently required under this SOW.

4.2 PERIOD OF PERFORMANCE

The period of performance for this contract is a one-year base period with four one-year option periods as follows:

Base Period January 1, 2027 through December 31, 2028 Option Period One January 1, 2028 through December 31, 2029 Option Period Two January 1, 2029 through December 31, 2030 Option Period Three January 1, 2030 through December 31, 2031 Option Period Four January 1, 2031 through December 31, 2032

4.3 PLACE OF PERFORMANCE

The primary place of performance will be the United States Coast Guard TRACEN Petaluma located at 599 Tomales Road, Petaluma, CA 94952.

4.4 HOURS OF OPERATION

Contractor employees shall generally perform all work between the hours of 0800 and 1500 PST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.

4.5 TRAVEL

Contractor travel must not be required for this requirement.

4.6 GENERAL REPORT REQUIREMENTS

The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).

Additionally, the contractor must provide access to online reporting, data trending, and logs as described in Section 2.0.

5.0 GOVERNMENT FURNISHED RESOURCES

The Government will not furnish any resources to the Contractor in support of this contract.

6.0 CONTRACTOR FURNISHED PROPERTY

The Contractor shall Furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 5.0.

Distasio, Amanda L CIV I would take this out and put the standard verbiage in.

STATEMENT OF WORK (SOW)
FOR

File details come from the government source that posted it. Updated .