Statement of Work Summary

This is a Statement of Work for monthly boiler maintenance and chemical testing services at the U.S. Coast Guard Training Center (TRACEN) Petaluma located at 599 Tomales Road, Petaluma, California 94952. The contract requires comprehensive chemical water treatment, testing, and monitoring of eleven hot water loops, one steam boiler, and associated cooling tower systems. The contractor must furnish all labor, tools, materials, equipment, supplies, vehicles, and services necessary to perform these operations, with no Government-furnished resources provided except those specified in the SOW.

The statement of work consists of six primary tasks: (1) routine monthly onsite service visits including standard chemical testing of boiler water, feedwater, condensate, and closed-loop systems while maintaining an online portal for digital reporting and data trending; (2) furnishing and applying scale and corrosion inhibitor chemicals, with supplemental corrosion inhibitors provided at no additional cost up to 10 percent of total system capacity annually; (3) checking, cleaning, calibrating, and servicing all chemical control, dosing, and feeding equipment; (4) maintaining inventory control of chemical reserves and legally disposing of empty containers in compliance with environmental regulations; (5) inspecting cooling towers during monthly visits and performing waterside inspections during scheduled facility shutdowns with comprehensive written reports including photographic evidence; and (6) providing certified laboratory analyses for diagnostic support, conducting chemical safety training for facility personnel, and guaranteeing maintenance of system operating efficiency with the contractor responsible for cleaning affected systems at no cost if fouling occurs due to treatment failure. The base period runs from January 1, 2027 through December 31, 2028, with four one-year option periods extending through December 31, 2032. Contractor employees must work generally between 0800 and 1500 PST, Monday through Friday, except Federal holidays, though weekend and holiday work may be required. All contractor personnel must possess valid Federal or State identification, appropriate vehicle registration and insurance, and must comply with all Government security, safety, and conduct regulations while onsite.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR # 61200PR270000061

STATEMENT OF WORK

LAST UPDATED: 11/13/2026

STATEMENT OF WORK (SOW)

FOR

MONTHLY BOILER MAINTENACE AND CHEMICAL TESTING

1.0 GENERAL

1.1 BACKGROUND

U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road Petaluma; CA 94952 is the Coast Guard’s largest West Coast Training Center. Our graduates are the latest chefs, medics, storekeepers, yeoman, information systems technicians, electronics technicians, operations specialists, and aviation survival technicians (AST). We are also home to the Coast Guard Leadership Development Center’s Chief Petty Officer Academy.

1.2 SCOPE

The requirement of this contract is for the contractor to furnish all labor, tools, materials, equipment, supplies, services, supervision, and all other items necessary to provide comprehensive boiler chemical testing, preventative water treatment, and scale/corrosion control on eleven (11) hot water loops, one (1) steam boiler, and associated cooling tower systems located at USCG TRACEN Petaluma. The contractor is responsible for all phases of chemical water treatment, system monitoring, periodic inspections, inventory control, and waterside efficiency assurance.

1.3 OBJECTIVE

The service provider shall provide all labor, equipment, materials, vehicles, and appliances necessary to perform all operations in connection with routine water testing, scale and corrosion mitigation, equipment calibration, and chemical water treatment across facility heating loops, steam boilers, and cooling systems at U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road, Petaluma, CA 94952-4154.

1.4 APPLICABLE DOCUMENTS

1.4.1 Reference Documents

The following documents may be helpful to the Contractor in performing the work described in this document:

• 29 CFR Part 1910 - Occupational Safety and Health Standards (General Industry)

• 29 CFR Part 1910.1200 - Hazard Communication Standard (Safety Data Sheets / Chemical Safety)

• Federal Acquisition Regulation (FAR) 4.1103 - System for Award Management

2.0 SPECIFIC REQUIREMENTS/TASKS

2.1 TASK ONE. ROUTINE MONTHLY ONSITE SERVICE AND WATER TESTING

• Provide one (1) onsite service visit per calendar month to conduct testing, monitoring, and chemical servicing of eleven (11) hot water loops and one (1) steam boiler.

• Perform standard chemical testing on boiler water, feedwater, condensate, and closed loop systems (evaluating pH, conductivity, dissolved solids, inhibitor levels, and alkalinity).

• Provide and maintain access to an online portal for digital service reporting, data trending, and continuous operational logging.

file:///C:/Users/CEYeargin/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/SCOPE%20PARAGRAPHS.doc

List of boilers locations:

2.2 TASK TWO. SCALE AND CORROSION INHIBITOR APPLICATION

• Furnish and apply chemical water treatment products engineered to retard scale and corrosion in the steam boilers.

• Furnish and apply corrosion inhibitor to closed hydronic loops should water loss occur from the systems.

• Provide supplemental corrosion inhibitors to treat system water loss up to a maximum volume of 10% total system capacity per calendar year at no additional cost to the Government.

2.3 TASK THREE. FEED EQUIPMENT CALIBRATION AND MAINTENANCE

• Check, clean, calibrate, and service all chemical control, dosing, and feeding equipment.

• Check, inspect, and verify the operational integrity of all associated water treatment control hardware and monitoring probes.

2.4 TASK FOUR. INVENTORY CONTROL AND CONTAINER DISPOSAL

• Maintain strict inventory control of all onsite chemical reserves, ensuring adequate supplies are always maintained.

• Promptly remove all empty chemical drums, containers, and packaging from Government property and dispose of them legally in full compliance with applicable environmental regulations.

2.5 TASK FIVE. COOLING TOWER AND WATERSIDE INSPECTIONS

• Inspect facility cooling towers during monthly service visits for operational anomalies, cleanliness, and safety concerns.

• Perform waterside inspections of boilers and condensers during scheduled facility shutdowns (provided sufficient advance notice is given by the Government).

• Provide a comprehensive written inspection report following open-vessel inspections, including color photographic evidence of waterside equipment conditions.

2.6 TASK SIX. LABORATORY ANALYSIS AND TECHNICAL SAFETY TRAINING

• Provide certified laboratory analyses for backup diagnostic support whenever anomalous conditions, severe contamination, or baseline verification is required.

• Conduct chemical safety and operational handling training for onsite USCG facility maintenance personnel.

• Participate in annual management reviews conducted at the discretion of TRACEN Petaluma facility engineering personnel.

• Guarantee that the present degree of operating efficiency of the cooling and heating systems will be maintained while under the contractor's program; should fouling or loss of efficiency occur as a result of chemical treatment failure, the contractor shall clean the affected systems at no additional cost to the Government.

3.0 CONTRACTOR PERSONNEL

3.1 QUALIFIED PERSONNEL

The Contractor shall provide qualified personnel to perform all requirements specified in this

SOW.

3.2 CONTINUITY OF SUPPORT

The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Government Technical

Representative prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.

3.3 EMPLOYEE IDENTIFICATION

3.3.1 Contractor employees visiting Government facilities must wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times. Due to heightened security at USCG facilities, all contractor employees performing tasks related to this SOW shall have a valid Federal or State identification while onboard a Coast Guard facility. Vehicles shall have current registration and insurance, and drivers shall have a valid driver’s license. Time spent undergoing entrance screening to USCG facilities will not be considered a government delay of work or differing site condition.

3.4 EMPLOYEE CONDUCT

Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at

Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.

3.5 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS

The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.

Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.

4.0 OTHER APPLICABLE CONDITIONS

4.1 SECURITY

Contractor access to classified information is not currently required under this SOW.

4.2 PERIOD OF PERFORMANCE

The period of performance for this contract is a one-year base period with four one-year option periods as follows:

Base Period January 1, 2027 through December 31, 2028 Option Period One January 1, 2028 through December 31, 2029 Option Period Two January 1, 2029 through December 31, 2030 Option Period Three January 1, 2030 through December 31, 2031 Option Period Four January 1, 2031 through December 31, 2032

4.3 PLACE OF PERFORMANCE

The primary place of performance will be the United States Coast Guard TRACEN Petaluma located at 599 Tomales Road, Petaluma, CA 94952.

4.4 HOURS OF OPERATION

Contractor employees shall generally perform all work between the hours of 0800 and 1500

PST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.

4.5 TRAVEL

Contractor travel must not be required for this requirement.

4.6 GENERAL REPORT REQUIREMENTS

The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).

Additionally, the contractor must provide access to online reporting, data trending, and logs as described in Section 2.0.

5.0 GOVERNMENT FURNISHED RESOURCES

The Government will not furnish any resources to the Contractor in support of this contract.

6.0 CONTRACTOR FURNISHED PROPERTY

The Contractor shall Furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in

SOW 2.0 and SOW 5.0.

STATEMENT OF WORK (SOW)
FOR

File details come from the government source that posted it. Updated .