610-23-515 - COMBINED DRAWINGS.pdf
PDF 2 MB Posted
- Solicitation number
- 36C25023B0034
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25023B0034 0001 Amendment.docx | DOCX document | |
| 610-23-515 Replace Roofs Buildings 32 33 34 Pre Bid Site visit.pdf | ||
| 610-23-515 - Combined Specs.pdf | ||
| RFI Form-36C25023B0034.docx | DOCX document | |
| WD.pdf | ||
| VAAR 852.219-75 VA Notice of Limitations on Subcontracting (JAN 2023).pdf | ||
| VHA_Directive_1192.pdf | ||
| 36C25023B0034_1.pdf | ||
| 610-23-515 Replace Roofs Buildings 32 33 34- OTFOC Sole Source Revised (002).pdf | ||
| Attachment 7 - EMR.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL NOTES:
1. THE CONTRACTOR WILL BE RESPONSIBLE FOR PROVIDING ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION NECESSARY FOR REMOVING AND INSTALLING NEW ROOFING, GUTTER'S, DOWNSPOUTS, CAST IRON CLEAN-OUTS, FASCIA BOARD ETC ... IN CONFORMANCE WITH THE DETAILS
AS SHOWN.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR VISITING THE SITE AND PERFORMING ANY AND ALL REQUIRED MEASUREMENTS USED IN
PREPARATION OF BIDDING DOCUMENTS. ALL DIMENSIONS ARE APPROXIMATE.
3. IT WILL BE THE CONTRACTORS RESPONSIBILITY TO LOCATE ALL SITE UTILITIES. IF DAMAGE OCCURS TO ANY UTILITIES, IT MUST BE REPAIRED AT
CONTRACTORS OWN EXPENSE.
4. WORK AREAS SHALL BE ROPED OFF AROUND WORK SITES. THE CONTRACTOR SHALL BE RESPONSIBLE FOR BLOCKING OFF AREAS AS REQUIRED, FURNISHING THE NECESSARY BARRICADES, SIGNS, ETC ... ALL ENTRANCES SHALL REMAIN OPERATIONAL AT ALL TIMES UNLESS PRIOR PERMISSION HAS BEEN OBTAINED FROM THE PROJECT ENGINEER TO RESTRICT OTHER THAN EMERGENCY ACCESS.
5. TOOLS AND EQUIPMENT SHALL BE SECURED ANY TIME WORKERS ARE NOT IN THE IMMEDIATE AREA. THE WORK SITE SHALL BE CLEANED UP AT
THE CONCLUSION OF EACH DAYS WORK.
6. UPON FINAL CLEAN-UP, THE CONTRACTOR SHALL REMOVE ANY DEBRIS, RUBBISH, AND EXCESS MATERIAL FROM THE STATION.
7. THE CONTRACTOR SHALL FOLLOW ALL APPLICABLE VAMC REGULATIONS, OSHA STANDARDS AND INTERIM LIFE SAFETY MEASURES.
8. SEE LEAD-BASED PAINT REPORT AND SPECIFICATION FOR ABATEMENT INFORMATION.
9. THE CONTRACTOR SHALL TAKE EVERY PRECAUTION TO PREVENT DAMAGING ADJACENT PAVING, SIDEWALKS, SHRUBBERY, ETC ... IF DAMAGE
OCCURS IT MUST BE REPAIRED AT CONTRACTORS OWN EXPENSE.
10. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REQUIRED REPAIRS TO DAMAGED SOD. COMPLETED REPAIRS MADE BY EXPERIENCED
PERSONNEL SHALL MATCH THE EXISTING.
11. THE WORK PREFORMED IN THIS CONTRACT SHALL BE CAREFULLY COORDINATED WITH THE PROJECT ENGINEER AND A WORK SCHEDULE SHALL
BE SUBMITTED BY THE CONTRACTOR FOR APPROVAL, PRIOR TO THE START OF ANY WORK. DEMOLISHED AREAS SHALL BE REPAIRED WITHIN 4 WORKING DAYS OF THEIR REMOVAL. HOWEVER, THE CONTRACTOR SHALL NOT REMOVE MORE ROOFING THAN CAN BE REPLACED IN ONE DAY.
IF ADDITIONAL ROOFING NEEDS TO BE REMOVED, IT SHALL BE APPROVED BY THE PROJECT ENGINEER.
12. THE CONTRACTOR SHALL ESTABLISH A CONTINGENCY PLAN TO COVER ANY OPEN ROOF IN THE EVENT OF RAIN AND SUBMIT THIS PLAN TO THE
PROJECT ENGINEER FOR APPROVAL BEFORE THE START OF ANY WORK.
13. THE CONTRACTOR SHALL BE RESPONSIBLE FOR A SCHEDULE ALLOWING A MINIMUM OF TEN ( 10) DAYS ADVANCE NOTICE OF THE PLANNED START OF WORK/CONSTRUCTION ACTIVITIES. THE CONTRACTOR WILL BE ALLOWED TO WORK AFTER THE CLOSE OF REGULAR BUSINESS HOURS BY APPROVAL ONLY. THIS SHALL BE SCHEDULED WITH THE PROJECT ENGINEER AND THE CONTRACTOR SHALL REPORT IN AND OUT
WITH THE VA POLICE WHEN WORKING AFTER HOURS.
14. THE CONTRACTOR SHALL HAVE ON THE JOB AT ALL TIMES DURING THE PROGRESS A FORMAN, SUPERINTENDENT OR OTHER COMPETENT REPRESENTATIVE TO WHOM ORDERS AND INSTRUCTIONS MAY BE GIVEN. HIS NAME IS TO BE CERTIFIED TO THE VA AND ANY ORDERS GIVEN TO SUCH REPRESENTATIVE SHALL HAVE THE SAME FORCE AND EFFECT AS IF GIVEN DIRECTLY TO THE CONTRACTOR. A PHONE NUMBER WHERE A RESPONSIBLE PERSON CAN BE REACHED AFTER HOURS IN CASE OF PROBLEMS ETC ... SHALL BE PROVIDED ALSO.
15. UPON REMOVAL OF EXISTING ROOFING, THE CONTRACTOR SHALL HAMMER IN ANY AND ALL LOOSE NAILS ON EXISTING DECKING
16. THE CONTRACTOR SHALL INSTALL NEW 1/,," OSB DECKING WITH 30 LB. FELT PAPER UNDER NEW STONE COATED 50 YEAR STEEL SHINGLES.
STEEL SHINGLES SHALL BE FASTENED WITH 2-1/4" MIN EPOXY COATED DECK SCREWS. THE CONTRACTOR SHALL ALSO REMOVE AND INSTALL
NEW VENTS AND VENT BOOTS.
17. ALL DRIP EDGE, FLASHING ETC ... SHALL BE COATED TO MATCH STEEL SHINGLES. ALL FLASHING ON FLAT ROOF AREA'S SHALL BE STAINLESS
STEEL.
18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ASSURING THAT THE FASCIA IS SQUARE SO THAT NEW SHINGLES ARE ALIGNED STRAIGHT AND
ARE FASTENED SECURELY.
19. ALUMINUM GUTTERS AND DOWNSPOUTS SHALL BE INSTALLED NEW WHERE SPECIFIED ALONG WITH CAST IRON CLEAN-OUTS BELOW GRADE WHERE SPECIFIED. ( SEE CAST IRON CLEAN-OUT DETAIL) . GUTTERS SHALL BE FASTENED WITH GUTTER SCREWS AND SCREWS SHALL BE COVERED WITH ADHESIVE. ALL REMOVED METALS SHALL REMAIN PROPERTY OF THE VAMC AND SHALL BE DISPOSED OF IN DESIGNATED AREA
APPROVED BY THE PROJECT ENGINEER.
20. INSTALL A NEW GUTTER LINER WITH A MIN. 10 YEAR WARRANTY THAT IS AN ALUMINUM FACED, SELF ADHERING, RUBBERIZED ASPHALT MATERIAL ( 40 MIL. MIN.) AND TUCK A MIN. OF 12" UNDER NEW STEEL SHINGLES. IF ANY SHINGLE. THE COLOR OF THE GUTTER LINER SHALL BE SLATE GRAY. ANY HOLES IN THE EXISTING METAL BOX GUTTER LARGER THAN A QUARTER SHALL BE COVERED WITH GALVANIZED FLASHING
BEFORE THE NEW GUTTER LINER IS INSTALLED.
�=t==:1
I
I --------11
---------illLJ
Officeof
E. ::
Management
= •l�ri=:=..
JI SIGN DEVI LOP'v1E
�LILLY SPJ:llNKLE'RH
Replace Roofs, building 32, 33, & 34
-�=n �pus 22-104 M L --� 2ara
I
| 1 - Construction Solicitation P.pdf |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
File details come from the government source that posted it. Updated .