61-55000-26-01208_Ute_Dam_RFP_QA.pdf.PDF
PDF 582 KB Posted
- Attached to
- UTE DAM OUTLET WORKS MODIFICATION PROJECT
- Solicitation number
- 61-55000-26-01208
- Issued by
- San Juan County, New Mexico
About this file
This is a Request for Proposals Questions & Answers document issued by the State Purchasing Division of the General Services Department and the Interstate Stream Commission (ISC) of New Mexico for the Ute Dam Outlet Works Modification Project located near Logan, New Mexico. The project involves comprehensive repair, modification, and installation services including mobilization, bulkhead repair and underwater installation, internal pipe inspection, fill pipe removal, outlet works bypass system installation with a 10-inch stainless steel pipeline and multi-orifice valve, electrical upgrades, pipe lining and coating repairs, and full commissioning with operations and maintenance manuals and training. Construction work is permitted Monday through Friday from 6 a.m. to dark. Contractor access is available via the south side boat ramp for reservoir access and the dam crest road, with no turnaround available on the dam crest road. An optional site visit occurred on June 17, 2026, and divers may use the marina on the north side of the reservoir to tie up their barge during off-hours. The bulkhead, which weighs approximately 2,500 lbs and was last installed in January 2000 without observed leakage, requires seal and bearing pad replacement. The top trash rack to be removed weighs an estimated 900 lbs and was previously removed in January 2000. The project includes approximately 25 sq ft of exterior coating and 25 sq ft of interior liner repair, with the existing coating applied during 2000 modifications using lead-free paint. Limited information is available on the 42-inch butterfly valve and actuator; only 1962 and 2000 design drawings and related data have been provided.
The RFP evaluation criteria total 1,000 points, comprised of Organizational Experience (400 points), Organizational References (150 points), Desirable Specifications (150 points), Financial Stability (50 points), Oral Presentations (50 points), and Cost (200 points), with Mandatory Specifications and required forms scored on a pass/fail basis. Qualified contractors must hold all required New Mexico contractor licenses, demonstrate underwater construction capabilities with qualified dive teams, provide evidence of confined-space and tunnel work experience, maintain OSHA-compliant safety programs, and carry mandatory general liability and workers' compensation insurance. A bid bond equal to 5% of the bid amount is required, along with performance and payment bonds each in the amount of 100% of the contract price as mandated by NMSA 13-4-18 for construction contracts exceeding $25,000. New Mexico and Native American Resident Preferences are available, providing 100 points for resident business preferences or 80 points for veteran preferences. The project is fully state-funded with no federal involvement. Written questions were due by June 10, 2026, with responses provided by June 15, 2026, and electronic proposals were due by 3:00 PM MST/MDT on June 23, 2026. Finalist oral presentations were scheduled for July 10, 2026, best and final offers were due July 11, 2026, and contract award was targeted for July 2026 or shortly thereafter.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DSCN8222.JPG | JPG image | |
| DSCN8202.JPG | JPG image | |
| DSCN8212.JPG | JPG image | |
| Thumbs.db | — | |
| DSCN8205.JPG | JPG image | |
| 61-55000-26-01208_UteDam_2000Drawings.pdf.PDF | ||
| 61-55000-26-01208_24112_Existing Actuator.pdf.PDF | ||
| DSCN8210.JPG | JPG image | |
| 61-55000-26-01208_UteDam_1962Drawings.pdf.PDF | ||
| 61-55000-26-01208__RFP 61-55000-26-01208 A001.docx.DOCX | DOCX document | |
| 61-55000-26-01208_61-55000-26-01208_Ute Dam Outlet Works Modification Project 5.20.26.pdf.PDF.crdownload | CRDOWNLOAD file | |
| DSCN8220.JPG | JPG image | |
| 61-55000-26-01208_61-55000-26-01208_Ute Dam Outlet Works Modification Project 5.20.26.pdf.PDF |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ute Dam – Request for Proposals Questions & Answers
Work Hours and Access Q1: What are the allowable workdays per week and hours per day for onsite construction?
A: Monday through Friday, 6 a.m. to dark.
Q2: Sheet 3: Can you confirm that the south side boat ramp is available for contractor access to the Ute Reservoir?
A: Yes, the south side boat ramp is available and may be used for reservoir access.
Q3: Sheet 3: Is the dam crest road available for contractor use? If yes, are there any restrictions?
A: Yes, the dam crest road is available for use. No restrictions; however, there is no turnaround.
Q4: Will there be a site visit to see access?
A: Per Amendment 1, the optional site visit occurred on June 17, 2026.
Q5: Where will divers be able to tie up their barge during off-hours?
A: The marina on the north side of the reservoir is available.
Bulkhead and Structural Components Q6: Provide details on repairs needed to the existing bulkhead, pictures, and any access restrictions.
A: The bulkhead seal and bearing pad require replacement in accordance with Technical Specification Section 01 31 00. Photos are attached.
Q7: Clarify where the 90 ft air vent hose must be secured above the reservoir water surface.
A: No information is available. The 1982 drawings do not provide details.
Q8: What is the weight of the bulkhead?
A: Approximately 2,500 lbs (1982 USBR design drawings).
Q9: Has the bulkhead ever been installed, and was leakage observed?
A: Yes, installed in January 2000. No leakage observed.
RFP # 61-55000-26-01208
P a g e | 2
Trash Racks and Hardware Q10: Provide information on the condition of trash rack hardware and the availability of dive inspection media.
A: No inspection media available. Trash rack elevation is 3,726.86 ft (NAVD88).
Additional details incomplete.
Q11: What is the weight of the top trash rack to be removed?
A: Estimated at approximately 900 lbs.
Q12: Has the trash rack ever been removed?
A: Yes, in January 2000.
Coatings and Environmental Considerations Q13: Breakdown of 50 sq ft coating/liner touch-up inside vs outside.
A: Approximately 25 sq ft exterior coating and 25 sq ft interior liner repair.
Q14: Is there lead known in the coating? When was it first painted?
A: Painted during 2000 modifications with lead-free specified paint (product unknown).
Q15: Is QP1 required?
A: No. The contractor must provide the required experience.
Equipment and As-Builts Q16: Information on the 42” butterfly valve and actuator.
A: Limited information available; attachments provided.
Q17: Will as-builts for tunnel or SOW components be provided?
A: Only available documents are the 1962 and 2000 design drawings and data.
61-55000-26-01208
| Work Hours and Access |
| Bulkhead and Structural Components |
| Trash Racks and Hardware |
| Coatings and Environmental Considerations |
| Equipment and As-Builts |