Past performance questionnaire

View the file

Other files

File Type Posted
Attachment_A_-_Sidewalk_repair_drawing.pdf PDF
60RRBH18Q0028.pdf PDF
Attachment_B_-_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C – 60RRBH18Q0028 – SIDEWALK REPAIR/SEALING SERVICES

PAST PERFORMANCE QUESTIONNAIRE

SIDEWALK REPAIR/SEALING SERVICES

Offeror:

Reference Organization:__Railroad Retirement Board__
Name of Contact:___________
Date:___________

Please mark an “x” next to the applicable response below.

1. Direct applicability of the referenced project:

The United States Railroad Retirement Board (RRB) is considering this contractor to provide Sidewalk Repair/Sealing services (Labor and Materials). Did this contractor perform this specific type of services for your organization?

A. Positively yes, the referenced project was virtually identical to what we are pursuing___
B. Basically yes; the referenced project was generally similar to what we are pursuing___
C. The referenced project was only slightly related to what we are pursuing___
D. The project was fundamentally different than what we are pursuing___

Comments:

2.Overall customer satisfaction:
How satisfied overall were you and others with the service provided?
A. Very satisfied with every aspect of the service___
B. Relatively satisfied___
C. Neither satisfied nor dissatisfied___
D. Dissatisfied___

Comments:

Which of the following statement is most true considering all aspects of the project?

A. There were no contractor-caused problems of any kind ___ B. Contractor-caused problems encountered were minor in nature and were remediated in a timely fashion ___ C. Contractor-caused problems were significant but the contractor was willing to adequately remediate the problems ___ D. Contractor-caused problems were significant and the contractor was unwilling to adequately remediate the problems ___

Comments:

Taking the entire project into account, would you use this contractor again?

A. Yes, definitely___
B. Yes, but with certain reservations___
C. Maybe/maybe not___
D. Never___

Comments:

3. Quality of service:

What was the quality of the work performed?

A. Of the highest quality that could be expected___
B. Exceeded minimum requirements___
C. Met minimum requirements___
D. Below minimum requirements___

Comments:

To what extend did the contractor display initiative in meeting requirements?

A. The contractor displayed considerable initiative___
B. The contractor displayed some initiative___
C. The contractor displayed little initiative___
D. The contractor displayed no initiative___

Comments:

4. Reliability and timeliness of performance:

Was the contractor reliable and timely in their performance of your work?

A. Yes, in every situation___
B. Yes, in most situations___
C. To a minimum acceptable level___
E. At an unacceptable level___

Comments: