This document outlines a federal contract opportunity for renovations to the second floor east wing at the Manchester VA Medical Center. The scope of work involves interior finishes and architectural work, mechanical ventilation system upgrades, and performance requirements in accordance with approved plans and specifications. Bids are due by March 7, 2024 with award anticipated shortly after. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses and seeks pricing for tasks including minor demolition, new flooring installation, wall patching, gypsum wall installation, painting, ceiling grid/tile replacement, and mechanical ventilation system upgrades to provide six air changes per hour for specified rooms. The contract value is estimated to exceed $750,000 resulting in contractor performance evaluations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24124B0031 0005.docx | DOCX document | |
| 36C24124B0031 0004.docx | DOCX document | |
| RFI ANSWERS.docx | DOCX document | |
| Site visit Sign in sheet.pdf | ||
| 36C24124B0031 0003.docx | DOCX document | |
| 36C24124B0031 0002.docx | DOCX document | |
| 608-23-001 Renovate Second Floor East Wing Dwgs.pdf | ||
| 36C24124B0031 0001.docx | DOCX document | |
| Project Specifications 650-23-001 020124.pdf | ||
| 36C24124B0031_1.docx | DOCX document | |
| SAM.gov NH WD 06302023.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA New England Healthcare System Manchester VA Medical Center
718 Smyth Road Manchester, NH 03104
STATEMENT OF WORK
Renovations to Second Floor East Wing
1.0 INTRODUCTION
Building one second floor east wing suffered a flood that damaged the ceiling, flooring, and walls.
During this time the occupants of the second floor east wing were removed while flood remediation was performed which included removing some of the drywall, ceiling grid/tiles, and all of the flooring. In preparation to reoccupy the space this project will return the wing to a useable state for laboratory operations as well as office space.
Contractor shall provide all labor, materials, tools, equipment, expertise, apparatus, administration, supervision, transportation, permits and disposal as necessary to perform all work as described in the contract documents and per the description herein.
Contractor shall completely prepare site for building operations, including demolition and removal of existing construction, and furnish labor and materials to perform work for Renovations to Second Floor East Wing in Building 1, at VAMC Manchester as required by drawings and specifications and this scope of work. The work on this project includes but is not limited to the renovation or replacement or removal of interior walls, flooring, ceiling, finishes, mechanical, electrical, and plumbing, The project also includes demolition and patching as required to complete the work for this project. Construction site security shall be maintained at all times. Normal hours of operation for the hospital are Monday- Friday 7:30am-4:30pm EST excluding federal holidays.
Construction to be performed during normal working hours.
The VA shall be considered the Engineer of record and all RFI’s and submittals shall be sent to them for resolution through the Contracting Officer.
After Contract Award the Contractor is required to provide a Payment Bond, a Performance Bond and an Insurance certificate within 10 days. Once received and confirmed, the period of performance for the above-mentioned project will begin with a Notice to Proceed (NTP) issued at a Pre-Construction Meeting (Pre-Con). As part of this solicitation the General Contractor (GC) shall submit a preliminary schedule using Microsoft Project showing the methodology for accomplishing the project.
The overall period of performance for this work is 120 calendar days after NTP has been issued.
Pending approval of the COR and CO this period of performance can be adjusted as needed to support the work. Upon notification to the contracting officer a no cost extension can be granted to the contract.
2.0 PROJECT STAFF
CONTRACTING OFFICER (CO)
TBD
718 Smyth Road| BSB Suite 105| Manchester, NH 03104
CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE (COR):
Andrew OBrien Assistant Chief 718 Smyth Road | Manchester, NH 03104 Phone 603.624.4366 x6534 | Email Andrew.obrien@va.gov
3.0 SCOPE
This project involves the following items as part of the project scope that has been broken down into three specific divisions:
TASK 1: Interior Finishes and architectural work.
As part of the second-floor relocation work interior finish work will need to be completed. This work includes minor demolition, installation on new flooring, patching of existing walls, installation of gypsum walls, painting, installation of ceiling grid and tiles. Refer to drawings and finish schedule 09 06 00 for types and material as well as locations to receive finish and architectural work.
TASK 2: Mechanical Ventilation:
Three areas within the space identified require a new HVAC ventilation system. These rooms in these three areas are identified on the plans as E200, E201, E222, E223, E224, E225, E226, E227, W230, W231, and W232. Work within W230, W231 and W232 cannot begin until work within Rooms E211, E212, E212A and E213 are completed.
Currently Mini-splits provide cooling to the lab spaces and are slated to remain. The space is also served by general exhaust units and fan coil units “Daiken/McQuay Thinline TSH FCUs”. These FCUS are in a state of disrepair with units either having blown motor issues, control issues, electrical issues or HVAC piping issues. Chilled water and hot water are provided to each FCU (total of 8 FCUS throughout the three spaces identified) and are controlled by pneumatic controllers. See mechanical drawings for existing state.
New work under this task shall include reinsulating refrigerant lines for the mini splits within these areas as well as providing a new/renovated HVAC system to meet the required air changes listed in the HVAC Design Manual for Pathology and Laboratories. The contractor shall engage with an HVAC designer/contractor to ensure that the requirements are met. The space shall be tested and balanced as part of overall acceptance of the space.
New Controls/controllers shall be installed as part of this task providing for constant volume and local temperature control. HVAC Units shall provide for 6 air changes per hour. Current installed
HVAC equipment can meet the requirements of this task provided equipment is refurbished and new controls are installed.
Documents:
HVAC Design manual Link here: dmHVAC.pdf – Pathology and Laboratories On page 6-96/6-97
4.0 PERFORMANCE REQUIREMENTS
Refer to contract documents (drawings and specifications) for complete details of project work.
This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed in accordance with the approved plans and specifications at the Manchester VAMC, located at 718 Smyth Rd, Manchester, NH 03104.
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety and infection control measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
Prior to the start of any field work, the contractor shall contact the VA COR to review proposed methods and plans for completion of work and to review infection control procedures, interim life safety procedures, above ceiling and wall penetration permits, hot work permits and the contractor’s site-specific safety plan.
***END OF THIS SCOPE OF WORK***