This is a Request for Proposal (RFP) issued by the Greater Dayton Regional Transit Authority (RTA) for the complete replacement of entrance and exit garage door systems at its facility located at 600 Longworth Street in Dayton, Ohio. The project requires demolition of existing door systems, modification of openings as necessary, and furnishing and installation of new bi-parting garage doors or equivalent proven systems. The new doors must be capable of handling up to 300 cycles per day (approximately 110,000 cycles annually), with opening and closing times within 15 seconds each, 480-volt three-phase electrical service operation, electric safety edges, perimeter seals, electric eyes for vehicle detection, windows for natural light, and parts availability for at least 25 years. The RFP was released on April 24, 2026, with a non-mandatory pre-proposal conference scheduled for June 23, 2026, at 10:00 a.m. The final deadline for questions and clarifications is June 29, 2026, at 5:00 p.m., and proposals are due by July 7, 2026, at 10:00 a.m. via OpenGov. Contract award will be made within 90 calendar days of proposal receipt. The contract term is twelve months, with RTA retaining the option to extend the contract by written notice within 30 days before expiration, provided preliminary notice is given at least 60 days in advance; however, the total contract duration, including any extensions, shall not exceed twelve months.

This is a firm-fixed-price contract with no established Disadvantaged Business Enterprise (DBE) set-aside requirement, though RTA welcomes DBE participation. There are no incumbent vendors identified. Evaluation occurs in two phases: Phase One assesses design and technical approach, methodology, qualifications, relevant experience, and project schedule, with only top-scoring proposals advancing to Phase Two for pricing submission. The contract will be awarded to the lowest responsive and responsible proposer among qualified firms. All pricing is firm and non-negotiable for the contract duration, with invoicing upon work completion, though partial payments are permitted for on-site materials and completed work with written RTA approval. All materials and labor carry a minimum one-year warranty from project completion, with manufacturer warranties exceeding this period taking precedence. The project is funded in part by the Federal Transit Administration (FTA) and the Ohio Department of Transportation (ODOT) and is subject to Ohio prevailing wage requirements. Contractors must comply with all applicable FTA clauses, Buy America requirements, debarment and suspension verification, federal certifications, and various environmental and civil rights compliance requirements. Bidders must demonstrate experience with large bi-parting garage doors and be licensed to do business in the State of Ohio.

View the file

Other files

File Type Posted
600_Longworth_Garage_Door_Project.pdf PDF
600_LONGWORTH_GARAGE_DOOR_DIMENSIONS-SPECIFICATIONS_-_FINAL_-_4-16-26.pdf PDF
600_LONGWORTH_GARAGE_DOOR_DIMENSIONS-SPECIFICATIONS_-_FINAL_-_4-16-26.pdf PDF
IMG_0831.JPG JPG image
IMG_0837.JPG JPG image
IMG_0839.JPG JPG image
IMG_0841.JPG JPG image
IMG_0843.JPG JPG image
IMG_0847.JPG JPG image
IMG_0831.JPG JPG image
IMG_0833.JPG JPG image
IMG_0840.JPG JPG image
IMG_0845.JPG JPG image
IMG_0836.JPG JPG image
IMG_0838.JPG JPG image
IMG_0845.JPG JPG image
IMG_0846.JPG JPG image
IMG_0836.JPG JPG image
IMG_0841.JPG JPG image
Inside_looking_out.JPG JPG image
IMG_0828.JPG JPG image
IMG_0830.JPG JPG image
IMG_0833.JPG JPG image
IMG_0835.JPG JPG image
IMG_0844.JPG JPG image
IMG_0828.JPG JPG image
IMG_0835.JPG JPG image
IMG_0837.JPG JPG image
IMG_0839.JPG JPG image
IMG_0842.JPG JPG image
IMG_0843.JPG JPG image
IMG_0844.JPG JPG image
IMG_0846.JPG JPG image
IMG_0832.JPG JPG image
IMG_0834.JPG JPG image
IMG_0840.JPG JPG image
IMG_0842.JPG JPG image
IMG_0848.JPG JPG image
Inside_looking_out.JPG JPG image
600_GARAGE_DOOR_VIDEO_1.mp4 MP4 file
600_GARAGE_DOOR_VIDEO_2.mp4 MP4 file
Entrance.JPG JPG image
600_GARAGE_DOOR_VIDEO_1.mp4 MP4 file
600_GARAGE_DOOR_VIDEO_2.mp4 MP4 file
Entrance_Door.JPG JPG image
Entrance.JPG JPG image
Entrance_Door.JPG JPG image
Sample_Contract_(DO_NOT_COMPLETE).pdf PDF
Sample_Contract_(DO_NOT_COMPLETE).pdf PDF
RTA_General_Terms_and_Conditions.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Greater Dayton Regional

Transit Authority

Request for Proposal

600 LONGWORTH GARAGE DOOR PROJECT

CONTRACT BID NO. GD 26-27

RELEASE DATE

April 24, 2026

REQUEST FOR PROPOSAL

600 LONGWORTH GARAGE DOOR PROJECT

RFP No. GD 26-27

TABLE OF CONTENTS

Letter to Proposers Scope of Work & Special Conditions Instructions to Proposers FTA Required Clauses Proposal Evaluation Criteria Proposal Submission

Attachments:

A - Sample Contract (DO NOT COMPLETE)

B - RTA General Terms and Conditions

C - 600 GARAGE DOOR VIDEO 1

D - 600 GARAGE DOOR VIDEO 2

E - Entrance Door

F - Entrance

G - IMG_0828

H - IMG_0830

I - IMG_0831

J - IMG_0832

K - IMG_0833

L - IMG_0834

M - IMG_0835

N - IMG_0836

O - IMG_0837

P - IMG_0838

Q - IMG_0839

R - IMG_0840

S - IMG_0841

T - IMG_0842

U - IMG_0843

V - IMG_0844

W - IMG_0845

X - IMG_0846

Y - IMG_0847

Z - IMG_0848

AA - Inside looking out

BB - 600 LONGWORTH GARAGE DOOR DIMENSIONS-SPECIFICATIONS - FINAL -

4-16-26

LETTER TO PROPOSERS

RELEASE DATE: Friday, April 24, 2026

DEAR PROSPECTIVE PROPOSER:

Re: Request for Proposal (RFP)

600 Longworth Garage Door Project

RFP No. GD 26-27

Notice is hereby given that the Greater Dayton Regional Transit Authority (RTA) is requesting proposals for the following procurement. All proposals must be submitted in accordance with requirements set forth in this procurement solicitation, and must be received via OpenGov before 10:00 am, Dayton (Eastern) time, on Tuesday, July 7, 2026, for the following project:

600 Longworth Garage Door Project

Please view the project timeline and make arrangements to attend the pre-proposal conference, if applicable.

RFP Release Date: April 24, 2026

Pre-Proposal Conference (Non-

Mandatory):

June 23, 2026, 10:00am

Agenda

600 Longworth St., Dayton, OH, Maintenance Conference Room

You are encouraged to attend this meeting in person; however, if you are unable to do so, there is a Teams link for your convenience.

Microsoft Teams meeting

Join:

https://teams.microsoft.com/meet/22033

5992400820?p=hgXjJH3OpOPmC4X0d

Meeting ID:

220 335 992 400 820

Passcode:

Vp3Pm3Cu

Final Date for Questions, Clarifications and Requests for Approved Equals:

June 29, 2026, 5:00pm

Proposal Due Date: July 7, 2026, 10:00am

All proposals and related documents shall be subject to a financial assistance contract between the RTA and the United States Department of Transportation under the Urban

Mass Transportation Administration Act of 1964, as amended, terms and conditions established under the Act will apply. All proposers will be required to certify they are not on the U.S. Comptroller General's Consolidated list of ineligible contractors. Manufacturers appearing on said list will be considered ineligible.

RTA hereby notifies all proposers that, in regard to any contract entered into pursuant to this procurement, advertisement or solicitation, disadvantaged business enterprises will https://government-project.s3.amazonaws.com/256240/49c0dcd0-8d13-4542-be80-66bdea7dce7d_Pre-Bid_Conference_Agenda_Sample.docx https://teams.microsoft.com/meet/220335992400820?p=hgXjJH3OpOPmC4X0d8 https://teams.microsoft.com/meet/220335992400820?p=hgXjJH3OpOPmC4X0d8 https://teams.microsoft.com/meet/220335992400820?p=hgXjJH3OpOPmC4X0d8 be afforded full opportunity to submit proposals in response and will not be subjected to discrimination on the basis of race, color, sex or national origin in consideration for an award.

DBE Participation: It is the policy of the Department of Transportation (DOT) that

DBEs, as defined in 49 CFR, parts 23 and 26, shall have the maximum opportunity to participate in the performance of contracts financed in whole or in part with federal funds under this Agreement. RTA welcomes DBE participation regardless of whether there is a DBE requirement. The DBE requirement for this project is 0%.

Please Note: This procurement package and any addenda are available on OpenGov, https://procurement.opengov.com/portal/greaterdaytonrta. In order to ensure that you receive all updates and addenda, please be sure to follow this project on OpenGov.

Should you have any questions or comments concerning the procurement, please submit through the Q&A Section of the posting on OpenGov prior to the due date and time for Questions and Inquiries.

Sincerely, Michelle Collier

Senior Purchasing Agent

SCOPE OF WORK & SPECIAL CONDITIONS

Scope of Work

The Greater Dayton Regional Transit Authority (RTA) is seeking proposals for the replacement of the existing entrance and exit garage door systems at its facility located at 600 Longworth Street, Dayton, Ohio 45402. If there are any questions or concerns about any component of this scope, submit a proposal and details can be worked out through pre-award discussions.

1. GENERAL DESCRIPTION

This project includes the complete demolition and proper disposal of existing door systems; modification or reframing of existing openings as required; and the furnishing, installation, testing, and commissioning of new entrance and exit doors. The contractor shall provide all labor, materials, equipment, and services related to the installation of the door. This project is subject to Ohio prevailing wage requirements.

The existing garage doors consist of top-hung, top-driven, bi-parting steel doors with bottom guide rollers, operated by OSCO Model GSL bi-parting door operators. Although the original manufacturer of the doors is unknown, the bi-parting configuration has demonstrated long-term reliability and suitability for high-volume transit bus operations, having been in service for approximately fifty (50) years. Each door set (entrance and exit) operates on a standard cycle time of approximately fifteen (15) seconds to open, a thirty (30) second open dwell, and fifteen (15) seconds to close. There are approximately 250 to 300 cycles per day, per door set, or approximately 110,000 cycles annually per door set. The existing doors are powered by 480-volt, three-phase https://procurement.opengov.com/portal/greaterdaytonrta electrical service and are connected to RTA’s emergency backup generator system.

The proposed replacement door system shall retain a bi-parting configuration or provide an equivalent, proven system suitable for transit applications; be designed to meet or exceed the existing operational cycle demands; operate on 480-volt, three-phase power; and fully integrate with RTA’s emergency backup generator to ensure continuous operation during power outages.

2. NEW GARAGE DOOR REQUIREMENTS – ENTRANCE AND EXIT DOORS

1. Must be able to handle up to 300 cycles per day or 110,000 per year

2. Must be able to open within 15 seconds and close within 15 seconds

3. Must be able to be programmed to stay open between 10 seconds and 3 minutes

4. Must be connected to electric eyes, such that if a bus or vehicle is within the eyes, the door stays open and resets the closing timer

5. Must have seals on bottom, top and sides of each door

6. Must have electric safety edge

7. Must be 480 3phase, unless approved otherwise

8. Can be driven from the top of the doors or the bottom of the doors

9. Must have windows to allow natural light into the building

10. Must maintain parts availability for at least 25 years

11. The door exterior shall be painted a medium brown and the interior shall be painted safety yellow. RTA will supply the paint color numbers and paint manufacturer. The contractor will paint a couple samples for RTA to approve prior to the final paint being selected.

12. Must be consistent with the detailed drawing included with this RFP, unless otherwise approved.

13. Must include detailed drawings, operational manuals, electrical schematics and parts manuals, all in electronic format and three (3) paper copies of all materials.

*There are two (2) videos and several pictures of the doors in the

ATTACHMENTS section of this solicitation for a visual reference.

*Drawing with dimensions in the ATTACHMENTS section of this solicitation.

3. CONTRACTOR QUALIFICATIONS

The awarded vendor, contractor or manufacturer should have adequate experience in the design or manufacturing and complete installation of large bi-parting garage doors.

Qualifications and experience of the installation team should be included in each proposal.

4. ON-SITE ELECTRICAL WORK

RTA will work with the awarded contractor to help coordinate the required electrical work through a qualified electrical contractor. The contractor is responsible for working with RTA to ensure electrical systems are integrated properly.

5. ON-SITE STRUCTURAL STEEL WORK

This project will require some structural steel work. There is an opening at the top of the door frame for both the entrance and exit locations where trolley wire used to exist in and out of the facility. If needed, RTA will work with the awarded contractor to help coordinate the required structural work through a local construction company or subcontractor.

6. ON-SITE CONCRETE – RAIL WORK – (OPTIONAL)

This project may require the replacement of the steel rail that the door rolls on. This steel was replaced about 4 years ago, but there is some rust that could have compromised the steel. If it is determined that this rail needs to be replaced, it shall be replaced with hot dipped galvanized steel. This item shall be priced as an option of the bid sheet.

7. SOFTWARE

Ideally, RTA would like the door system proposed to have some type of computer technology built into it where the software program can assist with troubleshooting and programming of the operational functions and reporting of usage events, which would include date and time of each event. The software shall be included and 5 years of technical support.

8. ADDITIONAL OR UNFORESEEN WORK

Should the successful vendor/contractor find that additional work is required, which was not evident during the RFP process, and was not part of the original proposal, the following shall prevail:

1. The contractor shall provide RTA with a detailed estimate of any additional work required, a breakdown of additional parts and labor, the reason this work is now required and why it was not included in the original proposal. The contractor shall provide photos of the additional work for reference.

2. RTA shall review the additional work estimate and if it agrees, shall issue written permission and a change order to perform the additional work as outlined in the written estimate.

3. All rates, labor, equipment, or other trades or professional services that are required for any additional work shall not exceed the rates provided as part of the original proposal.

WARRANTY

1. All materials and labor shall be warranted by the vendor, contractor and manufacturer for a minimum period of one (1) year from the date of official project completion. If any manufacturer’s material warranty exceeds the one (1) year warranty period, the longer warranty shall prevail.

2. The awarded vendor/contractor is responsible for all warranty work.

3. If additional warranty options are available, the contractor shall provide them to RTA for consideration at the time the RFP is submitted.

INVOICING

1. Invoicing shall be upon completion of the work, unless otherwise agreed upon by the parties.

2. The RTA will allow partial payments for materials that are on-site at the RTA or for work that has been completed, both of which require clear documentation and shall be approved in writing by RTA’s Project manager.

PROPOSAL AND AWARD

This Request for Proposals (RFP) will be conducted in two phases:

• Phase One – Qualifications & Technical Evaluation

Proposers will be evaluated based on:

o Design and technical approach o Methodology o Qualifications o Relevant experience o Project schedule

Only the top scored proposals that meet all of RTA's Phase One criteria will be invited to submit their best price in Phase Two.

• Phase Two – Pricing Evaluation

Shortlisted proposers from Phase One will be invited to submit their best price.

RTA intends to award a single contract to one qualified proposer capable of furnishing and installing a complete, fully operational garage door system that meets all of RTA's design, operational, and performance requirements.

Contract Terms (Requirements Contract)

1. Contract Pricing

This is a fixed price contract. All prices offered and accepted are firm for the duration of the contract. Contractors may not change or negotiate contract prices after award.

Except as provided in this contract, no special fees or expenses shall be charged directly to the RTA.

2. Contract Duration

The duration or term of this contract shall be for twelve (12) months. RTA reserves the right to award this contract to one or more contractors.

The Greater Dayton Regional Transit Authority may extend the term of this contract by written notice to the Contractor within 30 days, provided that the RTA shall give the

Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the RTA to an extension. If the

RTA exercises this option, the extended contract shall be considered to include this option provision. The total duration of this contract, including the exercise of any options under this clause, shall not exceed twelve (12) months.

3. Quantity and Delivery Requirements

There is no set quantity nor delivery schedule for this contract. Goods and/or services shall be provided as required by RTA. Awarded vendors responsible for meeting all requirements for the awarded items over the contract period. No guarantee is made or implied as to the minimum quantities that may be ordered for the duration of the contract.

INSTRUCTIONS TO PROPOSERS

Greater Dayton RTA Background

History

RTA is an independent political subdivision of the State of Ohio organized pursuant to

Ohio Revised Code Section 306.30 through 306.71, inclusive, as amended.

The RTA was created on September 6, 1971, pursuant to the Revised Code, by ordinances of the Councils of the City of Dayton and the City of Oakwood. After completing the purchase of the assets of City Transit, the major privately owned public transportation system in the area, the RTA became operational on November 5, 1972. In

September 1980, after the approval in the preceding April by the voters of the County of a one-half percent sales and use tax of unlimited duration for all purposes of the RTA, the boundaries of the RTA were extended to be co-extensive with the boundaries of

Montgomery County and parts of Greene County.

Governing Body

All power and authority of the RTA is vested in and exercised by its nine (9) member

Board of Trustees.

Proposal Submission Instructions

The Greater Dayton Regional Transit Authority, hereinafter called "RTA", requests bids for 600 Longworth Garage Door Project, hereinafter called "above-named project" or by the specific project name, under the following requirements and conditions, which shall be considered an essential part of the contract documents.

1. Submission and Modification

Submissions are due electronically by 10:00 am, Dayton (Eastern) time on Tuesday, July 7, 2026, through OpenGov. Any submission received after the exact date and time specified will not be considered.

Submissions may be modified online through OpenGov prior to the due date and time by unsubmitting a bid or proposal and making modifications and then re-submitting.

In addition, any costs incurred while preparing a bid or proposal submission, including site visits, will not be reimbursed by RTA.

2. Requests for Clarification

All requests for clarifications or changes must be submitted through the Q&A Section of the project on OpenGov prior to the stated due time and date.

Any new or relevant information given to any one contractor will be furnished to all contractors as addenda to this procurement.

3. Proposal Evaluation

RTA reserves the right to reject any or all Proposals. Issuance of this solicitation does not bind RTA to award a contract, nor does RTA in any way assume liability for expense incurred by Proposer in preparation of its Proposal. This RFP and the resulting

Proposals shall be used as the basis for contract negotiation.

During the evaluation, negotiation and selection process, evaluation committee members may not disclose any information regarding the procurement. Except for the identity and background of the successful proposer and the contract price, all information provided by proposers remains confidential after the conclusion of the process, to the extent permitted by law.

4. Contract Award

The RTA reserves the right to postpone, accept or reject any proposal, to waive any informalities in the proposals received, and to award the contract(s) to the best responsive and responsible proposer. In awarding a contract(s), the RTA reserves the right to consider all elements entering the determination of the responsibility of the proposer. Any proposal that is incomplete, conditional, obscure, or contains additions not called for or irregularities of any kind, may be cause for rejection of the proposal.

Contract(s) for the purchase of goods and/or services may be awarded within 90 calendar days from the date upon which proposals were received to the best proposer(s) the RTA deems responsive and responsible.

In the event a single proposal is received, the RTA will conduct a price and/or cost analysis of the proposal. A price analysis is the process of examining and evaluating a price submitted without examining in detail the separate cost elements and the profit included in the cost proposal. It should be recognized that a price analysis through comparison to other similar procurements must be based upon an established or competitive price of the elements used in the comparison. The comparison must be made to a purchase of similar quantity and involving similar specifications. Where a difference exists, a detailed analysis must be made of this difference and the costs associated thereto. RTA has the right to enter into a negotiated procurement should only a single proposal be received.

Where a valid price analysis is impossible to obtain, the RTA may need to conduct a cost analysis of the proposal price. Competent and experienced auditors or price analysts shall make the price and/or cost analysis an engineer's estimate or comparison of the prices involved is insufficient.

5. Funding

The proposed contract shall be funded in part from the Federal Transit Administration

(FTA) and the Ohio Department of Transportation (ODOT). Each vendor shall examine all contract documents noting particularly all requirements, which will affect the contractor's work.

6. Specified Material and "Approved Equals"

1. Contractors shall furnish with their submission, as an integral part thereof, complete descriptions and specifications of the product they propose to furnish.

When the descriptions and specifications of the product meet the description and specifications provided in the solicitation document, no additional submission is required.

2. Where brand names or specific items or processes are used in the specifications, consider the term "or approved equal" to follow. However, a request for approval for any proposed substitution as an equal must be submitted in writing.

3. For all items listed and which are described or defined by dimensions or another measure of physical characteristics or performance, it is understood that such information indicates the character of the required items and so strict interpretations with respect to nonessential details shall not be made as to limit competition among manufacturers of substantially equivalent items.

A. Whenever this specification defines the material or article required by using a proprietary product or of a manufacturer or vendor, rather than by using descriptive detail of substance and function, the term "or equal" always is understood to follow immediately the name of the make, vendor or proprietary product. An item of material shall be considered equal to the item so named in the specifications if: (1) it is at least equal in quality, durability, appearance, strength, and design; (2) it will perform at least equally the function imposed by the general design for the material or equipment being purchased; and (3) it conforms substantially, even with deviations, to the detailed requirements for the item in this specification.

B. Whenever in this specification the names of one or more manufacturers are mentioned as indicating that their product will comply with a particular specification or where specific trade names are mentioned, it is not intended to exclude products of other manufacturers whose names or symbols have not been provided, only however, that such products conform to the detailed requirements for the item as indicated in the specifications.

4. Bidders and Proposers shall be responsible for providing the RTA with information in the latest applicable revision of any part or process specifically called for in the specifications for consideration.

5. Only standard parts of units that conform in material, design, and workmanship to the best procedure known in the industry shall be used. No reconditioned or obsolete parts shall be used. All parts shall be identical and interchangeable in its class. All manufactured articles, material, and equipment shall be applied, installed, connected, erected, used, cleaned, adjusted and conditioned as directed by the manufacturer unless herein specified to the contrary.

7. Requesting an Approved Equal

To request an approved equal, contact Michelle Collier at mcollier@greaterdaytonrta.org prior to the final date for questions and clarifications which is Monday, June 29, 2026. Any request for approved equal must include a formal product sheet that lists all relevant specifications that are included in the scope of work of this project. If there are required specifications that are not addressed or the proposed equal has insufficient specifications, the proposed equal will not be approved.

8. Protest Procedures

RTA will hear and consider a sustainable protest regarding its procurement actions in accordance with the below procedures. Due to the significantly limited role of FTA in protests, it is anticipated that the majority of all protests will be evaluated, and the final decision rendered by RTA. RTA intends to provide a thorough review of all sustainable protests. The RTA's primary concern is the timely procurement of needed capital equipment, supplies, or services. Therefore, it does not intend to allow the filing of bid or proposal protests to unnecessarily delay the procurement process.

DEFINITIONS

1. Protest: A protest is a written objection by a potentially interested party to a solicitation or award of a contract over the small purchase threshold. An interested party must be an actual or prospective bidder or proposer whose direct economic interest would be affected by the award or failure to award the applicable contract in accordance with FTA Circular 4220.1.

2. Pre-Submission: A written objection is made during the solicitation phase and is received before the bid opening or proposal due date.

3. Pre-Award: A written objection is made before an award and is received after the bid opening or proposal due date, but before award of the contract.

4. Post-Award: A written objection made by an unsuccessful offeror and received after the Board approves award of the contract.

SUBMITTAL PROCESS

1. Before Protest

The contractor should contact or make an appointment with the solicitation’s procurement representative to resolve any issues.

2. Filing a Protest

Protests may be filed during the following:

A. Solicitation phase must be submitted no later than five (5) business days before the closing of said solicitation. If the protester fails to meet this deadline, protests based on those solicitation issues may not be allowed.

B. Pre-award must be received no later than five (5) business days after the bid opening or proposal due date.

C. Post-award must be received at least five (5) business days after the Board approves contract award.

3. Protest Submittals

Protest shall include, at a minimum:

A. The name and address of the protesting party and its relationship to the procurement are sufficient to establish that an interested party is filing the protest.

B. Identity of the contact person for the protester, including name, title, address, telephone, fax, and e-mail addresses. If the contact point is a third party representing the protester, the same information must be provided, plus a statement defining the relationship between the protester and the third party.

C. The name and number of the solicitation or contract.

D. A description of the nature of the protest, referencing the portion(s) of the solicitation involved.

E. Identification of the provision(s) of any law, regulation, or other governance upon which the protest is based.

F. A complete discussion of the basis for the protest, including all supporting facts, documents, or data.

G. A statement of the specific relief requested.

H. State if an informal conference is wanted to discuss the protest with RTA.

I. Submit the protest in writing by certified mail or another delivery method by which receipt can be verified and address it to:

Director of Procurement

Greater Dayton Regional Transit Authority

4 S. Main StreetDayton, OH 45402

4. Protest Determination

A. Director of Procurement or designee will review the protest submittal to determine if sustainable.

B. If not sustainable, the protester will be notified in writing within ten (10) business days of receipt of the protest.

C. If sustainable and an informal conference is requested, the protester will be notified in writing of the location and time within three (3) business days of such notice.

D. A decision will be made in writing and sent to the protester within ten (10) business days after receipt of the protest. Such a decision is final.

5. Request for Reconsideration

A. The protester shall deliver the request to the Chief Executive Officer (CEO) with a copy to the Director of Procurement within five (5) business days of receipt of the initial decision. The request shall state the reason(s) why the decision should be reconsidered and any information to support such a position.

B. The CEO shall review and decide on the request for reconsideration and issue a written decision to the protester within ten (10) business days of receipt of the request. Such a decision is final.

9. Confidentiality of Proposals

The RTA will be exempt from disclosure of proprietary information, trade secrets, and confidential commercial and financial information submitted. Any such proprietary information or confidential commercial or financial information that the contractor believes should be exempted from disclosure shall be specifically identified and marked as such. Blanket type identification by designating whole pages or sections as containing proprietary information, trade secrets, or confidential commercial or financial information will not assure confidentiality. The specific proprietary information, trade secrets, or confidential commercial and financial information must be clearly identified as such.

10. Trade Secret Notification

Under Ohio Law, a bid or proposal document may be a public record unless it meets an exception under the Public Records Law. One such exception is trade secrets and are treated with confidentiality. However, the contractor must notify the RTA in all of their submitted documents as to which portions of their submission constitute trade secrets and are to be treated as confidential. It is the responsibility of the submitting party to mark those parts of the submission which you wish to have treated as confidential.

While this does not assure that these portions of the document will constitute a trade secret and be exempt from public records requests under Ohio Law, in the absence of notice from you to us that those documents are to be treated as trade secrets and to be held confidential, they will be made available to the public upon a public records request unless another exception applies to exempt them from disclosure.

Terms & Conditions

The Greater Dayton RTA's General Terms and Conditions are attached to this solicitation in Attachments B.

FTA REQUIRED CLAUSES

Contractor shall comply with the following Federal Transit Administration (FTA) requirements. For purposes of these clauses, the RTA is the FTA recipient that is entering the Contract with the Contractor.

No Federal Government Obligation to Third Parties

The RTA and Contractor acknowledge and agree that, notwithstanding any concurrence by the Federal Government in or approval of the solicitation of this Contract, absent the express written consent by the Federal Government, the Federal Government is not a party to this Contract and shall not be subject to any obligations or liabilities to the RTA, Contractor or any other party (whether or not a party to that Contract) pertaining to any matter resulting from the Contract. Contractor shall include the above clause in each subcontract financed in whole or in part with Federal assistance provided by the FTA. It is further agreed that the clause shall not be modified, except to identify the subcontractor who will be subject to its provisions.

Incorporation of FTA Terms

The preceding provisions include, in part, certain Standard Terms and Conditions required by the U.S. Department of Transportation (DOT), whether or not expressly set forth in the preceding contract provisions. All contractual provisions required by DOT, as set forth in FTA Circular 4220.1F, and are hereby incorporated by reference. Anything to the contrary herein notwithstanding, all FTA mandated terms shall be deemed to control in the event of a conflict with other provisions contained in the contract.

Contractor shall not perform any act, fail to perform any act, or refuse to comply with any requests of the RTA that would cause the RTA to be in violation of the FTA terms and conditions. Contractor shall include this clause in each subcontract financed in whole or in part with Federal assistance provided by the FTA.

Program Fraud & False Statements or Related Acts

Contractor acknowledges that the provisions of the Program Fraud Civil Remedies Act of 1986, as amended, 31 U.S.C. § 3801 et seq. and U.S. DOT regulations, "Program

Fraud Civil Remedies," 49 CFR part 31, apply to its actions pertaining to this Project.

Upon execution of the Contract, Contractor certifies or affirms the truthfulness and accuracy of any statement it has made, it makes, it may make, or causes to be made, pertaining to the Contract or the FTA-assisted project for which this contract work is being performed. In addition to other penalties that may be applicable, Contractor further acknowledges that if it makes, or causes to be made, a false, fictitious, or fraudulent claim, statement, submission, or certification, the Federal Government reserves the right to impose the penalties of the Program Fraud Civil Remedies Act of

1986 on Contractor to the extent the Federal Government deems appropriate.

Contractor also acknowledges that if it makes, or causes to be made, a false, fictitious, or fraudulent claim, statement, submission, or certification to the Federal Government under a contract connected with a project that is financed in whole or in part with

Federal assistance originally awarded by FTA under the authority of 49 U.S.C. chapter

53, the Government reserves the right to impose the penalties of 18 U.S.C. § 1001 and

49 U.S.C. § 5323(l) on Contractor, to the extent the Federal Government deems appropriate.

Contractor shall include the above two paragraphs in each subcontract financed in whole or in part with Federal assistance provided by FTA. It is further agreed that the clauses shall not be modified, except to identify the subcontractor who will be subject to the provisions.

Access To Records, Reports, & Sites

Record Retention. Contractor shall retain and will require its subcontractors of all tiers to retain, complete and readily accessible records related in whole or in part to the contract, including, but not limited to, data, documents, reports, statistics, sub-agreements, leases, subcontracts, arrangements, other third-party agreements of any type, and supporting materials related to those records.

Retention Period. Contractor shall comply with the record retention requirements in accordance with 2 CFR § 200.333. Contractor shall maintain all books, records, accounts and reports required under this Contract for a period of at least three (3) years after the date of termination or expiration of this Contract, except in the event of litigation or settlement of claims arising from the performance of this Contract, in which case records shall be maintained until the disposition of all such litigation, appeals, claims or exceptions related thereto.

Access to Records. Contractor shall provide sufficient access to the U.S. Secretary of

Transportation, the Comptroller General of the United States, FTA, the RTA, and their duly authorized representatives to inspect and audit records and information related to performance of this contract as reasonably may be required.

Access to the Sites of Performance. Contractor shall permit FTA, the RTA, and their duly authorized representatives' access to the sites of performance under this Contract as reasonably may be required.

Federal Changes

Contractor shall at all times comply with all applicable federal laws, regulations, requirements, policies, procedures, guidance, and directives, including without limitation those listed directly or by reference in the FTA Master Agreement between the RTA and the FTA, as they may be amended or promulgated from time to time during the term of the Contract. Contractor’s failure to so comply shall constitute a material breach of the

Contract.

Civil Rights

Contractor must prohibit: (a) discrimination based on race, color, religion, national origin, sex (including sexual orientation and gender identity), disability, or age; (b) exclusion from participation in employment or a business opportunity for reasons identified in 49 U.S.C. § 5332; (c) denial of program benefits in employment or a business opportunity identified in 49 U.S.C. § 5332; and (d) discrimination identified in

49 U.S.C. § 5332, including discrimination in employment or a business opportunity identified in 49 U.S.C. § 5332.

Contractor must follow the most recent edition of FTA Circular 4702.1, “Title VI

Requirements and Guidelines for Federal Transit Administration Recipients,” to the extent consistent with applicable federal laws, regulations, requirements, and guidance.

However, FTA does not require an Indian Tribe to comply with FTA program specific guidelines for Title VI when administering its agreement supported with federal assistance under the Tribal Transit Program.

Contractor must comply with: (a) Title VI of the Civil Rights Act of 1964, as amended, 42

U.S.C. § 2000d, et seq.; (b) U.S. DOT regulations, “Nondiscrimination in Federally-

Assisted Programs of the Department of Transportation – Effectuation of Title VI of the

Civil Rights Act of 1964,” 49 CFR Part 21; and (c) Federal transit law, specifically 49

U.S.C. § 5332; and

Contractor must follow: (a) the most recent edition of FTA Circular 4702.1, “Title VI

Requirements and Guidelines for Federal Transit Administration Recipients,” to the extent consistent with applicable federal laws, regulations, requirements, and guidance;

(b) U.S. DOJ, “Guidelines for the enforcement of Title VI, Civil Rights Act of 1964,” 28

C.F.R. § 50.3; and (c) all other applicable federal guidance that may be issued.

Equal Employment Opportunity

1. Federal Requirements and Guidance. Contractor must prohibit discrimination based on race, color, religion, sex, sexual orientation, gender identity, or national origin. Contractor must also comply with: (a) Title VII of the Civil Rights Act of

1964, as amended, 42 U.S.C. § 2000e, et seq.; (b) Title I of the Americans with

Disabilities Act of 1990, as amended, 42 U.S.C. §§ 12101, et seq.; (c) Executive

Order No. 11246, “Equal Employment Opportunity” September 24, 1965 (42

U.S.C. § 2000e note), as amended by any later Executive Order that amends or supersedes it in part and is applicable to federal assistance programs; (d) federal transit law, specifically 49 U.S.C. § 5332, as provided in section 12 of this Master

Agreement; and (e) FTA Circular 4704.1 “Equal Employment Opportunity (EEO)

Requirements and Guidelines for Federal Transit Administration Recipients.”

Further, Contractor must follow other federal guidance pertaining to EEO laws, regulations, and requirements.

2. Affirmative Action. If required to do so by U.S. DOT regulations (49 CFR Part 21) or U.S. Department of Labor regulations (41 C.F.R. chapter 60), Contractor must take affirmative action that includes but is not limited to: (a) recruitment advertising, recruitment, and employment; (b) rates of pay and other forms of compensation; (c) selection for training, including apprenticeship, and upgrading;

and (d) transfers, demotions, layoffs, and terminations.

3. Indian Tribe. Contractor recognizes that Title VII of the Civil Rights Act of 1964, as amended, exempts Indian Tribes under the definition of “Employer.”

Free Speech & Religious Liberty

All Federal funding must be expended in full accordance with the U.S. Constitution, Federal Law, and statutory and public policy requirements, including but not limited to those prohibiting discrimination and protecting free speech, religious liberty, public welfare, and the environment.

Disadvantaged Business Enterprises Requirements

It is the policy of the RTA and the United States Department of Transportation (“DOT”) that Disadvantaged Business Enterprises (“DBE’s”), as defined herein and in the

Federal regulations published at 49 C.F.R. part 26, shall have an equal opportunity to participate in DOT-assisted contracts.

The contractor or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 C.F.R. part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the RTA deems appropriate, which may include, but is not limited to:

• Withholding monthly progress payments;

• Assessing sanctions;

• Liquidated damages; and/or

• Disqualifying the contractor from future bidding as non-responsible. 49 C.F.R. §

26.13(b).

Prime contractors are required to pay subcontractors for satisfactory performance of their contracts no later than 30 days from receipt of each payment the RTA makes to the prime contractor. 49 C.F.R. § 26.29(a).

Finally, for contracts with defined DBE contract goals, the contractor shall utilize the specific DBEs listed unless the contractor obtains the RTA’s written consent; and that, unless the RTA’s consent is provided, the contractor shall not be entitled to any payment for work or material unless it is performed or supplied by the listed DBE. 49

C.F.R. § 26.53(f) (1).

Prompt Payment

The contractor is required to pay its subcontractors performing work related to this contract for satisfactory performance of that work no later than 30 days after the contractor’s receipt of payment for that work. In addition, the contractor is required to return any retainage payments to those subcontractors within 30 days after the subcontractor's work related to this contract is satisfactorily completed.

The contractor must promptly notify the RTA, whenever a DBE subcontractor performing work related to this contract is terminated or fails to complete its work and must make good faith efforts to engage another DBE subcontractor to perform at least the same amount of work. The contractor may not terminate any DBE subcontractor and perform that work through its own forces or those of an affiliate without prior written consent of RTA.

Energy Conservation

Contractor shall comply with mandatory standards and policies relating to energy efficiency, which are contained in the state energy conservation plan issued in compliance with the Energy Policy and Conservation Act (42 U.S.C. §§ 6321 et seq.).

Safe Operations of Motor Vehicles

Seat Belt Use. Contractor is encouraged to adopt and promote on-the-job seat belt use policies and programs for its employees and other personnel that operate company-owned vehicles, company- rented vehicles, or personally operated vehicles. The terms

“company-owned” and “company-leased” refer to vehicles owned or leased either by

Contractor or RTA.

Distracted Driving. Contractor shall adopt and enforce workplace safety policies to decrease crashes caused by distracted drivers, including policies to ban text messaging while using an electronic device supplied by an employer, and driving a vehicle the driver owns or rents, a vehicle Contactor owns, leases, or rents, or a privately-owned vehicle when on official business in connection with the work performed under this

Contract.

Subcontracts. Contractor shall insert the substance of this clause, including this paragraph, in all subcontracts that exceed the micro-purchase threshold, as defined in

Federal Acquisition Regulation 2.101 on the date of subcontract award.

Contractor Policies To Ban Text Messaging While Driving

Definitions. As used in this clause: (1) "driving" means operating a motor vehicle on an active roadway with the motor running, including while temporarily stationary because of traffic, a traffic light, stop sign, or otherwise (note: "driving" does not include operating a motor vehicle with or without the motor running when one has pulled over to the side of, or off, an active roadway and has halted in a location where one can safely remain stationary); and (2) “text messaging” means reading from or entering data into any handheld or other electronic device, including for the purpose of short message service texting, e-mailing, instant messaging, obtaining navigational information, or engaging in any other form of electronic data retrieval or electronic data communication (note: “text messaging” does not include glancing at or listening to a navigational device that is secured in a commercially designed holder affixed to the vehicle, provided that the destination and route are programmed into the device either before driving or while stopped in a location off the roadway where it is safe and legal to park).

Executive Order. This clause implements Executive Order 13513, Federal Leadership on Reducing Text Messaging While Driving, dated October 1, 2009. Contractor is encouraged to adopt and enforce policies that ban text messaging while driving company-owned/rented vehicles, Government-owned vehicles, and privately-owned vehicles when on official Government business or when performing any work for or on behalf of the Government. Contractor is also encouraged to conduct initiatives in a manner commensurate with the size of the business, such as: (1) establishment of new rules and programs or reevaluation of existing programs to prohibit text messaging while driving; and (2) education, awareness, and other outreach to employees about the safety risks associated with texting while driving.

Subcontracts. Contractor shall insert the substance of this clause, including this paragraph, in all subcontracts that exceed the $10,000

Prohibited Telecommunications/Surveillance Services/Equipment.

The RTA is prohibited from obligating or expending loan or grant funds to: procure or obtain, extend or renew a contract to procure or obtain, or enter into a contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.

Contractor shall not provide covered telecommunications equipment or services in the performance of the Contract. As described in Public Law 115-232, section 889, covered telecommunications equipment is: (A) telecommunications equipment produced by

Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities); (B) video surveillance and telecommunications equipment produced by

Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities) for the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes; (C) Telecommunications or video surveillance services provided by such entities or using such equipment; and

(D) telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.

Trafficking In Persons

Contractor and its subcontractors or their employees shall not: (A) engage in severe forms of trafficking in persons during the Contract Term; (B) procure a commercial sex act during the Contract Term; or (C) use forced labor in the performance of the

Contract. Contractor shall inform RTA immediately of any information Contractor receives from any source alleging a violation of a prohibition in this section. RTA may terminate this Contract for any violation of this section; such right of termination is in addition to all other remedies for noncompliance that are available to the RTA.

Termination

The termination rights under this Contract are in addition to, and in no way limit, the

Federal Government’s right to terminate as described in 2 CFR § 200.340.

Termination for Convenience

RTA may terminate this contract, in whole or in part, at any time by written notice to the

Contractor when it is in RTA’s best interest. The Contractor shall be paid its costs, including contract close-out costs, and profit on work performed up to the time of termination. The Contractor shall promptly submit its termination claim to RTA to be paid the Contractor. If the Contractor has any property in its possession belonging to

RTA, the Contractor will account for the same and dispose of it in the manner RTA directs.

Termination for Default

If the Contractor does not deliver supplies in accordance with the contract delivery schedule, or if the contract is for services, the Contractor fails to perform in the manner called for in the contract, or if the Contractor fails to comply with any other provisions of the contract, the RTA may terminate this contract for default. Termination shall be affected by serving a Notice of Termination on the Contractor setting forth the manner in which the Contractor is in default. The Contractor will be paid only the contract price for supplies delivered and accepted, or services performed in accordance with the manner of performance set forth in the contract. If it is later determined by the RTA that the

Contractor had an excusable reason for not performing, such as a strike, fire, or flood, events which are not the fault of or are beyond the control of the Contractor, the RTA, after setting up a new delivery of performance schedule, may allow the Contractor to continue work, or treat the termination as a Termination for Convenience.

Opportunity to Cure

The RTA, in its sole discretion may, in the case of a termination for breach or default, allow the Contractor ten (10) business days in which to cure the defect. In such case, the Notice of Termination will state the time period in which cure is permitted and other appropriate conditions.

If Contractor fails to remedy to RTA's satisfaction the breach or default of any of the terms, covenants, or conditions of this Contract within ten (10) business days after receipt by Contractor of written notice from RTA setting forth the nature of said breach or default, RTA shall have the right to terminate the contract without any further obligation to Contractor. Any such termination for default shall not in any way operate to preclude RTA from also pursuing all available remedies against Contractor and its sureties for said breach or default.

Waiver of Remedies for any Breach

In the event that RTA elects to waive its remedies for any breach by Contractor of any covenant, term or condition of this contract, such waiver by RTA shall not limit RTA’s remedies for any succeeding breach of that or of any other covenant, term, or condition of this contract.

American With Disabilities Act

The contractor agrees to comply with all applicable requirements of section 504 of the

Rehabilitation Act of 1973, as amended, 29 U.S.C. § 794, which prohibits discrimination on the basis of handicaps, with the Americans with Disabilities Act of 1990 (ADA), as amended, 42 U.S.C. §§ 12101 et seq., which requires that accessible facilities and services be made available to persons with disabilities, including any subsequent amendments to that Act, and with the Architectural Barriers act of 1968, as amended, 42 U.S.C. §§ 4151 et seq., which requires that buildings and public accommodations be accessible to persons with disabilities, including any subsequent amendments to that

Act. In addition, the contractor agrees to comply with any and all applicable requirements issued by the FTA, DOT, DOJ, U.S. GSA, U.S. EEOC, U.S. FCC, any subsequent amendments thereto and any other nondiscrimination statute(s) that may apply to the Project.

Notification To FTA

If a current or prospective legal matter that may affect the Federal Government emerges, Contractor must promptly notify the RTA, which must then promptly notify the

FTA Chief Counsel and FTA Regional Counsel for Region 5. Contractor must include an equivalent provision in its sub agreements at every tier for any agreement that is a

“covered transaction” according to 2 C.F.R. §§ 180.220 and 1200.220.

1. Types of Legal Matters Requiring Notification.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .