60-80500-26-EM011_Emergency_Procurement Onate Bridge Justification FINAL 02Mar2026 Signed.pdf.PDF
PDF 308 KB Posted
- Attached to
- ONATE BRIDGE AMENDMENT NO. 1
- Solicitation number
- 60-80500-26-EM011
- Issued by
- Rio Arriba County, New Mexico
About this file
This is an Emergency Determination Form and Amendment No. 1 justification filed by the New Mexico Department of Transportation for emergency procurement related to interim scour stabilization at the Onate Street Bridge (Bridge No. 1836) at Pier 10. The scope of work includes construction of bypass relief channels at piers P7, P8, and P9, excavation and spoil hauling, expanded Stormwater Pollution Prevention Plan (SWPPP) support with Best Management Practices (BMPs) including straw wattles, channel stabilization with revised quantities and placement methods, and restoration activities. The area of disturbance has been expanded from 1 acre to 2 acres to accommodate relief channel excavation and staging. The emergency procurement was triggered by an underwater inspection conducted in late February 2025 that identified significant scour around Pier 10, creating a serious threat to public safety and property; a follow-up inspection in late fall 2025 provided updated findings that required scope revisions. The contract is with AUI Inc. (PO Box 9825, Albuquerque, NM 87119) with an anticipated term of 10 months and completion targeted for mid-May 2026.
The original contract amount under EMERG05 was $1,517,750.00 (excluding Gross Receipts Tax), with Amendment No. 1 revising the total to $1,804,114.00 (less GRT), resulting in a revised contract amount of $1,960,846.40 including GRT at 8.6875% applicable to Espanola/Santa Clara Pueblo. The additional funding request above the original NTE is $443,096.40, necessitated by updated flow modeling indicating that the original stabilization measures could be lost or damaged if spring runoff flows exceed approximately 1,000 cubic feet per second, requiring additional materials and work to increase the maximum design flow capacity to approximately 1,500 cfs. The Department justified the emergency procurement under NMSA 1978, Section 13-1-127, citing the immediate need to address a serious threat to public health, welfare, safety, and property that cannot be acquired through normal procurement methods. The Department commits to completing this emergency procurement once the emergency condition is resolved and is evaluating longer-term alternatives and permanent countermeasures for the bridge's other piers, including updating the Statewide Bridge Repair Price Agreement to prevent similar emergency procurements in the future.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2022 Emergency Form
STATE OF NEW MEXICO
EMERGENCY DETERMINATION FORM
The emergency procurement method (NMSA 1978, Section 13-1-127) may only be used when the service, construction or item of tangible personal property procured:
1. is needed immediately to:
a. control a serious threat to public health, welfare, safety or property caused by a flood, fire, epidemic, riot, act of terrorism, equipment failure or similar event; or
b. plan or prepare for the response to a serious threat to public health, welfare, safety or property caused by a flood, fire, epidemic, riot, act of terrorism, equipment failure or similar event; and
2. cannot be acquired through normal procurement methods.
a. The agency entering into an emergency procurement should employ a competitive process to the extent practicable under circumstances.
The purchase or lease of heavy road equipment is not allowed under the emergency procurement statute.
The state purchasing agent or a central purchasing office that makes an emergency procurement shall outline its determination of the basis for the procurement and its selection of the contractor in writing and include the writing in the procurement file. (That writing can be made on this form.)
Promptly thereafter:
• the state purchasing agent shall post notice of the procurement on its website; or
• the central purchasing office shall post notice of the procurement on its website, if it maintains one, and shall transmit the notice to the state purchasing agent for posting on the state purchasing agent's website.
NOTE: the state purchasing agent or a central purchasing office that makes an emergency procurement to plan or prepare for the response to a serious threat to public health, welfare, safety or property caused by a flood, fire, epidemic, riot, act of terrorism, equipment failure or similar event shall account for the money spent in making the procurement and report on that accounting to the legislative finance committee and the department of finance and administration within sixty days after the end of the fiscal year in which the procurement was made.
I. Name of Agency: New Mexico Department of Transportation
Agency Chief Procurement Officer: Christina Baca
Telephone Number: 505-469-8800
EMERG05 Emergency Procurement Amendment No. 1
Docusign Envelope ID: 8945CD82-D560-4A7A-BEA6-5D3E0EB5D07C
II. Name of Contractor: AUI Inc.
Address of Contractor: PO Box 9825
Albuquerque, NM 87119
Amount of prospective contract: $1,804,114.00 plus $156,732.40 GRT (Española/Santa
Clara Pueblo @ 8.6875%) for a Total Amount of $1,960,846.40. Amount may change depending on field conditions and river flows.
Term of prospective contract: 10 Months
III. Thoroughly list the services (scope of work), construction or items of tangible personal property being procured:
This addendum supports Amendment No. 1 to Contract EMERG05 for interim scour stabilization at Bridge No. 1836 (Oñate Street Bridge) at Pier 10. The amendment revises the scope and quantities from the original conceptual emergency package to a constructible, safety-appropriate scope based on updated flow modeling and changing field conditions.
An additional underwater inspection was performed in late fall 2025. The inspection results were received after the conceptual plan had already been used as the basis for contractors to develop their proposed scopes of work and pricing. Because the inspection information was not available in time, the conceptual plan could not be updated prior to bid submittals. The later-received inspection findings indicated changing site conditions, requiring revisions to quantities and erosion control measures to maintain constructability and safety during higher spring runoff flows.
Updated flow modeling indicates that the originally conceptual stabilization measures are likely to be lost or damaged if spring runoff flows increase above approximately
1,000 cfs (cubic feet per second). The revised scope adds materials and work necessary to increase the maximum design flow that can be safely carried during construction and to better preserve the installed countermeasures, targeting approximately 1,500 cfs.
Revised scope elements include:
• Construction of bypass relief channels (P7, P8, and P9) and associated excavation and spoil hauling to reduce hydraulic demand at Pier 10 and support the increased maximum flow capacity (approximately 1,500 cfs) based on prior years run-off.
• Increase in area of disturbance from 1 acre to 2 acres to accommodate relief channel excavation, staging, and additional erosion control measures.
• Expanded SWPPP support and additional BMPs (including straw wattles) needed due to the increased disturbed area and relief channel work, including additional clearing/grubbing, seeding, and restoration quantities.
• Revised channel stabilization quantities and placement methods as required under the updated flow assumptions, including increased materials where needed to protect the work under higher flows.
IV. Provide an explanation for the justification of the procurement including a description of the emergency condition(s) requiring use of emergency procurement and the practicable competition utilized in compliance with NMSA 1978, Section 13-1-127.
An underwater inspection received in late February 2025 identified significant scour at and around Pier 10, including significant loss of riverbed material and exposure of bridge foundation elements. Subsequent engineering evaluation determined the condition represented a serious threat to public safety and property because a single major rainfall or high-flow event can accelerate scour in hours, not weeks, further reducing foundation support and triggering sudden undermining, settlement, or sudden catastrophic bridge failure with little, if any, practical warning.
The bridge was closed based on that determination because doing otherwise would be to knowingly put the travelling public at risk with an unaddressed, known structural vulnerability. Although a catastrophic failure has not occurred to date, but that outcome reflects timing, not the elimination of risk. The hazard will intensify quickly during future high-flow events and evolving scour conditions.
The bridge was designed using historic standards and assumptions that predate modern understanding of scour, hydraulic loading, and shallow foundation vulnerability developed through decades of engineering practice. Modern engineering practice explicitly recognizes these risks, and the observed conditions warrant emergency stabilization measures.
The Department is also evaluating longer-term alternatives to mitigate scour risk at the other bridge piers that are not currently in immediate danger, including additional inspection, hydraulic and geotechnical analysis, and development of permanent countermeasures as part of a future project.
A follow-up underwater inspection was performed in late fall 2025, and the results were received in December 2025 after the conceptual stabilization plan had already been provided to the contractor to develop their proposed scope of work and pricing.
Due to the timing of receipt, it was not feasible to incorporate the follow-up inspection findings into the conceptual plan. Because the repairs must be performed in the active river channel, work must be completed prior to spring runoff exceeding 1,500 cfs.
Work within the river cannot be performed once flows exceed approximately 1,500 cfs due to overtopping of the diversion.
The original emergency quantities and approach were conceptual and required refinement after updated flow modeling and constructability planning. The updated modeling indicates that, if spring runoff flows exceed approximately 1,000 cfs, the work and installed countermeasures are likely to be lost or damaged. Therefore, additional work and materials are required to increase the maximum flow capacity during construction to approximately 1,500 cfs and to better preserve the emergency stabilization measures. Additional recent underwater inspections also indicated changing site conditions that required adjustments to the stabilization approach and quantities.
V. Describe what measures are being taken to minimize the duration and effect of this particular emergency procurement (for example: is the emergency only in place until a competitive process can be completed, etc.).
This purchase order will be only in place until this emergency is resolved. We are anticipating that this construction will be completed by mid-May 2026.
VI. Describe what measures the Agency will take in the future to prevent/mitigate use of an emergency procurement under similar circumstances.
This bridge was built in 1940; the NMDOT now designs bridge structures to have footings or piles which are to depths which would survive scour caused by a 500 year flood event.
The NMDOT will determine if adding items to the Statewide Bridge Repair Price
Agreement is warranted in light of this project. Before putting it out for bid, the
NMDOT reviews the price agreement for changes such as this.
Funding Summary (for Amendment Support)
Reference Amount Notes
Original Contract NTE (less GRT) $1,517,750.00 Executed EMERG05
Revised Proposal Subtotal (less GRT) $1,804,114.00 Additional work/materials to increase max flow capacity
Estimated Revised NTE (incl. GRT @
8.6875%)
$1,960,846.40 Subject to Procurement confirmation of
GRT
Requested above the original NTE: $443,096.40
Certified by: Date: _______________
Agency Chief Procurement Officer
Agency Approval by: Date: _______________
Cabinet Secretary/Governmental Entity Head or Designee
Docusign Envelope ID: 8945CD82-D560-4A7A-BEA6-5D3E0EB5D07C
03/02/26
03/03/26
| 2026-03-03T13:26:41-0800 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .