This is a specifications and requirements document for a water playground safety netting installation project issued by the Parks and Recreation Division for the County of Broward, Florida. The project involves manufacturing and installing safety netting for the Paradise Cove water playground located at C.B. Smith Park in Pembroke Pines, Florida. The netting system must meet detailed specifications including 100% polyester filament construction with 3/16-inch minimum diameter cord, mesh openings not exceeding 1 inch square, UV treatment, rot resistance, sand color, and a melting point greater than 100 degrees Fahrenheit. The netting must be secured to water playground equipment using stainless steel hooks or anchors and braided fishing line. All bidders are recommended to conduct site visits, with final field measurements being the vendor's responsibility. Vendors must demonstrate they are regular providers of similar safety netting through verifiable references. Delivery is FOB Destination with work completion required within 30 calendar days of purchase order receipt. Questions and clarifications must be submitted through Bonfire BPRO by the specified questions due date, with all solicitation responses required to be submitted electronically through the same platform by the closing deadline.

The contract is a fixed-price engagement with a one-year warranty requirement from installation. No pricing information, set-asides, funding sources, or award amounts are specified in this requirements document. The vendor is responsible for all labor, materials, and incidentals necessary to complete the installation. Project management contact information is provided through Brian Mclaughlin at 954-357-5181 or Sean Gilmartin at 954-357-5170 for site inspection scheduling.

View the file

Other files

File Type Posted
2-Insurance Requirements - Quotes Bids.docx DOCX document
8-Drawings 1-34.pdf PDF
1-CAB Sales Tax Exemption Certificate.pdf PDF
7-Insurance Requirement- Water Playground Safety Netting.pdf PDF
5-Anti-Human Trafficking Affidavit.docx DOCX document
3-Vendor Questionnaire - CABs.docx DOCX document
4-General Conditions - Quotes Bids.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications and Requirements

Water Playground Safety Netting

Scope: Provide all labor, materials, and incidentals to manufacture and install safety netting for the Paradise Cove water playground located at C.B. Smith Park per the specifications and drawings.

1. Netting must be 100% polyester filament, tested and approved for outdoor use.

2. Netting cord must be no less than 3/16 inch in diameter.

3. Mesh must be not greater than 1 ¾ inch square opening measured between the joints. Each mesh piece must be a continuous piece. Seamed, spliced or pieces otherwise joined together to satisfy the dimensions will not be accepted.

4. Netting must be UV treated and rot resistant.

5. Netting must be sand color.

6. Netting melting point must be greater than 100 degrees Fahrenheit.

7. Netting must include stainless steel hooks or anchors to connect to the eye bolts attached to the water playground equipment. The preferred type of hook is pictured below.

8. Netting must be attached to the water slides using a braided fishing line.

9. The netting system must be warranted for at least one (1) year from installation.

10. All bidders are recommended to attend a site visit.

11. Vendor is responsible for final field measurements. No extra compensation will be provided for failure to visit the site and understand site conditions.

12. Submission of a bid shall indicate that the vendor is sufficiently familiar with the work to be performed and must be a regular provider of this type of safety netting as evidenced by verifiable references for projects of similar size and scope.

13. Delivery shall be FOB Destination with work completed within 30 calendar days of receipt of purchase order.

14. Project location:

C.B. Smith Park

900 N. Flamingo Road

Pembroke Pines, FL 33028

Project Manager: Brian Mclaughlin, 954-357-5181

To schedule a time to inspect the site, contact Brian Mclaughlin or Sean Gilmartin at 954-357-5170.