MOBILIZATION Section 01 71 13-1
SECTION 01 71 13 - MOBILIZATION
PART 1 - GENERAL
1.1 SCOPE
A. This work consists of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
1.2 MEASUREMENT AND PAYMENT
A. The accepted quantities will be paid for at the contract unit price for item 01 71 13, Mobilization.
B. Progress payments will be made as follows:
1. The Government will pay to the Contractor in the first progress payment the total premium paid by the Contractor to obtain bonds. This payment shall not be in addition to the contract price and will be included in Item 01 71 13, Mobilization.
2. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
3. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
4. Upon completion of all work on the project, any unpaid amount for item 01 71 13, Mobilization, will be paid.
C. The total of all payments will not exceed the original contract amount for item 01 71 13, Mobilization.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 71 13
SITE IMPROVEMENTS Section 32 30 00 - 1
SECTION 32 30 00 – SITE IMPROVEMENTS
PART 1 – GENERAL
1.1 SCOPE: This Section includes the following:
A. Fabrication and installation of (2) single swing steel pipe gate and all apparatuses.
a. Wagon Flat Campground & Rattlesnake Trailhead gates measures approximately 14’. See attached map for approximate location. The final location will be staked by the Contracting Officer Representative (COR) for the pre-bid meeting. It is the contractor’s responsibility to confirm all gate measurement at the pre-bid meeting.
1.2 MEASUREMENT AND PAYMENT: Measurement for work performed under this section will be made under those pay items as listed in the Schedule of Items and will constitute full compensation for all materials, labor, equipment, testing and incidentals necessary to complete the work and provide a complete and operational gate for the site as specified herein and AS SHOWN ON THE DRAWINGS.
PART 2 – PRODUCTS
2.1 Steel gates and all components are to be constructed of Schedule 40 and Schedule 80 steel pipe AS SHOWN ON THE DRAWINGS. After the gate is constructed, all welds completed and all exposed cuts shall be ground smooth, gate is to be powder coated white. Final gate post’s locations shall be determined by the Contracting Officer Representative (COR).
2.2 Signs shall be provided by the contractor and shall be installed AS SHOWN ON THE DRAWINGS.
PART 3 – EXECUTION
3.1 Steel Pipe Gate
a. Install gate AS SHOWN ON THE DRAWINGS.
b. Concrete shall be minimum 3000 psi in accordance with Specification 03 30 00, Cast-In-Place
Concrete.
c. Allow concrete to set a minimum of 7 days before hanging the gate on the gate post.
d. Remove all construction debris generated by the gate install in accordance with Section 01 74 00, Cleaning and Waste Management, prior to final approval.
3.2 All apparatuses shall be fully functional.
END OF SECTION 32 20 00
Wagon Flats & Rattlesnake Barrier
Section 607-2 SPS
SPECIAL PROJECT SPECIFICATIONS
607-2 BARRIER INSTALLATION (11-03)
607-2.01 Description
This work consists of furnishing and installing Barrier Assemblies and Horse Gates. The contractor shall furnish all labor, equipment, and transportation necessary to perform the work in this specification.
607-2.02 Materials
1. The contractor shall furnish Barrier Assemblies and Horse Gates manufactured to conform to the drawings.
2. Materials shall conform to notes on the drawings.
3. The posts will not require concrete and will be directly buried into the native soil.
4. Contractor shall compact soil around new barrier posts to ensure that it is secure and level.
5. All other materials, labor, and incidentals necessary for Barrier installation and Horse Gate shall be furnished by the contractor, and shall be included in the contract price.
607-2.03 Barrier Installation
1. Gate posts shall be erected plumb and in accordance with the details SHOWN ON THE
DRAWINGS.
2. Exact locations will be staked by the COR.
607-2.04 Measurement
The quantity to be measured will be the completed Barriers listed in the SCHEDULE OF ITEMS and accepted under this Section.
607-2.05 Payment
A. The accepted quantities will be paid at the contract unit price shown in the SCHEDULE OF ITEMS.
Wagon Flats & Rattlesnake Barrier
Section 607-2 SPS
B. Payment will be made under:
Pay Item Pay Unit
LF 607-2(1) Construct and Install Barrier Assembly (Steel Pipe)
607-2(2) Furnish and Install Public Walkover, 3 feet long
EA
| Section 202 |
| Section 202 - Removal of Structures & Obstructions |
| Section 602 Minor concrete |
| Section 602 - Minor Concrete Structures |
| Section 602-1 SPS |
| Section 607-2 SPS |
| Barrier Installation |
| Section 607-3 Removable Barrier Installation |
| Removable Steel Pipe Barrier Installation |
| Horse Gate Installation |
| Section 633 Signage |
| Section 633. — PERMANENT TRAFFIC CONTROL |
| Section 836-8 Road Decommissioning Revised 2-20-19 |
| Section 837 Drainage maintenance |
| 1. DESCRIPTION |
| 2. MATERIALS |
| 3. MAINTENANCE REQUIREMENTS |
| 4. MEASUREMENT |
| 5. PAYMENT |
| Section 839 Restore Drainage_Storm Proofing |
| 1. DESCRIPTION |
| 2. MAINTENANCE REQUIREMENTS |
| 3. METHOD OF MEASUREMENT |
| 4. PAYMENT |
| Section 862-2 F.S. Gate Installation |
| Gate Installation |
| Section 881 MOBILIZATION |
| Section 883 CLEANING OF EQUIPMENT |
| Specifications.pdf |
| 01 71 13 Mobilization |
| END OF SECTION 01 71 13 |