6-Division 01 - General Requirements.pdf

PDF 720 KB Posted

Attached to
Kings Grant Pump Station Upgrade - Rebid
Solicitation number
Not on record
Issued by
Chester County, Claysville Borough, Pennsylvania

About this file

This document is the Division 01 General Requirements specification for the King's Grant Pump Station Upgrades project by the Caln Township Municipal Authority in Pennsylvania. The project involves electrical equipment upgrades to an existing wastewater pump station and offsite rebuild of two KSB Model KRT F100-401 pumps (50HP, 3/60/460 VAC, 1800RPM, explosion proof rated) and one Muffin Monster Model 30005-0012-DI hydraulically driven grinder, followed by site restoration. Sealed bids are due electronically via PennBid by 10:00 A.M. local time on Thursday, April 24, 2026, with bid documents available at no cost beginning March 27, 2026. The specification sections establish the contractual framework for scheduling of values, applications for payment, submittals including construction progress schedules and product data, quality control procedures, temporary construction facilities, soil erosion and sediment control measures, and contract closeout requirements.

The contract requires each bid to be accompanied by a bid bond or certified check of not less than ten percent of the bid amount. The successful bidder must furnish performance and payment bonds equal to 100 percent of the contract amount and a maintenance bond equal to fifteen percent of the contract amount. The work is subject to the Pennsylvania Prevailing Wage Act (Act No. 442), and all equipment furnished must carry manufacturer guarantees of not less than twelve months from continuous operation or eighteen months from delivery, whichever occurs first. The contract includes lump sum and unit price payment options for various work items including mobilization/demobilization, demolition and site restoration, fence grounding, pump control panel installation, electrical equipment installation, lighting upgrades, and optional alternates for pump and grinder rebuilds or renewal. Payment applications are submitted monthly using EJCDC Form 1910-8-E, with the contractor responsible for all temporary utilities, water service, sanitary facilities, dust control, and progress cleaning throughout the project duration.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 1

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Contract Considerations

1. Schedule of Values

2. Applications for Payment

3. Change Procedures

4. Alternatives

B. Coordination and Meetings

1. Coordination

2. Field Engineering

3. Preconstruction Meeting

4. Site Mobilization Meeting

5. Progress Meetings

6. Pre-installation Meetings

7. Equipment Electrical Characteristics and Components

8. Cutting and Patching

C. Submittals

1. Submittal Procedures

2. Construction Progress Schedules

3. Product Data

4. Shop Drawings

5. Samples

6. Manufacturer Installation Instructions

7. Manufacturer Certificates

D. Quality Control

1. Quality Assurance-Control of Installation

2. Examination

3. Preparation

4. Tolerances

5. References

6. Mock-ups

7. Testing Laboratory Services

8. Observation Services

9. Manufacturers' Field Services

E. Construction Facilities and Temporary Controls

1. Temporary Electricity

2. Temporary Lighting for Construction Purposes

3. Temporary Heating

4. Temporary Ventilation

5. Telephone Service

6. Temporary Water Service

7. Temporary Sanitary Facilities

8. Barriers and Fencing

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 2

9. Water Control

10. Exterior Enclosures

11. Interior Enclosures

12. Protection of Installed Work

13. Security

14. Access Roads

15. Parking

16. Progress Cleaning and Waste Removal

17. Project Identification

18. Field Offices and Sheds

19. Removal of Utilities, Facilities and Controls

20. Dust Control

F. Material and Equipment

1. Products

2. Transportation, Handling, Storage and Protection

3. Product Options

4. Substitutions

5. Equipment Guarantee

G. Starting of Systems

1. Starting Systems.

2. Demonstration and Instructions.

H. Contract Closeout

1. Contract Closeout Procedures

2. Final Cleaning

3. Adjusting

4. Project Record Documents

5. Operation and Maintenance Manual

6. Spare Parts and Maintenance Materials

7. Other Documentation

1.02 SCHEDULE OF VALUES

A. Submit a printed schedule on EJCDC Form 1910-8-E. Contractor's standard form or electronic media printout will be considered in lieu of EJCDC Form 1910-8-E.

B. Submit Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

See Supplementary Conditions for format relative to a lump sum contract.

1.03 APPLICATIONS FOR PAYMENT

A. Submit three copies of each application on EJCDC Form 1910-8-E.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly.

1.04 CHANGE PROCEDURES

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 3

A. Change Order Forms: EJCDC 1910-8-B.

B. Stipulated Price Change Order: Based on proposal request and Contractor’s fixed price quotation.

C. Unit Price Change Order: For pre-determined unit prices and quantities, the Change Order will be on a fixed unit price basis. For unit costs or quantities of units of work which are not pre-determined, the Change Order price shall be based on a proposal request and Contractor’s proposed unit prices and quantities of units as approved by Engineer.

1.05 ALTERNATIVES

A. Accepted Alternatives will be identified in the Agreement.

B. Coordinate related Work and modify surrounding Work as required.

1.06 COORDINATION

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities.

1.07 FIELD ENGINEERING

A. Verify that field measurements are as indicated on Shop Drawings or as instructed by the manufacturer.

1.08 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting and prior to commencement of the Work for all affected parties.

B. Engineer shall preside at the meeting, record minutes and distribute copies to Owner and all other participants.

1.09 SITE MOBILIZATION MEETING

A. Engineer may schedule a site mobilization meeting after Effective Date of the Agreement and prior to Contractor occupancy for all affected parties.

B. Engineer shall preside at the meeting, record minutes, and distribute copies to Owner and all other participants.

1.10 PROGRESS MEETINGS

A. Resident Project Representative shall schedule and administer meetings throughout progress of the Work on an as-needed basis.

B. Resident Project Representative shall preside at meetings, record minutes, and distribute copies within five (5) working days to Owner, Engineer and all other participants.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 4

1.11 PRE-INSTALLATION MEETINGS

A. When required in individual specification section, convene a pre-installation meeting at Project site prior to commencing work of the section.

1.12 EQUIPMENT ELECTRICAL CHARACTERISTICS AND COMPONENTS

A. Not Used.

1.13 CUTTING AND PATCHING

A. Employ a skilled and experienced installer to perform cutting and patching of new Work.

B. Execute cutting, fitting and patching including excavation and fill, to complete Work, and to:

1. Fit the several parts together, to integrate with other Work.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and non-conforming Work.

4. Remove samples of installed Work for testing.

C. Cut masonry and concrete materials using masonry saw or core drill.

D. Refinish surfaces to match adjacent finishes.

1.14 SUBMITTAL PROCEDURES

A. Submittal form to identify Project, Contractor, Subcontractor or supplier; and pertinent Contract Document references.

B. Apply Contractor's stamp, signed or initialed, certifying that review, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

C. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

D. Revise and resubmit submittals as required; identify all changes made since previous submittal.

1.15 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of the Agreement for Engineer's review.

B. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version. Indicate estimated percentage of completion for each item of Work at each submission.

1.16 PRODUCT DATA

A. Product Data For Review

1. Submit to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 5

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes.

B. Product Data For Information

1. Submit for Engineer’s benefit as contract administrator or for Owner.

C. Product Data For Project Closeout

1. Submit for Owner’s benefit during and after project completion.

D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this project.

1.17 SHOP DRAWINGS

A. Shop Drawings For Review

1. Submit to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes.

B. Shop Drawings For Information

1. Submit for Engineer’s benefit as contract administrator or for Owner.

C. Shop Drawings For Project Closeout

1. Submit for Owner’s benefit during and after project completion.

D. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Engineer.

1.18 SAMPLES

A. Samples For Review

1. Submit to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

2. After review, provide duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes.

B. Samples For Information

1. Submit for Engineer’s benefit as contract administrator or for Owner.

C. Samples For Selection

1. Submit to Engineer for aesthetic, color, or finish selection.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 6

2. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes.

D. Submit samples to illustrate functional and aesthetic characteristics of the Product.

E. Submit samples of finishes from the full range of manufacturers’ standard colors (or custom colors when specified), textures, and patterns for Engineer’s selection.

1.19 MANUFACTURER INSTALLATION INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing to Engineer in quantities specified for Product Data.

1.20 MANUFACTURER CERTIFICATES

A. When specified in individual specification sections, submit certifications by manufacturer to Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

1.21 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions.

C. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

1.22 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that utility services are available, of the correct characteristics, and in the correct locations.

1.23 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Apply manufacturer required or recommended substrate primer, sealer or conditioner prior to applying new material or substance in contact or bond.

1.24 TOLERANCES

A. Monitor fabrication and installation tolerance control of installed Products over suppliers, manufacturers, Products, site conditions, and workmanship, to produce acceptable Work. Do not permit tolerances to accumulate.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 7

B. Comply fully with manufacturers’ tolerances.

1.25 REFERENCES

A. Conform to reference standard by date of issue current on date for receiving bids, except where a specific date is established by code.

B. Should specified reference standard conflict with Contract Documents, request clarification from Engineer before proceeding.

1.26 MOCK-UPS

A. Tests will be performed under provisions identified in this section and identified in the respective Product specification sections.

B. Accepted mock-ups are representative of the quality required for the Work.

C. Where mock-up has been accepted by Engineer and is specified in Product specification sections to be removed; remove mock-up and clear area when directed to do so.

1.27 TESTING LABORATORY SERVICES

A. Contractor shall furnish to Engineer duplicate certified copies of all routine tests made by the mill, shop or factory at which material or equipment is fabricated or manufactured for the Work.

B. An independent firm will perform tests, and other services when so specified in individual specification sections.

C. Cooperate with independent firm; furnish samples as requested.

D. Re-testing required because of non-conformance to specified requirements shall be performed by an independent firm on instruction by Engineer.

E. Contractor shall pay for all testing and laboratory services and/or test reports as are required in individual specification sections including any required re-testing.

1.28 OBSERVATION SERVICES

A. Owner will employ and pay for observation services during construction of the Project.

B. Cooperate with construction observer; furnish safe access and incidental assistance as requested.

1.29 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions and to initiate instructions when necessary.

B. Report observations and site decisions or instructions that are supplemental or contrary to manufacturers' written instructions.

1.30 TEMPORARY ELECTRICITY

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 8

A. The Contractor to provide and pay for a power service as necessary for completion of the work.

1.31 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES

A. Provide and maintain lighting for construction operations, as needed.

B. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.

1.32 TEMPORARY HEATING

A. The Contractor shall provide and pay for temporary heating, as necessary for completion of the work.

1.33 TEMPORARY VENTILATION

A. Ventilate enclosed areas, as needed, to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, and gases.

1.34 TELEPHONE SERVICE

A. Not Used.

1.35 TEMPORARY WATER SERVICE

A. Provide, maintain and pay for potable water for drinking purposes.

1.36 TEMPORARY SANITARY FACILITIES

A. Provide, maintain and pay for required facilities and enclosures.

B. Maintain in clean and sanitary condition.

1.37 BARRIERS AND FENCING

A. Provide barriers to prevent unauthorized entry to construction areas. Provide measures for the Owner’s use of site while to protecting existing facilities, materials, equipment, designated vegetation, and adjacent properties from damage.

B. Construction: Contractor's option.

1.38 WATER CONTROL

A. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

1.39 EXTERIOR ENCLOSURES

A. Not Used.

1.40 INTERIOR ENCLOSURES

A. Not Used.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 9

1.41 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Prohibit traffic or storage upon waterproofed or roofed surfaces.

C. Prohibit traffic from landscaped areas.

1.42 SECURITY

A. Provide security and facilities to protect the Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.

1.43 ACCESS ROADS

A. Not Used.

1.44 PARKING

A. Provide temporary parking areas to accommodate construction personnel.

1.45 PROGRESS CLEANING AND WASTE REMOVAL

A. Collect and maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

1.46 PROJECT IDENTIFICATION

A. Not Used.

1.47 FIELD OFFICES AND SHEDS

A. Not Used.

1.48 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Final Application for Payment.

B. Remove underground installations to a minimum depth of 2 ft.

C. Clean and repair damage caused by installation or use of temporary work.

D. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.49 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Resident Project Representative) to prevent air-borne dust from dispersing into atmosphere.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 10

C. Dust control measures shall be employed when required in the opinion of the Resident Project Representative at no additional cost to Owner.

1.50 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.51 TRANSPORTATION, HANDLING, STORAGE AND PROTECTION

A. Transport, handle, store and protect Products in accordance with manufacturer's instructions.

1.52 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named in accordance with the following Article on Substitutions.

1.53 SUBSTITUTIONS

A. Instructions to Bidders specify time for submitting requests for Substitutions during the bidding period to requirements specified in this section.

1.54 EQUIPMENT GUARANTEE

A. All equipment furnished shall be guaranteed by the manufacturer to be free from all defects in workmanship, design and material for a period of not less than 12 months from the date that the equipment is placed in continuous operation or not less than 18 months from the date of delivery to the job site, whichever occurs first.

B. This guarantee shall be in addition to the one year correction period provided by Contractor under Article 13, paragraph 13.12 of the General Conditions.

C. If the continuous operation of a piece of equipment is interrupted due to a defect requiring the replacement of the equipment or part thereof, the equipment manufacturer's 12-month guarantee shall restart from the beginning when the required replacement item is installed and the equipment is returned to a continuous operation.

1.55 STARTING SYSTEMS

A. Not Used.

1.56 DEMONSTRATION AND INSTRUCTIONS

A. Not Used.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 11

1.57 CONTRACT CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Complete all punch list items as soon as possible and within the Contract Time.

C. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.

1.58 FINAL CLEANING

A. Execute final cleaning prior to final Project inspection.

B. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.59 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

1.60 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of Contract Documents to be utilized for record documents.

B. Record actual revisions to the Work. Record information concurrent with construction progress.

C. Specifications: Legibly mark and record at each Product section a description of actual Products installed.

D. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction.

E. Submit documents to Engineer with final Application for Payment.

1.61 OPERATION AND MAINTENANCE MANUAL

A. Not Used.

1.62 SPARE PARTS AND MAINTENANCE MATERIALS

A. Not Used.

1.63 OTHER DOCUMENTATION

A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:

1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).

2. Waiver of Liens by all Subcontractors and Suppliers or Contractor’s Affidavit, Contractor’s Release of Liens and Consent of Surety Company to Final Payment.

MARCH 2026

01 00 00 – BASIC REQUIREMENTS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 00 00 - 12

3. Maintenance Bond.

4. Any Change Orders with supporting documentation which remain to be submitted.

5. Test and/or sample results.

6. Equipment warranties.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

Not Used

MARCH 2026

01 11 13 – SUMMARY OF WORK

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 11 13 - 1

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes

1. Description of Work

2. Work by Owner

3. Work by other parties

4. Owner supplied Products

5. Contractor use of site and premises

6. Future work

7. Work sequence of construction

8. Owner occupancy

9. Availability of lands

10. Special Requirements

1.02 DESCRIPTION OF WORK

A. The construction project will involve electrical equipment upgrades for an existing wastewater pump station as well as offsite rebuild of the (2) existing pumps and grinder and site restoration.

1. Pump information: KSB Model KRT F100-401, 50HP, 3/60/460 VAC, 1800RPM, explosion proof rated.

2. Grinder information: Muffin Monster, Model 30005-0012-DI, hydraulically driven.

1.03 WORK BY OWNER

A. The Owner will not be performing any work related to this project.

1.04 WORK BY OTHER PARTIES

A. None

1.05 OWNER SUPPLIED PRODUCTS

A. The Owner is not supplying any products for this project.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. The Work is situated within the Owner’s property. The Contractor is reminded to respect the boundaries of the property and limit their disturbances to the areas within.

B. The Contractor will be responsible to notify all property owners and residents at least twenty-four (24) hours prior to the start of construction on or near their properties.

1.07 FUTURE WORK

A. None

1.08 WORK SEQUENCE OF CONSTRUCTION

A. The Contractor is responsible for developing a sequence of construction, which shall be

MARCH 2026

01 11 13 – SUMMARY OF WORK

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 11 13 - 2

submitted to Engineer for review and approval.

1.09 OWNER OCCUPANCY

A. Cooperate with individual property owners and the Township to minimize conflict, and to facilitate continuous service of existing utilities.

1.10 AVAILABILITY OF LANDS

A. The site will be available upon notice to proceed.

PART 2 - PRODUCTS

Not Used

MARCH 2026

01 22 00 - MEASUREMENT AND PAYMENT

MARCH 2026 01 22 00 - 1

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.

1.02 PROCEDURE

A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.

B. The Resident Project Representative and Contractor shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. Contractor shall assist by providing necessary equipment and personnel as required.

C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.

PART 2 - PRODUCTS

3.01 MOBILIZATION/DEMOBILIZATION AND BONDS AND INSURANCE (ITEM 1)

A. Payment

1. Fifty percent (50%) of the price bid will be payable to the Contractor when he has completed five percent (5%) of the work of the contract. For the purposes of this item, five percent (5%) of the work shall be considered complete when the total of payments earned (exclusive of the amount bid for this item, bonds, insurance, and stored materials) as shown on the monthly certificates of the approximate quantities of work done, prepared in conformance with “Payments and Completion” of the General Conditions shall exceed five (5%) percent of the total price bid for the Contract.

2. The final fifty percent (50%) of the price bid will be payable to the Contractor when he has performed all work and delivered all required as-builts.

3.02 DEMOLITION AND SITE RESTORATION (ITEM 2)

1. Payment will constitute full compensation for furnishing all labor, materials, and equipment required to successfully perform the task of excavation, saw cutting and removing asphalt pavement, soils and asphalt removal and disposal, soil and backfill, and asphalt payment restoration as shown on the Contract Drawings and specified in the Project Manual.

MARCH 2026 01 22 00 - 2

3.03 FENCE GROUNDING (ITEM 3)

equipment required to successfully perform the task of supplying and installing grounding and testing for the fence as shown on the Contract Drawings and specified in the Project Manual.

3.04 PUMP CONTROL PANEL AND ASSOCIATED INSTRUMENTS, AUTODIALER, CELLULAR

EQUIPMENT, RAIN GAUGE (ITEM 4)

equipment, including raceways, junction boxes, low voltage wire, control voltage wire, backboards and supports required to successfully perform the task of furnishing and installing the pump control panel, level transmitter and backup floats, rain gauge, autodialer and cellular antenna and antenna cable to complete the work in accordance with the Contract Drawings and specified in the Project Manual.

3.05 PUMP COMBINATION STARTERS, POWER PANEL BREAKERS, SURGE PROTECTION

EQUIPMENT, JUNCTION BOXES, AND SUPPORTS (ITEM 5)

B. Payment equipment, including raceways, junction boxes, low voltage wire, backboards and supports required to successfully perform the task of furnishing and installing pump combination starters, power panel breakers and surge protection equipment to complete the work in accordance with the Contract Drawings and specified in the Project Manual.

3.06 STATION INTERIOR AND EXTERIOR LIGHTING (ITEM 6)

equipment required to successfully perform the task of supplying and installing replacement indoor light fixtures, supplying and installing new exterior light fixtures, supplying and installing emergency and egress light fixtures, removal and disposal of old light fixtures, furnish and install all light switches, conduit, wire and supports to complete the work in accordance with the Contract Drawings and specified in the Project Manual.

3.07 ADD ALTERNATE 1 – PUMP 1 AND 2 REBUILD (ITEM 7)

1. Payment will constitute full compensation for removing each pump, sending off site for rebuild, successful rebuild and installation on site, including completion of factory acceptance testing (FAT) and site acceptance testing (SAT) and prove out of pump operation upon reinstallation. Work shall be as indicated on the Contract Drawings and specified in the Project Manual.

3.08 ADD ALTERNATE 2 – GRINDER REBUILD (ITEM 8)

MARCH 2026 01 22 00 - 3

1. Payment will constitute full compensation for removing the grinder (with the exception of the torque motor), sending off site for rebuild, successful rebuild and installation on site, including completion of factory acceptance testing (FAT) and site acceptance testing (SAT) and prove out of grinder operation upon reinstallation. Work shall be as indicated on the Contract Drawings and specified in the Project Manual.

3.09 ADD ALTERNATE 2 – GRINDER RENEW (ITEM 9)

1. Payment will constitute full compensation for removing the grinder (with the exception of the torque motor) and sending off site for manufacturer renewal. The contractor shall furnish and install a “renewed” grinder, equal to the one sent out for renewal, including completion of factory acceptance testing (FAT) and site acceptance testing (SAT) and prove out the grinder operation upon reinstallation. Work shall be as indicated on the Contract Drawings and specified in the Project Manual.

3.10 STATED ALLOWANCE (ITEM 10)

1. The Owner may elect to authorize work that is over and above that required by the Contract Documents. Payment will be for the precise amount authorized by the Owner, which may be less than the total stated allowance but may not exceed the stated allowance.

MARCH 2026

01 29 00 - CONTRACT CONSIDERATIONS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 29 00 - 1

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes

1. Schedule of values

2. Application for payment

3. Change procedures

4. Alternates

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere

1. Section 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals: Schedule of Values.

4. Section 01 60 00: Material and Equipment: Product substitutions and options.

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on EJCDC 1910-8-E. Contractor's standard form or electronic media printout will be considered in lieu of EJCDC 1910-8-E.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on EJCDC C-620.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly

D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only)

E. Include Payroll Certification forms with each Payment Application.

F. Include an updated construction progress schedule.

MARCH 2026

01 29 00 - CONTRACT CONSIDERATIONS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 29 00 - 2

1.05 CHANGE PROCEDURES

A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract

Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing supplemental instructions.

B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors.

Document any requested substitutions in accordance with Section 016000.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.

F. Work Directive Change: Engineer may issue a directive, on EJCDC C-940 Work Directive Change signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Change Order Forms: EJCDC Form C-941.

J. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. Accepted alternates will be identified in the Agreement.

B. Coordinate related work and modify surrounding work as required.

PART 2 - PRODUCTS

MARCH 2026

01 33 00 - SUBMITTALS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 33 00 - 1

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes

1. Submittal procedures

2. Construction progress schedules

3. Product data

4. Shop Drawings

5. Samples

6. Design data

7. Test reports

8. Certificates

9. Manufacturer’s instructions

10. Manufacturer’s field reports

11. Erection drawings

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere

1. Section 01 40 00: Quality Control

2. Section 01 70 00: Contract Closeout

1.03 REFERENCES

A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.

1.04 SUBMITTAL PROCEDURES

A. Transmit each submittal to Engineer.

B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project and to coordinate submission of related items.

F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Engineer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

MARCH 2026

01 33 00 - SUBMITTALS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 33 00 - 2

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.05 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.

B. Revise and resubmit as required.

C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.

D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.

E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

1.06 PRODUCT DATA

A. Product Data for Review

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Product Data for Information

1. Submitted for the Engineer’s knowledge as contract administrator or for Owner.

C. Product Data for Project Closeout

1. Submitted for Owner’s benefit during and after project completion.

D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.

E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.

1.07 SHOP DRAWINGS

A. Shop Drawings for Review

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce copies and distribute in accordance with Submittal Procedures

MARCH 2026

01 33 00 - SUBMITTALS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 33 00 - 3

article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Shop Drawings for Information

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

C. Shop Drawings for Project Closeout

1. Submitted for Owner’s benefit during and after project completion.

D. Submit shop drawings electronically by email in .pdf format.

1.08 SAMPLES

A. Samples for Review

1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Samples for Information

1. Submitted for Engineer’s knowledge as contract administrator or for Owner.

C. Samples for Selection

1. Submitted to Engineer for aesthetic, color, or finish selection.

2. Submit samples of finishes from the full range of manufacturers’ standard colors (unless stated otherwise in the plans) textures, and patterns for Engineer’s selection.

3. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

E. Include identification on each sample, with full Project information.

F. Submit the number of samples specified in individual specification sections; one of which will be retained by Engineer.

G. Reviewed samples which may be used in the Work are indicated in individual specification sections.

H. Samples will not be used for testing purposes unless specifically stated in the specification section.

1.09 DESIGN DATA

MARCH 2026

01 33 00 - SUBMITTALS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 33 00 - 4

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.10 TEST REPORTS

A. Submit for Engineer’s knowledge as contract administrator or for Owner.

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.11 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.

1.12 MANUFACTURER’S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.

1.13 MANUFACTURER’S FIELD REPORTS

A. Submit reports for Engineer’s benefit as contract administrator or for Owner.

B. Submit report in duplicate within 30 days of observation to Engineer for information.

C. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.14 ERECTION DRAWINGS

A. Submit drawings for Engineer’s benefit as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or Owner.

MARCH 2026

01 33 00 - SUBMITTALS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 33 00 - 5

PART 2 - PRODUCTS

Not Used

MARCH 2026

01 40 00 – QUALITY CONTROL

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 40 00 - 1

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes

1. Quality assurance - control of installation

2. Tolerances

3. References and standards

4. Mock-up

5. Testing laboratory services

6. Observation services

7. Manufacturers' field services

8. Examination

9. Preparation

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere

1. Section 00 72 00: General Conditions

2. Section 00 73 00: Supplementary Conditions

3. Section 01 33 00: Submittals

4. Section 01 42 13: Organization and Reference Acronyms

5. Section 01 60 00: Material and Equipment

1.03 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply fully with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Comply with specified standards as minimum quality for the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform Work by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.

1.04 TOLERANCES

A. Monitor fabrication and installation tolerance control of Products to produce acceptable Work.

Do not permit tolerances to accumulate.

MARCH 2026

01 40 00 – QUALITY CONTROL

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 40 00 - 2

B. Comply with manufacturers’ tolerances. Should manufacturers’ tolerances conflict with Contract Documents, request clarification from Engineer before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

1.05 REFERENCES AND STANDARDS

A. For Products or workmanship specified by association, trade or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date for receiving bids, except where a specific date is established by code.

C. Obtain copies of standards where required by Product specification sections.

D. Should specified reference standard conflict with Contract Documents, request clarification from Engineer before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Engineer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.06 MOCK-UP

A. Tests will be performed under provisions identified in this section and identified in the respective Product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Engineer and is specified in Product specification sections to be removed; remove mock-up and clear area when directed to do so.

1.07 TESTING LABORATORY SERVICES

A. Contractor shall furnish to Engineer duplicate certified copies of all routine tests made by the mill, shop or factory at which material or equipment is fabricated or manufactured for the Work when so specified in individual specification sections.

B. An independent firm will perform tests and other services when so specified in individual specification sections and as required by Engineer.

C. Testing and source quality control may occur on or off the Project site. Perform off-site testing as required by Engineer.

D. Reports will be submitted by the independent firm to Engineer, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access and assistance by incidental labor as requested.

MARCH 2026

01 40 00 – QUALITY CONTROL

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 40 00 - 3

1. Notify Engineer and independent firm 24 hours prior to expected time for operations requiring services.

2. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

F. Testing does not relieve Contractor to perform Work to contract requirements.

G. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by Engineer.

H. Contractor shall pay for all testing and laboratory services and/or test reports as are required in individual specification sections.

1.08 OBSERVATION SERVICES

A. Owner will employ and pay for observation services during construction of the Project.

Construction observers may be members of Owner’s staff.

B. Cooperate with construction observer; furnish safe access and assistance by incidental labor as requested.

1. Notify construction observer 24 hours prior to expected time for operations requiring services.

C. Observation does not relieve Contractor to perform Work to contract requirements.

1.09 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, as applicable, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers’ written instructions.

C. Refer to Section 01 33 00 - Submittals, Manufacturers’ field reports article.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

MARCH 2026

01 40 00 – QUALITY CONTROL

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 40 00 - 4

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

MARCH 2026

01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS

CALN TOWNSHIP MUNICIPAL AUTHORITY

KING’S GRANT PUMP STATION UPGRADES

MARCH 2026 01 42 13 - 1

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Listing of acronyms and associated organization and/or references which may be cited in the Project Manual.

1.02 SCHEDULE OF ACROYNYMS

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

AI Asphalt Institute

AISC American Institute of Steel Construction

AISI American Iron and Steel Institute

AITC American Institute of Timber Construction

AMCA Air Movement & Control Association

ANSI American National Standards Institute

APA American Plywood Association

ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers

ASME American Society of Mechanical Engineers

ASTM American Society for Testing and Materials

AWPA American Wood-Preservers Association

AWS American Welding Society

AWWA American Water Works Association

BOCA Building Officials & Code Administrators International, Inc.

CIPP Cured-In-Place-Pipe

CLFMI Chain Link Fence Manufacturers Institute

CRSI Concrete Reinforcing Steel Institute

CSA Canadian Standards Association

DHI Door and…