This is a Scope of Work document for RFP 26-04 issued by a Pennsylvania County Department of Assets & Infrastructure, Division of Roads & Bridges, soliciting engineering design services for the replacement of County Bridge No. 83, a 1926-built three-span concrete T-beam bridge with a 198-foot span and 34-foot curb-to-curb width crossing Wissahickon Creek in Upper Dublin Township. The selected engineering firm will be responsible for engineering design, environmental permitting, and construction consultation services. The contract period for the engineering and environmental permitting phase is thirty-six months from the Notice-to-Proceed, with construction consultation extending through the duration of the construction phase. The scope requires a comprehensive full scope of work including sixteen tasks: project management and administration, topographic survey and base mapping, environmental studies and permitting, roadway design with submissions at 30%, 60%, and 90% completion, erosion control plans, geotechnical engineering, hydrologic and hydraulic analysis, structural design, right-of-way property plots, traffic control plan, signing and pavement marking plan, utility coordination, agency coordination, plans and specifications, and construction consultation. Bidders are strongly encouraged to complete a site visit, and all proposals must be submitted electronically through the County's Bonfire procurement portal by the posted deadline.
The cost proposal must be submitted as a not-to-exceed price with detailed line-item breakdown for each task, including all direct and indirect costs and out-of-pocket expenses. This is a Best Value solicitation where the County will award to the responsible offeror offering the most advantageous balance between technical merit and cost. Evaluation criteria are weighted as follows: overall project approach and team commitment to delivery and schedules (40%), project manager's experience with similar projects (25%), project staff and their ability to meet design and construction schedules (20%), and the team's approach to designing an effective construction plan while minimizing future maintenance (15%). The selected firm must be PennDOT pre-qualified with specific experience in municipal bridge design, demonstrating at least five completed projects within the past five years. The project will be funded through the Act 13 Marcellus Legacy Fund, and the consultant will not be responsible for obtaining Structural Adequacy Approval from PennDOT District 6-0.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Contract Cover and Signature Page (SAMPLE).pdf | ||
| 1-Appendix A - Rev 10.25.23 FILLABLE.pdf | ||
| 5-Grant Addendum TCs.pdf | ||
| 4-Exhibit A - Standard Terms and Condition for Services - Updated 7.30.24.docx | DOCX document | |
| 3-Instructions to Bidders Template.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 26-04 A&I Dept. of Roads & Bridges Engineering Design Services for Bridge 83
SCOPE
The County, on behalf of the Department of Assets & Infrastructure, Division of Roads & Bridges, is seeking a qualified engineering firm to perform the required engineering, environmental permitting and construction consultation for the replacement of County Bridge No. 83, Butler Pike over Wissahickon
Creek in Upper Dublin Township. The existing bridge, built in 1926, is a three-span concrete T-beam bridge. The bridge has a span of 198 feet with a curb-to-curb width of 34 feet.
REQUIREMENTS
It is expected that the selected firm will work with the Division to provide the County with the necessary plans, environmental permitting, and bid documents to advertise this bridge project for construction.
The County plans on funding this project utilizing Act 13 Marcellus Legacy Fund. Due to the funding being utilized, the consultant will not be responsible for obtaining Structural Adequacy Approval from
PennDOT District 6-0.
QUALIFICATIONS
The County seeks PennDOT pre-qualified engineering firms with specific experience in the design of municipal bridges (no less than five completed in the last five years).
CONTRACT PERIOD WITH OPTION TO EXTEND
The duration of the engineering and environmental permitting phase shall be thirty-six (36) months commencing on date of Notice-to-Proceed. Construction consultation will be for the duration of the construction phase. If the engineering and environmental permitting phase is not completed within this time frame, the selected firm must request a time extension that includes a description of why the request is needed and a detailed schedule showing the anticipated completion date. Construction consultation will last for the duration of the construction phase.
SCOPE OF SERVICES
The following tasks are required to complete this project. All required subtasks must be included within these tasks. A full scope of work needs to be provided to be considered for this project. Any missing tasks will disqualify the proposer.
1: Project Management/Administration
2: Topographic Survey & Base mapping
3: Environmental Studies
4: Environmental Permitting
5: Roadway Design – submissions are expected at 30%, 60% and 90% complete.
6: Erosion Control Plans
7: Geotechnical Engineering
8: Hydrologic and Hydraulic Analysis
9: Structural Design – TS&L and Final Structure Plans are required to be submitted.
10: Right-of-Way Property Plots – expected to be submitted with the 60% submission.
11: Traffic Control Plan
12: Signing and Pavement Marking Plan
13: Utility Coordination
14: Agency Coordination and Meetings
15: Plans, Specifications and Estimate
16: Construction Consultation
COST PROPOSAL
The format of the cost proposal shall be a not-to-exceed price with a detailed line-item breakdown of the cost associated with each task. The cost proposal should contain all costs both direct and indirect, including all out-of-pocket expenses.
COMPANY PROFILE AND PROVIDER INFORMATION
The proposal to this request must contain the following:
Brief (one or two paragraphs) description of the provider’s business, its history and future plans.
Provider identification (EIN)
State of Incorporation
Corporate name
Corporate address
Telephone numbers
Contact person(s)
Vendor size
Vendor stability
Organization chart of the Project team for this contract
Resumes of key personnel for this contract
List of past or current projects of similar scope or size, including contact information for the recipient of service.
PROPOSAL EVALUATION
All proposals received by the specified date shall be subject to evaluation by a review committee. The following criteria will be used to evaluate offers:
This is a “Best Value” solicitation. The County will award a contract to the responsible offeror who can accomplish the requirements set forth in the RFP. The County will select the proposal that represents the best value to the County based on the comparative analysis and an integrated assessment of proposals against all evaluation criteria in the solicitation.
The County’s primary goal is achieving the most advantageous balance between technical merit
(“quality”) and cost (i.e. price). All evaluation factors other than cost or price, when combined, are more important than cost or price. However, the importance of price could become greater depending upon the equality of the technical proposals. If competing technical proposals are determined to be essentially equal, price could become the determining factor. The County may award a contract to other than the lowest priced cost proposal or other than the highest evaluated technical proposal.
EVALUATION CRITERIA
Project team must discuss their overall approach to delivering the project. This discussion shall include the team’s commitment to project delivery and meeting schedules. (40%)
Project Manager’s experience with similar projects. (25%)
Discuss the staff for this project and how they will pursue project delivery in relation to developing and/or meeting design and construction project schedules. (20%)
Discuss how the project team will design an effective construction plan while minimizing future maintenance (15%)
CONTACTS & SUBMISSIONS
1. All questions are to be submitted via the Messages / Opportunity Q&A section for this solicitation in the Bonfire portal and all answers will be provided for public review.
2. All final Proposal submissions must be made electronically via the County’s procurement submission portal - https://montcopa.bonfirehub.com/portal - by the posted submission deadline.
3. Bidders are strongly encouraged to complete a site visit to fully familiarize themselves with the site constraints.
File details come from the government source that posted it. Updated .