6-Attachment C.pdf
PDF 247 KB Posted
- Attached to
- Design and Build Services
- Solicitation number
- 541473
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This is a Design Services Fee proposal template from the City of Detroit Office of Contracting and Procurement for design-build services related to an office renovation project at the Department of Housing and Redevelopment (HRD) located at 2 Woodward Suite 908, Detroit, Michigan 48226. The project encompasses permit drawings for fire alarm, mechanical, and elevator upgrades, with Phase 1 deliverables including design and permit drawings completed as needed. Phase 2 construction items include markup fees, general conditions with specified duration, and insurance and bond costs. A mandatory pre-bid walkthrough is scheduled for Tuesday, February 17, 2026 at 2:00 PM EST at the project location in Detroit.
The proposal requires respondents to provide fully burdened labor rates for all construction manager project personnel, including positions such as project director, project manager, project superintendent, project engineer, project estimator, accounting, clerical, and journeyman general contractor staff, with additional positions available as needed. The document indicates an anticipated construction cost of approximately $700,000 and requests specific information regarding general contractor duration and mobilization and staffing requirements. All pricing for Phase 1 and Phase 2 items are to be entered in designated columns, with specific sections noting that certain columns are calculated fields and should not be edited by respondents.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design Services Fee Anticipated Duration/HoursComments A. Design and Permit Drawings -$ - As needed Permit drawings for Fire
Alarm, Mechanical, and Elevator Upgrade
Awardee Mark up Fee for Phase 1 if applicalbe and/or not included in A
Phase 1 Sub Total: -$
Phase 2: Construction Items Value - Costs
1. Mark Up Fee -$
2. General Conditions - specify duration -$
3. Insurance and Bond -$
Construction Manager's Project Personnel *Hourly Rate* Project Director -$ Project Manager -$ Project Superintendent -$ Project Engineer -$ Project Estimator -$ Accounting -$ Clerical -$ Journeyman for General Contractor -$ Others: -$ Others: -$ Others: -$ Others: -$ Others: -$
HRD Price Proposal
DO NOT EDIT ANY OF THE B COLUMNS - THESE ARE CALCULATED FIELDS
Phase 1:
Comments if construction cost is approx. $700,000
Also, note the constructin duration of the GC's, This is to include mobilization and staffing.
*Provide Fully Burdened Labor Rates*
File details come from the government source that posted it. Updated .