This document is a Scope of Work for the Kane Creek Phase 2 Project, involving the Abandoned Mine Reclamation Project (AMRP) in San Juan County, Utah, spanning Lower Kane Creek, Upper Kane Creek, and Brumley Ridge Mining Districts. The project aims to close 140 hazardous mine features/openings across privately-owned, Trust Lands Administration (TLA), and US Forest Service lands, with a detailed closure plan including 43 backfills, 35 walls (stone/block), 58 grates (adit/shaft), and 4 bat gates. A mandatory site visit is scheduled for September 3rd, 2025, at 8:00 AM MST in Moab, with construction planned from October 6th to December 20th, 2025.
The estimated project cost is $700,000, with potential adjustments pending right-of-entry agreements with TLA and private landowners. The project follows Phase 1, which previously closed 77 mine features on Bureau of Land Management (BLM) lands. The final number and type of closures may be modified based on landowner preferences, potentially including the option of no closures on specific properties. The project is part of a comprehensive effort to address 228 open uranium mines identified in the Kane Creek Project area, focusing on environmental remediation and safety mitigation in the mining districts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Chapter 5 Fillable PDF.pdf | ||
| 7-KML.zip | ZIP file | |
| 3-037918 KaneCreek Phase2.pdf | ||
| 1-Vendor Prerequisites - IFB Agency.pdf | ||
| 7-Attachment B Scope of Work Kane Creek Phase 2 Construction.pdf | ||
| 4-Att.-A-PO-Terms-and-Conditions (2).docx | DOCX document | |
| 6-KML Files.zip | ZIP file | |
| 5-Attachment C BidSchedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KANE CREEK PHASE 2 PROJECT
Background:
The Kane Creek Abandoned Mine Reclamation Project includes the Lower Kane Creek, Upper Kane Creek, and Brumley Ridge Mining Districts in San Juan County, Utah. The boundaries for this project are shown on the location map at the end of this synopsis. Inventory of the mining districts found in the Kane Creek Project area identified 228 open uranium mines.
During Phase I of the Kane Creek Project, 77 mine closures were conducted on Bureau of Land Management (BLM) lands. Phase 2, which will complete the Kane Creek Project, is located within the same project area as Phase 1 but addresses mine features on privately-owned, Trust Lands Administration (TLA), and US Forest Service lands.
Scope of Work:
As part of the Kane Creek Phase 2 Project, AMRP is planning to close 140 hazardous mine features/openings in the project area. The breakdown of closures planned is as follows:
Backfill Wall (Stone/Block)
Grate (Adit/Shaft)
Bat Gate (Rebar/Angle iron) 43 35 58 4
Potential Issues/Changes to Project Right-of-entry agreements are still pending with TLA and private landowners. The final number and type of closures may be adjusted based on landowner preferences, including the possibility of no closures on specific property.
Mandatory Site Visit 09/03/2025 at 8:00 AM, MST. Moab Kane Creek Blvd (Co rd. 145) Co-ordinates: 38.502136, -109.605986. See KML “Prebid_location” for pin Please arrive early. We will start promptly at 8 AM. All late comers will be asked to leave.
Estimated Schedule:
Construction Start: October 6th, 2025 Construction Completion: December 20th, 2025
Estimated Cost:
$700,000
Attachment B Scope of Work
NC26-17
Signature: