This document is a Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a GSA lease solicitation in Erie, Pennsylvania. The comprehensive schedule outlines a structured timeline for lease-related activities, spanning approximately 255 working days from lease award, including key milestones such as design kick-off meetings, design intent drawing submissions, construction documents preparation, price proposal submission, negotiations, construction, and final project completion. Critical phases include 30 days for initial design intent drawings, 45 days for TI/BSAC bid negotiations, 75 days for lessor-completed construction work, and 10 days each for government acceptance and punch list completion. The solicitation seeks 1,300-2,000 rentable square feet of office space in downtown Erie, with a 10-year lease term (5 years firm), and includes specific requirements such as above-ground, contiguous space on one floor, and exclusions for buildings housing law enforcement entities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachments/Links

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 10 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Design Kick-Off Meeting with Lessor, GSA & Agency 15 days after lease award

Lessor-Provides Initial Design Intent Drawings (DIDs) 30 days

Lessor Provides 100% DIDs 15 days

Government Approval of DIDs 10 days

Lessor Provides Initial CDs 20 days

Lessor Provides 80% CDs 15 days

Lessor Provides 100% CDs 15 days

Lessor Preparation and Submission of the TI and BSAC Price Proposal 20 days

TI/BSAC Bid Negotiations Completed 45 days

Construction Kick Off Meeting 15 days

Lessor Completes Required Construction Work 75 days

Government Acceptance/ Substantial Completion 10 days

Punch List Completed 10 days