This is a solicitation for construction services to renovate space for a PET/CT scanner at the Lebanon VA Medical Center in Lebanon, Pennsylvania. The solicitation is set aside for verified Service-Disabled Veteran-Owned Small Businesses. The construction magnitude is between $250,000 and $500,000 under NAICS code 236220 with a small business size standard of $39.5 million. Bids are due by 9:30 AM on February 8, 2021 at which time a public bid opening will be held. Davis Bacon wage determination PA20200093 dated October 2, 2020 applies. The work shall be performed according to the attached specifications, drawings, and codes. The Department of Veterans Affairs Veterans Health Administration VISN 4 is the agency.

View the file

Other files

File Type Posted
36C24421B0005.docx DOCX document
595-19-340_BID-SET_DRAWINGS.pdf PDF
Wage Determination PA2020093.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 595-19-340 Renovate for PET/CT Scanner Lebanon VAMC

00 01 10-1 05-01-20

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 05-20 01 42 19 Reference Standards 09-19 01 45 00 Quality Control 03-19 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Acoustical Insulation 10-17 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 16 Resilient Sheet Flooring 05-18 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 26 00 Wall Protection 10-15

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-19 22 15 00 General Service Compressed-Air Systems 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15

00 01 10-2 05-01-20

SECTION NO. DIVISION AND SECTION TITLES DATE

22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC Insulation 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 10 00 VFD Controllers 23 21 13 Hydronic Piping 02-20 23 23 00 Refrigerant Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 Exhaust Fan 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 82 16 Air Coils 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 36 Wireways for Radiology Equipment 01-18 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 33 53 Static Uninterruptible Power Supply 01-17 26 51 00 Interior Lighting 01-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI-001 Cover Sheet GI-002 ICRA and Life Safety Plans GI-003 Construction Phasing Plan

ARCHITECTURAL

AD-100 Partial Floor Plan – Demolition AD-200 Partial Reflected Ceiling Plan – Demolition AS-100 Partial Floor Plan AS-200 Partial Reflected Ceiling Plan

MECHANICAL, FIRE PROTECTION, MEDICAL GAS, PLUMBING

M-001 Mechanical, Plumbing and Fire Protection Symbols, Abbreviations and Schedules FD-101 Ground Floor Fire Protection Demolition Plan MGD-101 Ground Floor Medical Gas Demolition Plan MD-101 Ground Floor Mechanical Ductwork Demolition Plan MD-102 Ground Floor and Roof Mechanical Piping Demolition Plan PD-101 Ground Floor Plumbing Demolition Plan FP-101 Ground Floor Fire Protection Plan MGP-101 Ground Floor Medical Gas Plan MP-101 Ground Floor Mechanical Ductwork Plan MP-102 Ground Floor and Roof Mechanical Piping Plan PP-101 Ground Floor Plumbing and Medical Gas Plan M-500 Mechanical Details

ELECTRICAL

E-001 Electrical Symbols Legend ED-100 Electrical Demolition Plan EL-100 Lighting Plan EP-100 Power Plan EP-101 Enlarged Power Plan ET-100 Telecommunications Plan

- - - END - - -

i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 GENERAL INTENTION

1.2 STATEMENT OF BID ITEM(S)

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.4 CONSTRUCTION SECURITY REQUIREMENTS

1.5 SAFETY

1.6 OPERATIONS AND STORAGE AREAS

1.7 DISPOSAL AND RETENTION

1.8 INFRASTRUCTURE

1.9 RESTORATION

1.10 AS-BUILT DRAWINGS

1.11 USE OF ROADWAYS

1.12 TEMPORARY TOILETS

1.13 AVAILABILITY AND USE OF UTILITY SERVICES

1.14 TESTS

1.15 INSTRUCTIONS

1.16 HISTORIC PRESERVATION

1.17 HOUSEKEEPING

1.18 EMERGENCY MEDICAL SERVICES

1.19 USE OF GOVERNMENT OWNED MATERIAL AND EQUIPMENT

1.20 SUPERINTENDENT COMMUNICATIONS AND RESPONSIBILITY

1.21 SMOKING

1.22 HAZARDOUS MATERIALS

1.23 INFECTION, AIRBORNE DUST AND FUME CONTROL DURING CONSTRUCTION

1.24 ASBESTOS CONTAINING MATERIALS

1.25 ENVIRONMENTAL PROTECTION

1.26 SUBMITTALS

1.27 POTABLE WATER

01 00 00 -2 20170623

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 GENERAL INTENTION

A. The Contractor shall completely prepare site for building operations and furnish labor and materials to perform work for RENOVATE FOR PET/CT SCANNER project as required by Statement of Work (SOW), drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer.

C. Offices of Tolman Engineering, Architecture & Surveying, PLLC dba Patriot Design & Consulting, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.2 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general interior construction, alterations and repairs. Including but not limited to, partition wall demolition and construction, interior finishes, door removal and relocation, floor finish demolition and replacement, suspended ceiling demolition and replacement, casework removal and relocation, lighting and other electrical work, HVAC, plumbing, fire protection and medical gas systems revisions associated with the interior renovations.

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Additional sets of drawings may be made by the Contractor, at Contractor's expense, from reproducible sepia prints furnished by Issuing Office. Such sepia prints shall be returned to the Issuing Office immediately after printing is completed.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

All contractor and subcontractor employees shall obtain from the VA Police Department an ID badge and shall always prominently wear it.

2. Secure all areas of work including, but not limited to construction sites, attics, crawl spaces, mechanical and electrical rooms against

01 00 00 -3 entry of unauthorized individuals including patients. Erection of a non-flammable partition to secure the job site may be required.

Close all windows at the end of each workday.

3. For working outside the “regular hours” as defined in the contract, The General Contractor shall request permission 5 working days’ prior to the Contracting Officer’s Representative for approval. This notice is separate from any notices required for utility shutdown described later in this section. Unless otherwise specified, “regular hours” are 0700 to 1600 Monday to Friday excluding Federal Holidays

4. No photography of VA premises is allowed without written permission of the Contracting Officer.

5. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.

3. The contractor will not be issued more than required sets of keys to complete this project.

4. The contractor's set(s) of keys will contain only those keys that the COR can issue without breaching the security of other areas of the medical center.

5. If the contractor loses a key, all areas that are keyed to that key will be rekeyed at the contractor's expense and all new keys required to be issued will be completed at the contractor's expense.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when

01 00 00 -4 there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. Separate permits shall be issued for General Contractor and its employees for parking in designated areas only.

1.5 SAFETY

A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only. The latest version of the publication at the time of contract award shall be the governing publication

1. American Society for Testing and Materials (ASTM):

E84-2009 ............ Surface Burning Characteristics of Building

Materials

2. National Fire Protection Association (NFPA):

10 Standard for Portable Fire Extinguishers

13 Standard for the Installation of Sprinkler Systems

30 Flammable and Combustible Liquids Code

51B Standard for Fire Prevention During Welding, Cutting and Other Hot Work

70 National Electrical Code

70E Standard for Electrical Safety in the Workplace

72 National Fire Alarm and Signaling Code

99 Health Care Facility Code

101 Life Safety Code

241 Standard for Safeguarding Construction, Alteration, and Demolition Operations

3. Occupational Safety and Health Administration (OSHA):29 CFR 1926 Safety and Health Regulations for Construction

4. International Code Council: International Building Code

B. Contractor shall comply with all applicable elements of the National Fire Protection Association (NFPA) Standard 241. This standard addresses:

01 00 00 -5

1. Temporary Construction, Equipment and Storage

a. Temporary offices and sheds

b. Temporary enclosures

c. Equipment

2. Processes and Hazards

a. Hot work operations including thermic welding

b. Temporary heating equipment

c. Smoking

d. Waste disposal

e. Flammable and combustible liquids

f. Explosive materials

3. Utilities

a. Electrical-temporary wiring (branch circuits, lighting and removal)

4. Fire Protection

a. VA's responsibility for fire protection

b. Site security

c. Fire alarm reporting

d. Access for fire fighting

e. Stand pipes

f. First-aid fire equipment

5. Construction Safeguards

a. Scaffolding, shoring and forms

b. Construction material and equipment storage

c. Roofing operations

d. Permanent heating equipment

e. Utilities

f. Fire cutoffs

g. Fire protection during construction - water supply, sprinkler protection and stand pipes

6. Demolition Safeguards

a. Special precautions

b. Temporary heating equipment

c. Smoking

d. Demolition using explosives

e. Utilities

f. Fire cutoffs

g. Fire protection during demolition

7. Underground Operations

01 00 00 -6

a. Special precautions

b. Equipment and storage requirements

c. Electrical

C. Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to Project Engineer and Facility Safety Officer for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc. Documentation shall be provided to the COR that individuals have undergone contractor’s safety briefing.

D. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

E. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).

F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.

G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Project Engineer and facility Safety Officer.

H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to Project Engineer and facility Safety Officer.

I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.

J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

K. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Any hot work operations including cutting, welding, thermal welding, brazing, soldering, grinding, thermal spraying, thawing pipes or any other similar activity will require a Hot Work Permit to be obtained by the contractor from the Facility Safety Manager. The contractor will be responsible for conforming to all Medical Center regulations, policies and procedures concerning Hot Work Permits as outlined below:

1. Prior to the performance of hot work in patient-occupied buildings, a request for a Hot Work Permit will be made to the Facility Safety Manager.

2. The Facility Safety Manager will inspect the area and ensure that the requirements of NFPA 241 and OSHA Standards have been satisfied. The Hot Work Permit will be granted and will be posted in the immediate

01 00 00 -7 area of the work.

3. The Hot Work Permit will apply only to the location identified on the permit. If additional areas involve hot work, additional permits must be requested.

4. Upon completion of all hot work, the Facility Safety Manager will be notified by the responsible individual to perform a re-inspection of the area.

5. In all other areas not occupied by patients, the supervisor will inspect the hot work area for compliance with NFPA 241 and OSHA Standards. Copies of the request form and permit are available from the Facility Safety Manager.

6. Do not use any of the extinguishers in the medical center for standby purpose while conducting hot work. Contractors are required to supply their own Class ABC extinguishers. Medical center extinguishers are only to be used in the event of a fire.

L. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to Project Engineer and facility Safety Officer.

M. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.

N. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.

O. If required, submit documentation to the Project Engineer that personnel have been trained in the fire safety aspects of working in areas with impaired structural or compartmentalization features.

P. Prior to commencing work, general contractor shall provide proof that a 30 hour OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

Q. Training:

1. All employees of general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and other relevant competency training, as determined by VA CP with input from the ICRA team.

2. Submit training records of all such employees for approval before the start of work.

R. Maintain safety in the construction site/area in accordance with the provisions of the contract, which includes the OSHA Regulations, NFPA 10, 13, 30, 51B, 70, 70E, 72, 99, 101 and 241. Work in a safe manner and take all proper precautions while performing your work. Extra precautions shall be taken when working around persons occupying the building during construction. The contractor shall comply with all requirements of 29 CFR 1926, NFPA 241 and the IBC for safeguarding the public at a construction area.

S. Submit a Coredrilling & Firestopping Permit, supplied by the government for all penetrations. Take precautions when coredrilling to protect persons and structural integrity of the building. Firestop all penetrations before the end of the workday. All Firestop material shall be RED in color.

01 00 00 -8

T. All ceiling tile must be replaced whenever the work site is left unattended. If tiles are broken, the broken tile must be replaced before the end of the day. This applies to all areas outside of areas closed and labeled as a construction area.

U. Make safety inspections and submit weekly, on government supplied form, directly to the Contracting Officer’s Representative

V. Provide Personal Preventive Equipment (PPE) for your employees.

W. Post appropriate signs in specific hazardous areas.

X. Keep tools, ladders, etc. away from patients to prevent injuries.

Tools, ladders, supplies, etc shall never be left unattended in an area with patient access.

Y. Safety inspections of all contract operations will be performed on a regular frequency by the professional Occupational Safety & Health Staff at this facility. Written reports of unsafe practices or conditions will be reported to the Contracting Officer’s Representative (COR) and Contracting Officer for immediate attention and resolution.

Z. Fire Alarms:

1. The fire alarm system connects all buildings at this facility, and is activated by various heat, duct, manual pull stations and smoke sensors. Manual pull stations are provided on each ward. Please survey the area in which you are working to locate the manual pull stations.

2. If in the event of a fire alarm sounding, you are instructed to remain in your area, unless medical center personnel (Safety, Nursing or Engineering) instruct otherwise, or unless a fire situation is in your area, in which case you should immediately evacuate.

3. The medical center operates an extensive patient evacuation program.

A total of approximately 15-20 personnel initially respond to all alarms. Historically, false alarms are caused by contractors generating dust or other disturbances of sensors. When working in an area producing dust, you will cover all alarms with covers approved by the COR. These covers will be removed at the end of the work shift, upon leaving the area after dust has settled.

4. If an alarm is determined by the COR to have been activated by contractor’s work other than from or resulting in a fire situation, the contractor will be charged $300 per occurrence.

5. Any work involving the fire protection systems will require written permission to proceed from the COR.

6. DO NOT tamper with or otherwise disturb any fire alarm system components without prior written permission.

AA. Permit Required Confined Spaces:

1. Contractors performing work on this facility will follow all requirements outlined in OSHA Standards for working in confined spaces. There are numerous permits required for confined spaces on this facility. These spaces have been identified. Some spaces have been posted, but the majority have not due to their configuration. A complete listing of these areas is located in the Engineering Service and Safety Office.

2. Confined spaces are areas which are large enough to be entered but have limited egress/exit potential and are not designed for permanent

01 00 00 -9 human occupancy. If you encounter any space which meets this definition or if it is a suspected confined space, please contact the COR for a listing of these spaces.

3. Contractors performing work in confined spaces are responsible for compliance with all applicable standards and regulations.

BB. Contractor Life Safety Responsibilities:

1. The contractor shall assume full responsibility for compliance to all applicable regulations pertaining to NFPA 101 with respect to their construction area.

2. Alterations to any life safety feature including, but not limited to means of egress, fire detection, fire suppression, fire alarms, smoke barriers and fire barriers must have prior approval of the COR through the Interim Life Safety Measure process.

3. The contractor shall provide, at their cost, any temporary measures needed to meet life safety requirements as laid out in the contract documents and/or the Interim Life Safety Measures. These can include but are not limited to, temporary fire detection and alarm systems, temporary sprinklers, temporary smoke and fire partitions constructed to UL standards and 24/7 fire watches. Any such measures must have the prior approval of the COR through the Interim Life Safety Measure process.

4. Maintain the integrity of floor slabs and fire/smoke walls by fire stopping all holes and penetrations before the end of each workday.

5. The COR on this project is designated as the person responsible for ensuring that the Safety/Fire Safety Plan is carried out to the completion of the project and has the authority to enforce the provisions of this specification section and other applicable fire protection standards.

6. If Interim Life Safety Measures are required in the execution of this contract, the contractor shall annotate their compliance with the established measures daily on ILSM Contractor’s Daily Monitor sheet.

The contractor shall turn in the sheet to the COR monthly.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. All utility connections shall be located underground. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by

01 00 00 -10 the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Do not store materials and equipment in other than assigned areas.

G. Phasing: To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR (4)-four weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.

H. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area as necessary around electrical equipment to be removed or installed. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).

Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.

1.7 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. PCB Transformers: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers. The transformers shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers for disposal, the "originator" copy of the Uniform Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste

01 00 00 -11

Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center's Chief.

a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261 ....... Identification and Listing of Hazardous Waste

CFR 262 Standards Applicable to Generators of Hazardous

Waste

CFR 263 Standards Applicable to Transporters of

Hazardous Waste

CFR 761 PCB Manufacturing, Processing, Distribution in

Commerce, and use Prohibitions

CFR 172 Hazardous Material tables and Hazardous Material

Communications Regulations

CFR 173

Shippers - General Requirements for Shipments and Packaging

CRR 173 Subpart A General

CFR 173 Subpart B Preparation of Hazardous Material for

Transportation

CFR 173 Subpart J Other Regulated Material; Definitions and Preparation

TSCA ............. Compliance Program Policy Nos. 6-PCB-6 and

6-PCB-7

B. Waste disposal in landfills shall be minimized to the greatest extent possible. Of the inevitable waste that is generated, as much of the waste material as economically feasible shall be salvaged, recycled or reused. Contractor shall provide a monthly summary of construction and demolition debris diversion and disposal, quantifying all materials generated at the work site and disposed of or diverted from disposal through recycling. If specification section 01 74 19 is included in this contract, the contractor shall follow all of its requirements.

1.8 INFRASTRUCTURE

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably

01 00 00 -12 interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Maintain existing utility services for Medical Center at all times.

Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

D. No utility service such as water, gas, steam, sewers, HVAC, electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS and 27 05 11 REQUIREMENTS FOR COMMUNICATIONS for additional requirements.

E. Contractor shall submit a request to interrupt any such services to COR, in writing, 3 weeks in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

F. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

G. Major interruptions of any system must be requested, in writing, at least 4 weeks in advance prior to the desired time and shall be performed as directed by the COR.

H. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

I. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

01 00 00 -13

J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

K. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

3. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.

Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.10 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR's review, as often as requested.

01 00 00 -14

C. Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.11 USE OF ROADWAYS, PARKING AND TRAFFIC

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. Parking:

1. Contractor employees shall be assigned parking areas by the COR.

Spaces may not be in the immediate area of the construction site.

Contractor employees shall not park outside of their assigned areas.

2. It is the responsibility of the contractor to barricade parking spaces when not in use.

C. Traffic:

1. Traffic hazards are minimal at this facility. Drivers should be particularly concerned with pedestrian traffic.

2. Seat belt use is mandatory on the station.

3. Federal police officers maintain a 24 hour patrol of the area and have state and federal enforcement authority.

4. Contractor is to have all deliveries made via the State Drive Entrance to the medical center. No deliveries will be allowed from the Lincoln Avenue Entrance (Main Entrance).

1.12 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.13 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines needed for completion of this contract.

Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

C. Temperature Control: Furnish temporary heat and humidity control necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.

01 00 00 -15

1.14 TESTS

A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.

Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

C. Electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building.

Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.

D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.

E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.15 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations.

Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given

01 00 00 -16 in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.16 HISTORIC PRESERVATION

A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

1.17 HOUSEKEEPING

A. Protect patients and VA personnel from the hazards of dust, noise, construction debris and material associated with a construction environment.

B. Keep work area clear, clean and free of loose debris, standing water, trash, construction materials and partially installed work, which would create a safety hazard, disease hazard, or interfere with VA personnel duties and traffic.

C. Wet mop occupied areas and remove any accumulation of dust/debris from cutting or drilling from any surface at the end of each work day.

D. Make every effort to keep dust and noise to a minimum at all times.

Take special precautions to protect VA equipment from damage, including excessive dust.

E. Access to mechanical and electrical devices and equipment should be free of debris and material at all times. This is required to ensure access to existing systems in the event of an emergency.

F. Clean area free of all construction debris and dust upon completion of demolition and/or renovation.

G. During construction operations, keep existing finishes protected from damage. Cover and protect all carpets during construction.

Any carpets or surfaces damaged, as a result of construction activities, will be replaced at the contractor’s expense.

1.18 EMERGENCY MEDICAL SERVICES:

A. Emergency medical services are available for contractors at this facility. For medical emergencies, dial 4999 when inside any building. Report the nature of the emergency and location. The operator will determine whether to dispatch in-house personnel or outside emergency assistance based on the nature of the emergency.

1.19 USE OF GOVERNMENT OWNED MATERIAL AND EQUIPMENT:

A. Use of government owned material and equipment is PROHIBITED except for that material specifically identified for the contractor’s use elsewhere in this contract.

1.20 SUPERINTENDENT COMMUNICATIONS AND RESPONSIBILITIES:

01 00 00 -17

A. At all times during the performance of this contract, the Contractor’s Superintendent is to be available by telephone (portable cellular phone). At the beginning of the contract and prior to beginning any construction, provide the Contracting Officer and COR with the superintendent’s telephone number.

B. The Contractor’s Superintendent shall post pertinent information at each job site for the benefit of the construction workers and for communicating with Medical Center Staff. A 2’x 4’ construction board shall be placed at the job site entrance in accordance with recommendations set forth by The Joint Commission, as illustrated on the sample Attachment D.

C. Prior to the start of work of any contractor or subcontractor employee, they shall read, review with the superintendent, and sign the Orientation of Construction Workers (attachment C.)

D. The Contractors Superintendent shall inspect and document on the Interim Life Safety Measures daily monitoring form the requested data.

E. The Contractors Superintendent shall maintain copies of all forms required by this specification section at the job site and shall be provide to the COR on request.

1.21 SMOKING

A. No smoking is permitted at the Lebanon VAMC except inside designated smoking shelters

B. If any contractor’s or subcontractor’s employee is found smoking in an unauthorized area, the contractor will be charged $200 for the first occurrence and $500 for every occurrence thereafter. The employee is subject to a $50 fine.

C. All contractor and subcontractor employees shall read and sign the Notification of Smoking Policy (attachment B) kept by the project Superintendent

1.22 HAZARDOUS MATERIALS:

A. Many of the operations you are scheduled to perform may involve the use of hazardous materials. Prior to locating hazardous materials on site, all Material Safety Data Sheets will be submitted through the COR for evaluation by the Facility Industrial Hygienist.

B. Storage of hazardous materials within buildings will be minimal with only enough on hand to perform daily work tasks. Flammable materials will either be removed from buildings at the end of the work shift or stored in approved flammable storage containers.

C. Care must be taken to assure adequate ventilation to remove vapors from hazardous materials in use. Many of the patients being cared for in the facility are susceptible to environmental contaminants, even when odors seem minimal. The more effective method to reduce complaints is to close the work area and use adequate ventilation.

1.23 INFECTION, AIRBORNE DUST AND FUME CONTROL DURING CONSTRUCTION:

A. The contractor shall comply with the requirements of the Infection Control Risk Assessment at all times.

B. All areas of construction are to be kept under negative pressure at all times during construction as required by the Infection Control Risk Assessment (ICRA). The contractor shall supply, maintain and

01 00 00 -18 keep in operation, as many negative air machines as required to keep the construction area under 0.010 inch water column negative pressure. The contractor shall supply, install and maintain an air pressure monitor to record the negative pressure in the construction area at all times during the construction period including non-working. The contractor shall supply the COR with the negative pressure records from the air pressure monitor on a weekly basis.

The contractor shall document the visual inspection of negative pressure on a negative air pressure verification log located directly outside the construction area at the start and end of each…

This is the start of the file's text. The full file is on GovTribe.