About this file

The document is a specification and questionnaire for double wall deicer tanks issued by the Illinois Department of Transportation (IDOT). The specification covers the requirements for 6,500-gallon double wall storage tanks capable of safely containing liquids weighing up to 12 pounds per gallon, such as Liquid Magnesium, Calcium Chloride, Beet Juice, or Liquid Salt Brine. The tanks must comply with various technical requirements, including double wall construction, integral UV resistance, lifting lugs, sight glass, and specified fittings and ports. Delivery, manuals, training, and warranty requirements are also detailed. Bidders must provide descriptive literature and proof of manufacturing experience. The tanks are to be delivered to Effingham County.

The specification requires bidders to complete and return the questionnaire with their bid. Pricing and other commercial terms are not provided. The contract is for the State of Illinois, with Effingham County as the jurisdiction. No information is provided about set-asides, incumbents, funding sources, or contract duration and renewal options.

View the file

Other files

File Type Posted
Terms and Conditions~14.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specification No. 572-60-02

Specification No. 572-60-02 Specifications and Questionnaire for Double Wall Deicer Tanks State of Illinois Department of Transportation Bureau of Business Services Specifications and Questionnaire for Double Wall Deicer Tanks August 2018 This specification and questionnaire covers a double walled storage tank(s) for use in storing various melting agents for use by Department of Transportation pavement maintenance operations. The Department of Transportation is specifying acceptable units by required accessories as outlined below.

Each bidder shall submit with their bid two sets of descriptive literature and specifications describing all the equipment and options proposed. This information shall be clearly marked to indicate the make, model, and accessories proposed to be furnished.

Bidders quoting on equipment must submit with their bid written proof of the following:

· The manufacturer of the equipment proposed has been actively involved in the manufacture of the equipment called for in the questionnaire for a period of not less than 5 years.

· Parts and service for the equipment proposed are readily available to the State of Illinois.

It is the responsibility of each bidder to complete and return this questionnaire with the bid.

Unless otherwise specified, the proposed equipment shall be complete in all parts and ready for immediate use upon delivery.

Bidders are advised to carefully read these specifications as changes have been made since the last solicitation issue.

Proposed with this Bid:

Make:
Model:
Manufactured by:
Bidder:
Contact name:
Telephone:
Email:

Tank(s):

The tank(s) shall be used to store a variety of melting agents designed for the winter maintenance of highways. These agents will include but not be limited to Liquid Magnesium, Calcium Chloride, Beet Juice, or Liquid Salt Brine. The tank(s) must be capable of safely containing liquids weighing up to and including 11 to 12 pounds per gallon, in the capacities requested.

· 6,500 gallon - 120″ diameter x 199″ high (approx.)

Complies: |_| Yes|_| No
If No describe:

The tank(s) shall be double wall constructed. The tanks shall be furnished from a single supplier and shall be equal or superior to Snyder Industries Containment System double wall tank series. The outer containment vessel shall have a minimum capacity of 110% of the inner tank.

Complies: |_| Yes|_| No
Tank manufacturer:

All tanks listed in this specification shall be tested by the manufacturer (to ASTM D1998-15), and all test data (including a hydrostatic water test) shall be documented and provided to the end user with the delivery of the tank(s).

Complies: |_| Yes |_| No All tank resins (HDPE – type II) shall be provided with integral U.V. (ultra violet) resistance protection in all tank(s).

Complies: |_| Yes |_| No All tanks shall have at least three (3) top mounted lifting lugs capable of supporting the entire weight of the completely assembled unit. Lugs shall an integral part of the top and molded-in.

Complies: |_| Yes|_| No
Number of lifting lugs:

Tiedown assembly (if required) shall be manufacture of galvanized steel, utilize tank’s molded-in top dome lugs (eight) and be compliant to IBC 2012 & CBC 2013 standards.

Complies: |_| Yes |_| No

Each tank furnished shall be equipped with an easily replaceable, sight glass type of gauge to provide the level of liquid in the tank easily read from a distance.

Complies: |_| Yes|_| No
Describe:

Each tank shall be equipped with the following ports and fittings:

· Manhole in the top, with replaceable gasket, and secured, approximate diameter 24” (Located near the ladder lugs)

· “U” vent 3” PVC with screen, located top center.

· Flange mount 2” fitting (for pump filling) location near the main manhole cover Must accept 2” full port cam-lock fittings.

· On the side of the tank, approximately 10” above the bottom of the tank (tee fitting) w/tube. This must also accept 2” full port cam-lock fittings.

· The top fitting (tee) for the sight glass shall be approximately 8.5” below the top of the tank.

Complies: |_| Yes|_| No
Describe if different:

Each tank shall be molded with lugs to attach a ladder. If the option for the ladder is called for in the bid, the ladder shall be provided. The ladder shall be secured to the tank yet easily removed.

Complies: |_| Yes |_| No Delivery:

The tanks are to be delivered in first-class condition with acceptance subject to Department of Transportation inspection and approval.

Complies: |_| Yes |_| No The tanks shall be delivered fully serviced and ready for operation.

Complies: |_| Yes |_| No Two (2) copies of all operators’ manuals, parts lists, electrical schematics, and warranty information shall be provided at time of delivery.

Complies: |_| Yes |_| No Note: The manuals, parts lists, and service or shop manuals listed above may be furnished on DVD in lieu of paper.

One session of instruction and training by qualified factory and dealer personnel covering operation and maintenance of the machine shall be provided. A video or PowerPoint presentation including operation and maintenance of the product shall be included.

Complies: |_| Yes |_| No Standard tool kits or special tools required for service or maintenance shall be provided.

Complies: |_| Yes |_| No |_| Not Required

Requirements Covering Items Detailed Above:

All equipment cataloged as standard or safety related shall be furnished and in place and shall be included in the purchase price of the unit. Any parts, tools, and/or accessories not specifically called for but required for proper operation shall be provided.

Complies: |_| Yes |_| No Since the continuous operation of this equipment is of the utmost importance and generally of an emergency nature, it is necessary that the successful bidder be in a position to render prompt parts and service within the State of Illinois.

List sources for service:

The vendor or manufacturer of the unit which is considered for award shall, at the request of the State of Illinois, demonstrate this or similar equipment within the receiving District in the State of Illinois and in the presence of authorized state personnel to prove out any features in question.

Complies: |_| Yes |_| No Warranties, Coverage and Duration:

Full coverage warranty on all components for a minimum 12 months from date put in service shall be provided. Attach a copy of warranty with the bid.

Complies: |_| Yes|_| No
Describe warranty:
If No to any portion, explain:

Bid Package:

Bidders will need to send two copies of each of the following with their bid response.

a) Specification Questionnaire

b) Descriptive Literature

File details come from the government source that posted it. Updated .