This document is an architectural drawing for a VA construction project, specifically the Door and Window Schedule for Correct Infrastructure Deficiencies in Building 408 located in Dayton, OH. The drawing provides comprehensive details about window and door specifications for the project, including precise measurements, materials, and types. The window schedule lists 11 different window types, all made of aluminum, with varying dimensions ranging from 2' - 3" to 6' - 8" in width and 2' - 0" to 7' - 0" in height. The door schedule details 7 doors with different configurations, including flush and half-glass types, constructed primarily of hollow metal (HM) and wood (WD) materials, with door widths ranging from 2' - 6" to 6' - 0" and standard height of 7' - 0". The document is marked as 100% Construction Documents, dated 08/15/2022, and is fully sprinklered, with the project being managed by the VA Office of Construction and Facilities Management.

View the file

Other files

File Type Posted
090600 - Schedule of Finishes.pdf PDF
36C25025B0036 0010.docx DOCX document
085113 - Aluminum Windows.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIXED

AS SCHEDULED

A S

S C

H E

D U

LE

D

SINGLE HUNG -

SIMULATED

AS SCHEDULED

A S

S C

H E

D U

LE

D

DOUBLE HUNG -

SIMULATED

AS SCHEDULED

A S

S C

H E

D U

LE

D

S3

AS SCHEDULED 2" TYP

A S

S C

H E

D U

LE

D

AS SCHEDULED AS SCHEDULED

A S

S C

H E

D U

LE

D

8" X 8"

A F

F

3'

2'

TYP

TYP

TYP

TYP

FL HG

T

DOOR TYPE ABBREVIATIONS

FL FLUSH

HG HALF GLASS

DOOR MATERIAL ABBREVIATIONS

AL ALUMINUM

HM HOLLOW METAL

WD WOOD

FRAME TYPE ABBREVIATIONS

S2 SINGLE / 2" HEAD

E2 DOUBLE EGRESS / 2" HEAD

FRAME MATERIAL ABBREVIATIONS

AL ALUMINUM

HM HOLLOW METAL

WD WOOD

2"

AS SCHEDULED

2"

4"

DOUBLE E3

S3-T

AS SCHEDULED 2" TYP

2"

AS SCHEDULED

2"

4"

DOUBLE

W/ TRANSOM

E3-T W/ TRANSOM

ALUM WINDOW FRAME

ALUM WINDOW TRIM

EDGE CONDITION CHANGES

VERIFY IN FEILD

1/4"

4"

EXISTING BRICK MASONARY

WALL: WALL THICKNESS MAY

VERY, VERIFY IN FIELD ALUM WINDOW TRIM

EXISTING FACE OF INTERIOR WALL

ALUM WINDOW FRAME

WOOD BLOCKING AND

SHIMS AS REQUIRED

ALUM BREAK METAL

FLASHING PAINTED WHITE

TO MATCH WINDOW FRAME

EDGE CONDITION CHANGES

VERIFY IN FIELD

4"

EXISTING BRICK MASONARY

WALL: WALL THICKNESS MAY

VERY, VERIFY IN FIELD

4"

EXISTING BRICK MASONARY

WALL: WALL THICKNESS MAY

VERY, VERIFY IN FIELD

HOLLOW METAL FRAME,

GROUT SOLID,

RE: DOOR SCHEDULE

SEALANT, BOTH SIDES

EXISTING BRICK MASONARY

WALL: WALL THICKNESS MAY

VERY, VERIFY IN FIELD

HOLLOW METAL FRAME,

GROUT SOLID,

RE: DOOR SCHEDULE

EXISTING BRICK MASONARY

WALL: WALL THICKNESS MAY

VERY, VERIFY IN FIELD

SEALANT, BOTH SIDES

JAMB ANCHOR

1"

/1

6"

3/ 8"

9/

1/

8"

1'

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

N O T F

O R

C O N

STR

U C

TIO

N

P

.1

V

A D a y to n

I D

IQ

\T

O

C o rr e c t In fr a s tr u c ti o n

D e fe c ie n c ie s B ld g

G D

I\

D ra w in g s \2

-1 A rc h it e c tu re \1

-1 R e v it \1

.1

.0

B L

D G v

.r v t

/2

/2

:3

:2

P

M

AS602

DOOR AND WINDOW SCHEDULE

GUIDON DESIGN INC.

1221 N. PENNSYLVANIA STREET, SUITE 200

INDIANAPOLIS, IN 46202

317-800-6388

ADAM OGRZEWALLA

HEAPY ENGINEERING

1400 W DOROTHY LANE

DAYTON, OH 45409

MATT GRAHAM

CORRECT INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OH 45428

552-19-102

PHIL WEST, COR

08/15/2022 JG KJW

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

WINDOW SCHEDULE

TYPE

MARK TYPE MATERIAL WIDTH HEIGHT Comments

A SINGLE HUNG - SIMULATED ALUMINUM 2' - 3" 5' - 0"

A.1 FIXED ALUMINUM 2' - 3" 2' - 9"

B SINGLE HUNG - SIMULATED ALUMINUM 3' - 6" 5' - 0"

B.1 FIXED ALUMINUM 3' - 6" 2' - 9"

C FIXED ALUMINUM 3' - 0" 2' - 0"

D DOUBLE HUNG - SIMULATED ALUMINUM 5' - 2" 4' - 2"

D.1 FIXED ALUMINUM 5' - 2" 2' - 4"

E DOUBLE HUNG - SIMULATED ALUMINUM 5' - 2" 6' - 0"

E.1 FIXED ALUMINUM 5' - 2" 3' - 0"

F SINGLE HUNG - SIMULATED ALUMINUM 3' - 0" 4' - 8"

G SINGLE HUNG - SIMULATED ALUMINUM 2' - 4" 4' - 8"

H DOUBLE HUNG - SIMULATED ALUMINUM 6' - 8" 5' - 2"

H.1 FIXED ALUMINUM 6' - 8" 2' - 10"

I DOUBLE - HUNG - SIMULATED ALUMINUM 6' - 8" 7' - 0"

J SINGLE HUNG - SIMULATED ALUMINUM 4' - 2" 7' - 0"

K DOUBLE HUNG - SIMULATED ALUMINUM 3' - 0" 4' - 2"

Y 4' - 0" 2' - 4"

Grand total: 341

DOOR SCHEDULE

DOOR

NUMBER

DIMENSIONS DOOR FRAME GLAZING

TYPE

HARDWARE

SET COMMENTSWIDTH HEIGHT THICKNESS TYPE MATERIAL FINISH TYPE MATERIAL FINISH

107 3' - 6" 7' - 0" 1 3/4" FL HM PAINT S3-T HM PAINT N/A PANIC

C-2-5B 3' - 10" 7' - 0" 1 3/4" FL HM PAINT S2 HM PAINT

C-2-5C 2' - 6" 7' - 0" 1 3/4" FL HM PAINT S3 HM PAINT N/A PANIC

C-2-5E 6' - 0" 7' - 0" 1 3/4" HG HM PAINT E3-T HM PAINT GL-1 PANIC

C-2-5F 3' - 6" 7' - 0" 1 3/4" HG WD PAINT S3 HM PAINT GL-1 PANIC

C-2-5G 3' - 6" 7' - 0" 1 3/4" FL HM PAINT S3-T HM PAINT N/A PANIC

C-2-5H 3' - 6" 7' - 0" 1 3/4" FL HM PAINT S3-T HM PAINT N/A PANIC

C-2-5I 3' - 0" 7' - 0" 1 3/4" FL HM PAINT S3 HM PAINT N/A PANIC

SCALE: 3" = 1'-0"AS602

3 INTERIOR WINDOW HEADER DETAIL

SCALE: 3" = 1'-0"AS602

4 INTERIOR WINDOW JAMB DETAIL

SCALE: 3" = 1'-0"AS602

5 INTERIOR WINDOW SILL DETAIL

SCALE: 6" = 1'-0"AS602

6 DOOR HEAD DETAIL, CMU

SCALE: 6" = 1'-0"AS602

7 DOOR JAMB DETAIL, CMU

Revisions: Date: 05/02/2025

DOOR SCHEDULE

09/08/2025ADDENDUM #3