This is a specification document for dry-dock repairs and maintenance services for the USCG Station Puget Sound (55107) vessel during fiscal year 2027. The solicitation number is 70Z04026QSBPL0015, issued by the Department of Homeland Security U.S. Coast Guard. The period of performance runs from February 16, 2027 through July 16, 2027, providing a five-month window for completion of all dry-dock work.

The specification package outlines the technical requirements, repair scope, and service standards required for the vessel's dry-dock maintenance. Interested contractors must submit responses in accordance with the Combined Synopsis/Solicitation document (Specification Package Rev-0, dated May 13, 2026), including completion of the Past Performance Questionnaire and Schedule of Supplies and Services. Pricing terms, specific repair requirements, and contractor qualifications are detailed within the specification documentation. This is a solicitation open to qualified contractors capable of executing comprehensive dry-dock repair and maintenance operations on a USCG vessel within the specified timeframe and performance standards.

View the file

Other files

File Type Posted
555107- 70Z04026QSBPL0015_0_US.pdf PDF
55107 PPQ.pdf PDF
55107-Schedule of Supplies and Services.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG 55107 (ANB 55A)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2027

Developed By: Timothy Tolliver

(Rev-0, 13 May 2026)

USCG 55107 (ANB-55A) DRYDOCK AVAILABILITY FY2027

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: General Welding, Provide WORK ITEM 2: Hull Plating, U/W Body, Inspect WORK ITEM 3: Hull Plating, U/W Body, Ultrasonic Testing WORK ITEM 4: Appendages, U/W, Leak Test WORK ITEM 5: Accessible Spaces, Inspect WORK ITEM 6: Mast, Inspect WORK ITEM 7: Main Diesel Engine(s), Align WORK ITEM 8: Exhaust Muffler(s), Clean and Inspect WORK ITEM 9: Exhaust Piping, Clean and Inspect WORK ITEM 10: Fuel Valves, Renew WORK ITEM 11: Ship Service Diesel Generator (SSDG), Clean and Inspect WORK ITEM 12: Sea Valves, Renew WORK ITEM 13: Sea Strainers, Duplex, All Sizes, Overhaul WORK ITEM 14: Potable Water Tank, Clean and Inspect WORK ITEM 15: Diesel Tanks, Refuel WORK ITEM 16: Buoy Handling Equipment, Renew WORK ITEM 17: Rub Rail, Fendering System, Remove, Inspect, Install WORK ITEM 18: Decks – Exterior (Buoy), Preserve 100 Percent WORK ITEM 19: Decks - Exterior, Preserve, Non-Skid Broadcast Grit System WORK ITEM 20: Superstructure, Preserve, 100 Percent WORK ITEM 21: Interior Hull Insulation, Inspect WORK ITEM 22: Marine Chemist Services, Provide WORK ITEM 23: Drydock WORK ITEM 24: Temporary Services, Provide WORK ITEM 25: Sea Trial Performance, Support, Provide WORK ITEM 26: U/W Body, Preserve, 100 percent WORK ITEM 27: Hull Plating Freeboard, Preserve, 100% WORK ITEM 28: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 29: Propeller Shafts, Remove, Inspect, and Install WORK ITEM 30: Propellers, Remove, Inspect and Install WORK ITEM 31: Standard Hoses, Renew WORK ITEM 32: Rudder Assembly, Remove, Inspect and Reinstall WORK ITEM 33: Hull Identification Markings, Apply WORK ITEM 34: Cathodic Protection / Zincs, Renew WORK ITEM 35: Propeller Shaft Packing Stuffing Box, Remove and Install WORK ITEM 36: Propeller Shaft Packing, Renew WORK ITEM 37: Water Lubricated Shaft Bearings, Renew WORK ITEM 38: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift . 135 WORK ITEM 39: Sewage Holding Tanks, Clean and Inspect WORK ITEM 40: Grey Water Holding Tanks, Clean and Inspect iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

55119)

Coast Guard Drawing 55 ANB 103-002, Rev P, Outboard Profile, Sections and Arrangements

Coast Guard Drawing 55 ANB 103-002, Rev R, Outboard Profile Sections & Arrangement

Coast Guard Drawing 55 ANB 103-002, Rev R, Outboard Profile, Sections and Arrangements

Coast Guard Drawing 55 ANB 103-2, Rev R, Outboard Profile and Arrangements

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan & Sections

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan and Sections 55101-55112

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan and Sections

Coast Guard Drawing 55 ANB 1101-002, Rev A, Construction Details

Coast Guard Drawing 55 ANB 1101-2, Rev A, Construction Details (55101-55112)

Coast Guard Drawing 55 ANB 1112-003, Rev A, Deck Winch Foundation Port/Starboard

Coast Guard Drawing 55 ANB 112-003, Rev C, Marine Crane Foundation Mods. (55101-55122)

Coast Guard Drawing 55 ANB 2002-002, Rev A, Crane & Deck Winch Hydraulics

Coast Guard Drawing 55 ANB 2200-1, Rev B, Rudder Port Stuffing Box Hub

Coast Guard Drawing 55 ANB 2200-1, Rev B, Rudder Stock & Stuff Box-Hub

Coast Guard Drawing 55 ANB 2200-2, Rev A, Steering Hydraulic System

Coast Guard Drawing 55 ANB 2200-2, Rev A, Steering-Hydraulic System

Coast Guard Drawing 55 ANB 3803-001, Rev C, Air Conditioning Systems Hulls 55101-55112

Coast Guard Drawing 55 ANB 4000-001, Rev E, Machinery Arrangement

Coast Guard Drawing 55 ANB 4000-1, Rev E, Machinery Arrangement

Coast Guard Drawing 55 ANB 4000-1, Rev E, Machinery Arrangement.

Coast Guard Drawing 55 ANB 4000-2, Rev B, Machinery Details

Coast Guard Drawing 55 ANB 4103-001, Rev A, Mn Eng Raw Water & Reduction Gear L/O Piping

Coast Guard Drawing 55 ANB 4301-001, Rev B, Forward End of Propeller Shaft and Propeller Shaft Coupling

Coast Guard Drawing 55 ANB 4301-002, Rev -, Propeller Shaft (A Class only)

Coast Guard Drawing 55 ANB 4301-2, Rev -, Propulsion Shaft

Coast Guard Drawing 55 ANB 4801-001, Rev D, Bilge Piping

Coast Guard Drawing 55 ANB 4804-1, Rev A, Fresh Water Tank, Access & Cover v (Rev-0)

Coast Guard Drawing 55 ANB 4805-2, Rev C, Potable Water Piping Hot & Cold (55101-55112)

Coast Guard Drawing 55 ANB 5500-001, Rev A, Fuel Supply Diag

Coast Guard Drawing 55 ANB 5500-001, Rev A, Fuel Supply Diagram

Coast Guard Drawing 55 ANB 573-001, Rev B, Portable Chain Stopper and Mounting

Coast Guard Drawing 55 ANB 573-002, Rev A, Removable Tow Rope Guard for Chain Stopper

Coast Guard Drawing 55 ANB 634-001, Rev -, Deck Covering

Coast Guard Drawing 55 ANB 634-1, Rev -, Deck Covering

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan (Supersedes 55-ANB-700-001, 55B-ANB-

700-002 & 55C-ANB-801-008)

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing 55 ANB-3901-1, Rev A, Insulation Installation (55101-55112)

Coast Guard Drawing 55 ANB-4000-1, Rev E, Machinery Arrangement

Coast Guard Drawing 55 ANB-4808-1, Rev B, Drains And Holding Tank Piping (A Class)

Coast Guard Drawing 55-ANB-500-001, Rev A, Lines & Offsets 55101-55112

Coast Guard Drawing 55-ANB-8201-001, Rev A, Lifting Slings Gen Arrg

Coast Guard Drawing 55-ANB-8201-002, Rev -, Boat Cradle Shipping

Coast Guard Drawing 55-ANB-997-001, Rev -, Docking Plan

Coast Guard Drawing 55B ANB 103-001, Rev K, Outboard Profile, Sections and Arrangements

Coast Guard Drawing 55B ANB 103-1, Rev K, Outboard Profile and Arrangements

Coast Guard Drawing 55B ANB 2000-001, Rev A, Crane & Deck Winch Hydraulic (55113-

Coast Guard Drawing 55B ANB 4000-001, Rev G, Machinery Arrangement

Coast Guard Drawing 55B ANB 4000-1, Rev G, Machinery Arrangement

Coast Guard Drawing 55B ANB 4000-1, Rev G, Machinery Arrangement.

Coast Guard Drawing 55B ANB 4103-002, Rev C, Main Engine Cooling System

Coast Guard Drawing 55B ANB 4301-001, Rev B, Shaft Coupling

Coast Guard Drawing 55B ANB 4301-002, Rev -, Propeller Shaft (B & C Class only)

Coast Guard Drawing 55B ANB 4901-002, Rev A, Compressed Air System

Coast Guard Drawing 55B ANB-3901-1, Rev D, Insulation Application & Details

Coast Guard Drawing 55B ANB-4000-1, Rev G, Machinery Arrangement

Coast Guard Drawing 55B ANB-4801-4, Rev-, Sanitary Drain Systems (B Class)

Coast Guard Drawing 55C ANB 170-001, Rev C, Mast Construction and Details

Coast Guard Drawing 55C ANB 201-001, Rev D, Machinery Arrangement

Coast Guard Drawing 55C ANB 201-1, Rev D, Machinery Arrangement

Coast Guard Drawing 55C ANB 201-1, Rev D, Machinery Arrangement.

Coast Guard Drawing 55C ANB 256-001, Rev C, Main Engine Cooling System

Coast Guard Drawing 55C ANB 514-001, Rev A, A/C Piping Plan & Details

Coast Guard Drawing 55C ANB 801-001, Rev H, Outboard Profile, Sections and Arrangements

Coast Guard Drawing 55C ANB 801-007, Rev B, Machinery Details

Coast Guard Drawing 55C ANB 801-7, Rev B, Machinery Details

Coast Guard Drawing 55C ANB-201-001, Rev D, Machinery Arrangement

Coast Guard Drawing 55C ANB-528-001, Rev A, Sanitary Drain System (C Class) vi (Rev-0)

Coast Guard Drawing FL-85-002, Rev D, GFE Boat Hot Work Diagrams

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

COAST GUARD PUBLICATIONS

SWBS Group(s) 503-562, Section A, Pump Freshwater

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 2048, SWBS 233, Jun 1988, Manufacturer’s Information Book – SWBS Group 233, 55' ANB (A), (B), and (C) Type Boats, Sections A, B, and C

Coast Guard Technical Publication (TP) 3394, Jan 2006, Manufacturer’s Information Book SWBS Group 167-261

Coast Guard Technical Publication (TP) 3394, January 2006, Manufacture’s Instruction Book- SWBS Group(s) 167-261, Section B, Globe Valves

Coast Guard Technical Publication (TP) 3394, SWBS 167-261, Jan 2006, Manufacturer’s Instruction Book, SWBS Group 167-261

Coast Guard Technical Publication (TP) 3394, SWBS 167-261, Jan 2006, Manufacturer's Instruction Book SWBS Group(s) 167-261, SWBS 241, Sec A, Marine Gear

Coast Guard Technical Publication (TP) 3397, Manufacturer’s Instruction Book SWBS 561, Section A, Steering Gear System

Coast Guard Technical Publication (TP) 3398, May 2004, Manufacturer’s Instruction Book- SWBS 633, Section A, Zincs, Hull

Coast Guard Technical Publication (TP) 3487, April 2012, Manufacturer’s Instruction Book- SWBS Group(s) 589, Section A, Crane Model MCK-420KM

Coast Guard Technical Publication (TP) 3487, April 2012, Manufacturer’s Instruction Book- SWBS Group(s) 589, Section B, Hydraulic Planetary Hoist – Model BG6A & BG6B

Coast Guard Technical Publication (TP) 3923, Apr 2004, Ship’s Service Diesel Generator Set Model

MDKBE

Coast Guard Technical Publication (TP) 3923, Manufacturer’s Information Book, April 2004, Ships Service Diesel Generator Set - MDKBE

Coast Guard Technical Publications (TP) 3397, Manufacturer’s Instruction Book-

Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022`, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place vii (Rev-0)

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ships Structures

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

American Society for Testing and Materials (ASTM) International F1508, 2021, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society of Mechanical Engineers (ASME) B16.34, 2025, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2022, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2022, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Description (CID) A-A-59313 (Notice 2), Nov 2019, Thread Compound; Antiseize, Zinc Dust-Petrolatum

Commercial Item Description (CID) A-A-59316, Abrasive Materials for Blasting

International Standard for Organization (ISO) 484/2, Dec 2015, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2022 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2022 Edition, Butterfly Valves viii (Rev-0)

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72A, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-DTL-18001L (Notice 2), Jun 2025, Anodes, Sacrificial Zinc Alloy (Commercially Accepted -

ASTM B418)

MIL-G-24716A, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

Society of Automotive Engineers (SAE) Standard J1475, 2014, Hydraulic Hose Fittings for Marine Applications

Society of Automotive Engineers (SAE) Standard J1942, 2019, Hose and Hose Assemblies for Marine Applications

Society of Automotive Engineers (SAE) Standard J1942-1, 2025, Qualified Hoses for Marine Applications

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning ix (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

29 Y **Shaft, Propeller (A-

Class only) NSN: 2010-01-599-9644 or

PN: DRWG #55 ANB-400001-

2 ea. 4,909.45

29 N **Coupling, Shaft (A- Class only)

NSN: 3040-01-135-4315 or

PN: XB6168

2 ea. 1,146.13

30 Y **Propeller, Right Hand (38x32)

NSN: 2010-01-130-4949 PN:

55ANB38X32RH

1 ea. 2,687.00

30 Y **Propeller, Left Hand (38x32)

NSN: 2010-01-125-3273 PN:

55ANB38X32LH

1 ea. 3,799.34

37 N See Note Below*Port & Starboard

Intermediate Bearing

NSN: 3120-01-131-3692 PN:

E13600

1 151.75

37 N *Port Strut Bearing NSN: 3120-01-131-3692 PN:

E13600

1 151.75

37 N *Starboard Strut Bearing

NSN: 3120-01-131-3692 PN:

E13600

1 151.75

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item

Title

3 Hull Plating, U/W Body, Ultrasonic Testing

4 Appendages, U/W, Leak Test

5 Accessible Spaces, Inspect

8 Exhaust Muffler(s), Clean and Inspect

9 Exhaust Piping, Clean and Inspect

13 Sea Strainers, Duplex, All Sizes, Overhaul

16 Buoy Handling Equipment, Renew

26 U/W Body, Preserve, 100 percent

29 Propeller Shafts, Remove, Inspect, and Install

32 Rudder Assembly, Remove, Inspect and Reinstall xi (Rev-0)

PRINCIPAL CHARACTERISTICS

55' ANB

PHYSICAL

Length overall 58' 4" Length overall - hull only 55' 0" Operating displacement 64,620 lbs.

Cargo, maximum 4,000 lbs.

Full load displacement 68,620 lbs.

Draft at operating displacement 5' 0" Draft at full load 5' 1" Freeboard fwd @ full load displ 5' 9-7/8" Freeboard aft @ full load displ 4' 9-1/8" Hoisting weight 63,900 lbs.

Shipping weight 54,630 lbs.

HULL

Hull material Aluminum Hull 10 each, bolted Propeller Shaft: 2 per shaft Frame spacing FR 1 to 2 3' 6" FR 2 to 8 4' 0" FR 8 to 9 3' 3" FR 9 to 10 3' 0" FR 10 to 13 3' 3" FR 13 to 15 3' 7"

MACHINERY

Engine details Gm 12v-71, 540 HP @ 2300 rpm, twin disc 514m gear, 2.5:1 reduction, 920 srpm Electrical system 120/240 VAC 30 KW single phase, 24 VDC Propeller details 38" D x 32" P, 3-blade R & L, 2-3/4" bore, Columbian "Hydroflite" Maximum speed 22 knots Cruise speed 18 knots Fuel capacity (diesel) 1,045 gal.

Range at Cruise 350 miles

TANKS

Fresh water capacity 240 gal.

Sanitary water capacity 110 gal.

OTHER DATA

Special features Crane, 2,000 lbs. capacity fire pump, 500 GPM @ 231 ft

1 (Rev-0)

00000_0226_FLT

REC_00000_FLT_Boats @ Commercial Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-0)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must

3 (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.6.1 Coast Guard turn-over preparation. The Contractor must be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew must be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:

3.6.1.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.

3.6.1.2 The Contractor may commence/continue work during these time frames.

3.6.1.3 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.

3.6.1.4 The Unit will contact the servicing ESD or ESU to set up removal/installation of the transducer if Unit personnel are unable to accomplish this task.

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

4 (Rev-0)

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

11 (Rev-0)

4.2 Tank and Void Assessment form.

12 (Rev-0)

13 (Rev-0)

07400_AKP_0925_BOAT_FLT

WORK ITEM 1: General Welding, Provide

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide general welding as identified in Table 1 (Welding).

TABLE 1 – WELDING

ITEM DESCRIPTION LOCATION APPROXIMATE

SQFT.

PHOTO ID

Crop and Renew Forepeak Bilge 3 Square Feet Photo #1

Perform Clad Welding Forepeak Frame STBD Side 6 Square Inches Photo #2

Inspect/Fabricate/Renew Windshield Washer Nozzles N/A Photos #3

Perform Clad Welding Pilothouse Exterior (Portside) 36 Square Inches Photo #4

Weld and Straighten Engineroom N/A Photo #5

Perform Clad Welding Engineroom Portside Aft (Muffler) 2 Square Inches Photo #6

Perform Clad Welding Port Shaft Seal 1 Square Foot Photo #7

Perform Clad Welding Crew Berthing Fwd of Frame 5 26 Square Inches Photo #8

Perform Clad Welding Starboard Shaft Seal 1 Square Foot Photo #9

Perform Clad Welding P/S Bilge Work Platform 2 Square Feet N/A

Inspect/Fabricate/Renew Pilothouse Oven Range/Counter Top N/A Photo #10

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing FL-85-002, Rev D, GFE Boat Hot Work Diagrams

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

14 (Rev-0)

OTHER REFERENCES

None

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

None.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Requirement. The Contractor must provide general welding, including but not limited to, fabrication, brazing, inspection, plate renewal, crack repair, overlay, and associated processes on Coast Guard vessels and equipment in accordance with Coast Guard Drawing FL-85-002 and SFLC Std Spec 0740.

3.3 Bidding. The Contractor must ensure for bidding purposes this specification will be broke down by the following:

One linear foot of welding/brazing.

Four square inches of clad/overlay welding.

One hour of fabrication.

One square foot of plate renewal.

TABLE 2 – PLATE TYPE

STEEL PLATE ALUMINUM PLATE

THICKNESS WEIGHT

PER SQFT.

TYPE/GRADE THICKNESS WEIGHT

PER SQFT

TYPE/ALLOY

3/16 (.1875) 7.66 lb 1/4 (.250) 10.21 lb 1/4 (.250) 3.53 lb 5/16 (.3125) 12.76 lb 5/16 (.3125) 4.41 lb 3/8 (.375) 15.31 lb 3/8 (.375) 5.29 lb 1/2 (.500) 20.42 lb 1/2 (.500) 7.06 lb

15 (Rev-0)

3.4 Touch-up preservation, general. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

Photo #1:

16 (Rev-0)

Photo #2:

Photo #3:

17 (Rev-0)

Photo #4:

Photo #5:

Photo #6:

18 (Rev-0)

Photo #7:

Photo #8:

Photo #9:

19 (Rev-0)

Photo #10: Remove oven range. Raise counter up level just under outlets circled in picture. Plumbing for sink needs to be fixed so it will drain properly. Re-position sink more forward to align with drawing 55- ANB-0103-2 (Outboard Profile, Sections And Arrangements). Sink would be in vicinity of where oven is currently following the drawing. Remove all particle wood cabinetry and replace with stainless steel material. Recommend a site visit for contractor to take measurement to formulate detailed plans to construct.

20 (Rev-0)

11000_ESD_0723_FLT

REC_11000_UWHIB_FLT_55 ANB ‘A’ Class (ALL) (0126)

WORK ITEM 2: Hull Plating, U/W Body, Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan and Sections

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

21 (Rev-0)

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor must accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor must provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:

A hull repair supervisor and a marker.

Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor must inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor must inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor must inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor must check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor must inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor must check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

22 (Rev-0)

3.2.6 Zinc anodes.

3.2.6.1 The Contractor must remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor must visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor must accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).

Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.

4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.

4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

23 (Rev-0)

11010_UT_ESD_0423_FLT

REC_11010_UT_FLT_55’ ANB ‘A’ Class (ALL) (0126)

WORK ITEM 3: Hull Plating, U/W Body, Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan and Sections

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph:

3.2 (UT measurements).

24 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor must perform a total of 150 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawings 55 ANB 997-001 and 55 ANB 1101-001 for guidance, in accordance with SFLC Std Spec 0740, Appendix C.

Mark up a copy of Coast Guard Drawing 55 ANB 1101-001 to show all locations selected for measurement and record all measurements in Table I (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit a CIR, to also include the marked up drawing(s) and completed Table I.

4.1 UT Table. Table 1 provided below is for the recording of all UT measurements.

25 (Rev-0)

TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT

PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE

26 (Rev-0)

11400_ESD_0723_FLT

REC_11400_UWAppndgs_FLT_55’ ANB ‘A’ Class (ALL) (0126)

WORK ITEM 4: Appendages, U/W, Leak Test

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform leak test of the U/W appendages.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 55 ANB 997-001, Rev -, Docking Plan (Supersedes 55-ANB-700-001, 55B-ANB-700-002 & 55C-ANB-801-008)

Coast Guard Drawing 55 ANB 1101-001, Rev D, Construction Plan and Sections 55101-55112

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single- Component Adhesives (AN)

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

3.2 Leak test.

3.4 Appendage air test.

27 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Leak test. In the presence of the Coast Guard Inspector, the Contractor must accomplish…