551-24241-CAK_24005437A_GRASS LAKE WEIGH STATION Bid Set_5-30-2025.pdf
PDF 9 MB Posted
- Solicitation number
- RFQ-171-250000000480-2
- Issued by
- Kalamazoo County, Grand Rapids City, Michigan
About this file
The document is a comprehensive set of architectural and engineering design plans for a building renovation project by the State of Michigan, Department of Technology, Management, and Budget (DTMB) for the Grass Lake Weigh Station Office Addition located in Jackson, Michigan. The project involves a building addition and renovation of an existing facility along Interstate 94, with design documents dated May 30, 2025. The bid set includes detailed plans covering architectural, structural, mechanical, electrical, and civil engineering aspects, with sheets spanning demolition, site plans, foundation details, floor plans, elevations, lighting, power, and mechanical systems.
The project is structured as a design-bid-build contract, with Colliers Engineering & Design serving as the structural engineer and architect. The renovation will expand the existing weigh station facility, adding a new conference room and updating various building systems. The design emphasizes energy efficiency, compliance with the 2021 Michigan Building Code, and meets accessibility standards. The project includes replacing electrical panels, updating lighting and power systems, modifying HVAC infrastructure, and making structural improvements. The estimated project scope suggests a medium-sized government infrastructure upgrade focused on improving functionality and efficiency of a state transportation facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
7050 West Saginaw Hwy. // Suite 200 // Lansing, MI 48917
517.272.9835 / 517.272.9836 fax www.colliersengineering.com
STRUCTURAL ENGINEER:
COLLIERS ENGINEERING & DESIGN
KIRA TENNES
7050 WEST SAGINAW HWY. SUITE 200
LANSING, MI 48917
517.272.9835
DEPARTMENT OF TECHNOLOGY,
MANAGEMENT, AND BUDGET
1/
1.
C
A K
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P
L A
C H
R
A
D
IR
E C
T O
R
F A
C
IL
IT
IE
S A
N D
B U
S
IN
E S
S S
E R
V
IC
E S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E S
IG
N E D
D R A W N
C H E C K E D
A P P R O V E D
D A T E
IS
S U E D
F O R
P E R M
IT
S E T
B
ID
S E T
F
IN
A L
R E C O R D
P L A N
R E V
IE
W
C O R R E C T
IO
N
S H E E T
ID
E N T
IF
IC
A T
IO
N
N O
F
IL
E
N O
C O N T R A C T
N O
BID SET
DRAWING INDEXPROJECT CONTACT LIST
OWNER:
STATE OF MICHIGAN, DTMB
CHRIS KULHANEK
3111 W ST. JOSEPH STREET
LANSING, MI 48917
CONTRACTOR:
TBD
ARCHITECT:
COLLIERS ENGINEERING & DESIGN
DAVID MOSS
7050 WEST SAGINAW HWY. SUITE 200
LANSING, MI 48917
517.272.9835
MECHANICAL ENGINEER:
COLLIERS ENGINEERING & DESIGN
MATT HOLLENBECK
3410 BRIARFIELD BOULEVARD. SUITE C
MAUMEE, OH 43537
567.804.5118
ELECTRICAL ENGINEER:
COLLIERS ENGINEERING & DESIGN
ANGELA ROBINSON
7050 WEST SAGINAW HWY. SUITE 200
LANSING, MI 48917
517.272.9835
W e st S a g in a w H w y.
S u ite
L a n si n g
M
I o ff ic e
.2
.9 fa x:
.2
.9 w w w .c o lli e rs e n g in e e ri n g .c o m
B U
IL
D
IN
G
R E
N O
V A
T
IO
N S
F O
R
G R
A S
S L
A K
E S
C A
L E
E /B
I-
J A
C K
S O
N
M
IC
H
IG
A N
G R
A S
S L
A K
E W
E
IG
H S
T A
T
IO
N O
F F
IC
E
A D
D
IT
IO
N
05/30/25
Grass Lake Weigh Station Addition
State of Michigan
3111 W. St Joseph Street, Lansing, MI 48917
G000
D M O S S
D M O S S
F P E T E R S E N
D M O S S
24005437
05/30/25
3/
/2
P
E R
M
IT
S E
T
5/
/2
IS
S U
E D
F O
R B
ID
00 - GENERAL
G000 COVER SHEET X X
G001 CODE COMPLIANCE & LIFE SAFTEY PLANS X X
01 - CIVIL
C-010 SURVEY X X
C-100 DEMO PLAN X X
C-200 SITE PLAN X X
C-300 GRADING AND UTILITY PLAN X X
C-310 SESC PLAN X X
C-311 SESC DETAILS X X
C-700 DETAILS X X
03 - STRUCTURAL
S001 GENERAL NOTES X X
S002 GENERAL NOTES X X
S010 LOAD DIAGRAMS X X
S101 FOUNDATION & FRAMING PLANS X X
S501 SECTIONS & DETAILS X X
S901 ISOMETRIC VIEWS X X
04 - ARCHITECTURAL
A001 GENERAL NOTES AND LEGENDS X X
AD101 DEMOLITION PLANS AND ELEVATIONS X X
A101 FLOOR PLAN AND ISOMETRICS X X
A102 ROOF PLAN X X
A121 CEILING PLAN X X
A201 EXTERIOR ELEVATIONS X X
A301 BUILDING SECTIONS X X
A501 ENLARGED DETAILS X X
A601 SCHEDULES, FINISH PLANS, BASIS OF DESIGN X X
05 - MECHANICAL
M001 MECHANICAL LEGEND SHEET X X
M101 MECHANICAL PLANS X X
M201 MECHANICAL SCHEDULES & DETAILS X X
08 - ELECTRICAL
E001 LEGEND X X
ED101 DEMOLITION PLAN X X
E101 POWER PLAN X X
E102 POWER PLAN X X
E201 LIGHTING PLAN X X
E202 LIGHTING PLAN X X
E801 SCHEDULES X X
DATE DESCRIPTION
FE
OCCUPANCY GROUP
# OCCUPANTS
S.F.
LEGEND
EXIT SIGN
EXIT
COMMON PATH OF EGRESS DISTANCE
TRAVEL DISTANCE TO EXIT DISCHARGE
(INCLUDING STAIRS)
FIRE EXTINGUISHER CABINET
SIGN DIRECTION
FACE OF SIGN
TD
CPET
B
382 SF
(NEW ADDITION)
C P
O T
C P
O T
B
1335 SF
(EXISTING)
33.75" CLEAR
168 ALLOW
4 ACTUAL
S H E E T
ID
E N T
IF
IC
A T
IO
N
N O
IS
S U E D
F O R
D A T E
F
IL
E
N O
C O N T R A C T
N O
P E R M
IT
S E T
B
ID
S E T
F
IN
A L
R E C O R D
D E S
IG
N E D
D R A W N
C H E C K E D
A P P R O V E D
S T
A T
E O
F M
IC
H
IG
A
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
B U
IL
D
IN
G
R E
N O
V A
T
IO
N S
F O
R
1/
1.
C
A K
Y
G R
A S
S L
A K
E S
C A
L E
E /B
I-
J A
C K
S O
N
M
IC
H
IG
A N
G R
A S
S L
A K
E W
E
IG
H S
T A
T
IO
N O
F F
IC
E
A D
D
IT
IO
N
W e st
S a g in a w
H w y.
S u ite
L a n si n g
M I o ff ic e
.2
.9
.2
.9 w w w .c o lli e rs e n g in e e ri n g .c o m
A D
A M
P L
A C
H
R A
D
IR
E
C T
O R
D M O S S
F P E T E R S E N
D M O S S
D M O S S
G001
SCALE : 1/4" = 1'-0"
CODE COMPLIANCE DIAGRAM - FIRST FLOOR
N
SINGLE
MIXED OCCUPANCY
IF SEPARATED, FIRE RESISTANCE RATING OF FIRE BARRIER :
OCCUPANCY CLASSIFICATION(S):
USES:
CONSTRUCTION CLASSIFICATION :
AUTOMATIC SPRINKLER SYSTEM PROVIDED: YES
13R
NO
13NFPA STANDARD:
OCCUPANCY CLASSIFICATION:
BUILDING DATA & CODE
HR
(CHAPTERS 3 & 5)
(TABLE 508.3.3)
(CHAPTER 6)
SEPARATED COMBINATIONNON-SEPARATED
HEIGHT & AREA - ACTUAL:
BUILDING HEIGHT HEIGHT IN FEET HEIGHT IN STORIES
ft
BUILDING AREA SUMMARY
FIRST (EXISTING)
BUILDING AREA
sf
ADDITION
TOTAL ALLOWABLE
(NOT INCLUDING
BASEMENT)
sf sf
(CHAPTER 5)
HEIGHT & AREA - ALLOWABLE:
AREA PER TABLE 504.3, 506.2
sf
OCCUPANCY
CLASSIFICATION TABULAR AREA AT
TABULAR HEIGHT
FEET
sf sf
STORIES
ft ft ft
(CHAPTER 5)
REHABILITATION OF EXISTING STRUCTURE:
REPAIRS
PER MICHIGAN REHABILITAION CODE FOR EXISTING BUILDINGS
ALTERATION - LEVEL 1
CHANGE OF OCCUPANCY
FORMER OCCUPANCY CLASSIFICATION:
NEW OCCUPANCY CLASSIFICATION:
PARTIAL CHANGE OF OCCUPANCY: YES NO
ADDITIONS
IF YES: SEPARATED NOT SEPARATED
ALTERATION - LEVEL 2
ALTERATION - LEVEL 3
SEPARATED ADDITION: YES NO
IF YES, FIRE RESISTENCE RATING:
HISTORIC BUILDING
(CHAPTER 6)
(CHAPTER 7)
(CHAPTER 8)
(CHAPTER 9)
(CHAPTER 10)
(CHAPTER 11)
(CHAPTER 12)
RELOCATED BUILDING (CHAPTER 13)
HR
(CHAPTER 9)
FIRE PROTECTION SYSTEMS:
SIZE AND LOCATION OF FIRE AREAS INDICATED ON CODE COMPLIANCE DRAWING(S)
FIRE PROTECTION SYSTEM REQUIRED PROVIDED SECTION
AUTOMATIC SPRINKLER
ALTERNATIVE AUTO FIRE EXT
STANDPIPE
PORTABLE FIRE EXTINGUISHER
FIRE ALARM & DETECTION
EMERGENCY ALARM
SMOKE CONTROL SYSTEM
SMOKE & HEAT VENTS
(903)
(904)
(905)
(906)
(907)
(908)
(909)
(910)
FIRE COMMAND CENTER (911)
FIRE RESISTANCE OF BUILDING ELEMENTS:
REQUIRED PROVIDED
STRUCTURAL FRAME
BEARING WALLS
NON-BEARING WALLS
NON-BEARING WALLS
FLOOR CONSTRUCTION
ROOF CONSTRUCTION
VERTICAL EXIT ENCLOSURE
SHAFT ENCLOSURE
SHAFT ENCLOSURE (LOCATION 2)
(LOCATION 1)
(LOCATION 1)
SECTION
(TABLE 601)
(TABLE 601)
(TABLE 602)
(TABLE 601)
(TABLE 601)
(TABLE 601)
(713.4)
(713.4)
(713.4)
(TABLE 1020.1)CORRIDORS
(EXTERIOR)
(INTERIOR)
(EXTERIOR)
MEANS OF EGRESS:
DESIGN OCCUPANT LOAD SUMMARY
(CHAPTER 10)
FLOOR LEVEL DESIGN OCCUPANT LOAD
TOTAL
MEANS OF EGRESS ELEMENT REQUIRED PROVIDED SECTION
NUMBER OF EXITS
EXIT ACCESS TRAVEL DISTANCE
DEAD-END LIMIT
COMMON PATH OF TRAVEL LIMIT
(TABLE 1006.3.1)
(TABLE 1017.2)
(1020.4)
(1006.2.1)
EGRESS WIDTH
PROVIDED SECTION
(TABLE 1005.1)
(1008.1.1)
DOORS
FIRST FLOOR
REQUIRED
X
32" MIN. CLEAR FOR HANDICAP ACCESSIBILITY
BASED ON CONSTRUCTION TYPE
FIRST
BEARING WALLS (TABLE 601)(INTERIOR)
OCCUPANTS =
APPLICABLE CODE:
CONSTRUCTION SHALL CONFORM TO CURRENT
EDITIONS OF THE 2021 MICHIGAN BUILDING CODE
(MBC), THE 2021 MICHIGAN UNIFORM ENERGY CODE
(MUEC), AS WELL AS ALL OTHER CURRENT LOCAL,
STATE, AND FEDERAL CODES AND REGULATIONS
APPLICABLE TO THIS PROJECT. CONTRACTOR SHALL
CONSTRUCT THE PROJECT IN ACCORDANCE WITH THE
APPLICABLE CODES RELEVANT TO THIS PROJECT.
AREA INCREASE sf
X =
TOTAL BUILDING AREA
(NOT INCLUDING
BASEMENT) sf
DESIGN OCCUPANT LOAD
(ADDITION) (OVERALL)
X
X
VB
BUSINESS
X
15 1
B 9000 40 2
X
X
X
NO
NO
NO
YES
NO
NO
NO
NO
NO
NO
YES
NO
NO
NO
NO NO
N/A
N/A
N/A N/A
N/A N/A
0 0
44'-6"
44'-6"
.213
VB
0 0
GENERAL NOTES:
1. EXTINGUISHERS TO BE INSTALLED AS REQUIRED (MBC 906)
1005.51
1005.351005.36 1005.941005.35
1005.42
1005.50
1005.08
1005.151005.17
1005.49 1005.071005.071005.07
1004.94
1005.02
1005.00
1005.02
1004.98
1004.19
1004.44
1004.46
1004.19
1004.60
1005.10
1005.10
1005.331005.36
1005.23
1004.29
1004.16
1004.59
1004.67
1004.55
1004.65
1004.71
1004.56
1004.18
1004.20
1004.59
1004.72
1004.68
1004.69
1005.22
1005.32
1004.68
1005.92
1005.35
1004.71
1004.68 1004.71
1004.54
1004.21
1003.98
1004.28
1004.62
1004.70
1005.41
1005.88
1004.73 1005.42
1005.46
1005.46
1005.46
1005.54
1005.82
1005.48
1005.49
1005.551005.581005.57
1005.55
1005.55
1005.491005.50
1004.74 1004.72
TREE
1004.44
1004.19
1004.51
1004.65
1004.57
1004.44
1004.96
1004.95
1003.79
SS
SS
1004.66
1004.68
1004.53
1004.18
1004.14
1004.09
1004.68
EAST BOUND I-94 WEIGH STATION
SURVEY NOTES:
1. THIS TOPOGRAPHIC AND PLANIMETRIC SURVEY WAS PERFORMED FOR THE
MICHIGAN DEPARTMENT OF STATE POLICE ON NOVEMBER 21, 2024 BY THE
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET, DESIGN AND
CONSTRUCTION, SITE SECTION.
2. CONTOUR INTERVAL BASED ON NORTH AMERICAN VERTICAL DATUM OF 1988.
HORIZONTAL COORDINATES BASED ON MICHIGAN STATE PLANE COORDINATE
SYSTEM WHICH IS BASED ON NAD83(2007). SCALE FACTOR IN THIS PROJECT AREA
IS 0.99972965.
3. THIS PROJECT LIES WITHIN SECTION 15, T2S, R2E, GRASS LAKE TOWNSHIP,
JACKSON COUNTY, MICHIGAN.
4. CONTOUR INTERVAL SHOWN IS 1-FOOT.
5. ALL UTILITIES SHOWN ARE LOCATED PER VISUAL EVIDENCE AT THE TIME OF
THIS SURVEY. UTILITY LOCATIONS SHOULD BE VERIFIED AT THE TIME OF
CONSTRUCTION. CONTRACTOR SHOULD ALSO CALL MISS DIG TO VERIFY ALL
UNDERGROUND UTILITY LOCATIONS.
SS
SS
C
B
A
D
E
EXISTING CONCRETE SIDEWALK
EXISTING CONCRETE
EXISTING CONCRETE
EXISTING CONCRETE
EXISTING CURB
EXISTING BARRICADE WALL
EXISTING BARRICADE WALL
KEY NOTES:
A. REMOVE EXISTING CONCRETE
B. RELOCATE EXISTING SHED
C. REMOVE EXISTING TREE
D. RELOCATE EXISTING SIGN
E. RELOCATE EXISTING ELECTRICAL SERVICE AS REQUIRED.
REFER TO ELECTRICAL DRAWINGS FOR ADDITIONAL
INFORMATION.
0 10 20 30 FT
1" = 10' SCALE BAR
DEMOLITION NOTES:
1. APPURTENANCES DESIGNATED FOR DEMOLITION SHALL NOT BE
DISTURBED BY THE CONTRACTOR UNTIL FURNISHED WITH NOTICE OF
POSSESSION AND APPROVAL TO PROCEED FROM OWNER AND
ACQUISITION OF ALL APPROPRIATE CONTRACTS. THE CONTRACTOR
SHALL COORDINATE THE SCHEDULE WITH EXISTING TENANTS AND
ADJACENT PROPERTY OWNERS. FOUNDATIONS, SLABS, ALL
UNDERGROUND STRUCTURES, AND UTILITIES DESIGNATED FOR
REMOVAL SHALL BE REMOVED ENTIRELY UNLESS OTHERWISE NOTED.
AREAS TO BE BACK FILLED IN ACCORDANCE WITH GEOTECHNICAL
REPORT.
2. CONTRACTOR IS SOLELY RESPONSIBLE FOR ANY DAMAGE TO EXISTING
UTILITIES THAT ARE INTENDED TO PROVIDE SERVICE WHETHER SHOWN
ON THE PLANS OR NOT.
3. CONTRACTOR TO VERIFY THAT ALL UTILITIES HAVE BEEN ABANDONED
OR PROPERLY SHUTOFF PRIOR TO EXCAVATION.
4. EXISTING UTILITIES AND TOPO LOCATIONS ARE BASED ON THE BEST
AVAILABLE INFORMATION. THE CONTRACTOR IS RESPONSIBLE FOR
VERIFYING ALL EXISTING UTILITY LOCATIONS.
5. PRIOR TO INITIATING DEMOLITION WORK, THE CONTRACTOR SHALL
DEVELOP A DIGITAL PHOTOGRAPH AND/OR VIDEO RECORD OF THE
EXISTING STRUCTURES AND SURROUNDING PROPERTIES. THE RECORD
SHALL INCLUDE CONDITIONS OF EXISTING STREETS AND ADJACENT
PROPERTIES. ONE COPY OF THE PHOTOGRAPH AND/OR VIDEO RECORD
SHALL BE PROVIDED TO THE OWNER.
6. ALL DEBRIS FROM DEMOLITION, NOT BEING REUSED, SHALL BE HAULED
OFF SITE AND DISPOSED OF BY LEGAL MEANS.
7. CONTRACTOR SHALL ERECT AND MAINTAIN TEMPORARY FENCE, 6
FOOT MINIMUM HEIGHT, FOR THE DURATION OF ALL DEMOLITION
PHASES.
8. CONTRACTOR SHALL NOT RESTRICT ACCESS TO ADJOINING PROPERTIES
DURING DEMOLITION OR CONSTRUCTION. ACCESS SHALL BE
MAINTAINED SO AS NOT TO INTERRUPT NORMAL OPERATIONS OF
ADJACENT FACILITIES.
9. CONTRACTOR SHALL NOT ALLOW ANY UTILITY OR SERVICES TO THE
NEIGHBORING PROPERTY(S) TO BE INTERRUPTED WITHOUT THE
EXPRESSED WRITTEN PERMISSION OF THE RESPECTIVE OWNERS. THE
CONTRACTOR IS RESPONSIBLE TO MAINTAIN ALL UTILITY SERVICES TO
THE NEIGHBORING BUILDINGS. IF IT IS NECESSARY FOR CONNECTIONS
TO BE INTERRUPTED, THE CONTRACTOR IS RESPONSIBLE TO PROVIDE
TEMPORARY SERVICES (I.E.. GENERATORS, PORTABLE GAS TANKS, ETC.).
THE CONTRACTOR IS RESPONSIBLE TO COORDINATE ALL UTILITY
ABANDONMENT AND REMOVAL WITH THE RESPECTIVE UTILITY
COMPANIES.
10. WORK CANNOT OCCUR OUTSIDE OF THE DEMOLITION LIMITS
WITHOUT PRIOR CONSENT OF OWNER, ADJACENT OWNER, AND
LOCAL JURISDICTION.
11. EROSION CONTROL PRACTICES MUST BE IN PLACE AND MAINTAINED
DURING DEMOLITION.
A
C-100
LEGEND:
KEY NOTE
LIMITS OF REMOVAL
REMOVE CONCRETE
SS
EXISTING LIGHT POLE
EXISTING UTILITY POLE
EXISTING ELECTRICAL MANHOLE
EXISTING STORMWATER MANHOLE
EXISTING SANITARY SEWER MANHOLE
EXISTING UTILITY BOX
EXISTING SPEAKER
EXISTING SCALE PIT
EXISTING AIR CONDITIONER
EXISTING BREAKER BOX
EXISTING NATURAL GAS TANK
EXISTING WELL
SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
TO
R
A
B
A
21.5'
20.7'
5.0'
5.0'
C
D
E
7.0'
F
GENERAL NOTES:
1. THE UNDERGROUND STRUCTURES AND UTILITIES SHOWN ON THESE
PLANS HAVE BEEN PLOTTED FROM AVAILABLE SURVEYS AND RECORD
MAPS, THEY ARE NOT CERTIFIED TO THE ACCURACY OF THEIR
LOCATION AND/OR COMPLETENESS. IT IS THE CONTRACTOR'S
RESPONSIBILITY TO VERIFY THE LOCATION AND EXTENT OF ALL
UNDERGROUND STRUCTURES AND UTILITIES PRIOR TO ANY DIGGING
OR CONSTRUCTION ACTIVITIES IN THEIR VICINITY.
2. THE CONTRACTOR SHALL PERFORM ALL WORK IN COMPLIANCE WITH
TITLE 29 OF FEDERAL REGULATIONS, PART 1926, SAFETY AND HEALTH
REGULATIONS FOR CONSTRUCTION (OSHA).
3. ALL ROADS AND PRIVATE DRIVES SHALL BE KEPT CLEAN OF MUD, DEBRIS
ETC. AT ALL TIMES.
4. REFER TO ARCHITECTURAL DRAWINGS FOR PRECISE BUILDING
DIMENSIONS.
5. THE CONTRACTOR SHALL CONSULT THE CONSTRUCTION MANAGER
BEFORE DEVIATING FROM THESE PLANS.
6. IN ALL TRENCH EXCAVATIONS, CONTRACTOR MUST LAY THE TRENCH
SIDE SLOPES BACK TO A SAFE SLOPE, USE A TRENCH SHIELD OR PROVIDE
SHEETING AND BRACING.
7. ALL EXISTING SURFACE APPURTENANCES (I.E. WATER VALVES, CATCH
BASIN FRAMES AND GRATES, MANHOLE COVERS) WITHIN THE PROJECT
LIMITS SHALL BE ADJUSTED TO FINISHED GRADE.
8. AREAS DISTURBED OR DAMAGED AS PART OF THIS PROJECT'S
CONSTRUCTION THAT ARE OUTSIDE OF THE PRIMARY WORK AREA
SHALL BE RESTORED, AT THE CONTRACTOR'S EXPENSE, TO THE
SATISFACTION OF THE OWNER'S REPRESENTATIVE.
9. THE CONTRACTOR SHALL CALL "MISS DIG" AT LEAST 3 WORKING DAYS
(EXCLUDING WEEKENDS AND HOLIDAYS) PRIOR TO CONSTRUCTION.
10. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE APPLICABLE
CODES, ORDINANCES, DESIGN STANDARDS AND STANDARD
SPECIFICATIONS OF THE AGENCIES WHICH HAVE THE RESPONSIBILITY OF
REVIEWING PLANS AND SPECIFICATIONS FOR CONSTRUCTION OF ALL
ITEMS INCLUDED IN THESE PLANS.
11. UNLESS SPECIFICALLY STATED, THE CONTRACTOR SHALL APPLY FOR
AND OBTAIN ALL NECESSARY PERMITS AS REQUIRED FOR
CONSTRUCTION OF THIS PROJECT PRIOR TO THE BEGINNING OF WORK
FROM THE PREVIOUSLY MENTIONED AGENCIES.
12. THE CONTRACTOR WILL BE REQUIRED TO ASSUME SOLE RESPONSIBILITY
FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION
OF THE PROJECT, INCLUDING THE SAFETY OF ALL PERSONS AND
PROPERTY. THIS REQUIREMENT SHALL BE MADE TO APPLY
CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS.
13. WHEN ANY EXISTING UTILITY REQUIRES ADJUSTMENT OR RELOCATION,
THE CONTRACTOR SHALL NOTIFY THE PROPER UTILITY COMPANY AND
COORDINATE THE WORK ACCORDINGLY. THERE SHALL BE NO CLAIM
MADE BY THE CONTRACTOR FOR ANY COSTS CAUSED BY DELAYS IN
CONSTRUCTION DUE TO THE ADJUSTMENT OR RELOCATION OF
UTILITIES.
14. THE CONTRACTOR IS TO VERIFY THAT THE PLANS AND SPECIFICATIONS
THAT HE/SHE IS BUILDING FROM ARE THE VERY LATEST PLANS AND
SPECIFICATIONS THAT HAVE BEEN APPROVED BY ALL APPLICABLE
PERMIT-ISSUING AGENCIES AND THE OWNER. ALL ITEMS CONSTRUCTED
BY THE CONTRACTOR PRIOR TO RECEIVING THE FINAL APPROVAL AND
PERMITS HAVING TO BE ADJUSTED OR RE-DONE, SHALL BE DONE AT THE
CONTRACTOR'S EXPENSE.
15. SHOULD THE CONTRACTOR ENCOUNTER CONFLICT BETWEEN THESE
PLANS AND SPECIFICATIONS, EITHER AMONG THEMSELVES OR WITH THE
REQUIREMENTS OF ANY AND ALL REVIEWING AND PERMIT-ISSUING
AGENCIES, HE/SHE SHALL SEEK CLARIFICATION IN WRITING FROM THE
CONSTRUCTION MANAGER BEFORE COMMENCEMENT OF
CONSTRUCTION. FAILURE TO DO SO SHALL BE AT THE SOLE EXPENSE
TO THE CONTRACTOR.
16. THE CONTRACTOR SHALL FURNISH AS-BUILT DRAWINGS INDICATING
ALL CHANGES AND DEVIATIONS FROM APPROVED DRAWINGS.
17. ALL SIGNS AND TRAFFIC CONTROL MEASURES DURING CONSTRUCTION
AND MAINTENANCE ACTIVITIES SHALL BE CONSTRUCTED AND
INSTALLED PER THE LATEST EDITION OF THE MICHIGAN MANUAL OF
UNIFORM TRAFFIC CONTROL DEVICES (M.M.U.T.C.D.).
18. ALL WORK WITHIN THE PUBLIC RIGHT OF WAY SHALL CONFORM TO
THE STANDARDS OF THE MICHIGAN DEPARTMENT OF
TRANSPORTATION.
SITE LEGEND:
CONCRETE
KEY NOTEAA
0 10 20 30 FT
1" = 10' SCALE BAR C-200
KEY NOTES:
A. CONCRETE SIDEWALK. SEE DETAIL A1 ON SHEET C700
B. BUILDING ADDITION, REFER TO ARCHITECTURAL PLANS
C. RELOCATE EXISTING SHED
D. RELOCATE EXISTING SIGN
E. APPROXIMATE LOCATION OF RELOCATED ELECTRICAL
SERVICE. SEE ELECTRICAL DRAWINGS FOR ADDITIONAL
INFORMATION.
F. 6" THICK CONCRETE PAD FOR AIR HANDLING UNIT, SEE
MECHANICAL PLANS FOR ADDITIONAL DETAILS.
4.4' 2.0'
5.1'
8.9'
SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
SS
1005.81
1005.87
1005.87
1005.92
1005.92
1005.69
1005.25
1005.47
1005.89
1005.57
1005.54 1005.55
1005.56
1005.90
1005.48
1005.46
-4 .6
-1 .4
-1 .0
% -1
.4 1%
-1.65%
-1.36%
-0 .2
1005.81
FF=1005.92
-2.26%
1005.37
1005.79
UTILITY NOTES:
1. ALL WORKMANSHIP, MATERIALS, AND
CONSTRUCTION PRACTICES SHALL CONFORM TO
THE REQUIREMENTS OF DELTA TOWNSHIP OR THE
AGENCY HAVING JURISDICTION OVER THE
APPLICABLE UTILITY.
2. CONTRACTOR IS RESPONSIBLE FOR REPAIRS OF
DAMAGE TO ANY EXISTING UTILITY DURING
CONSTRUCTION AT NO COST TO THE OWNER.
3. ALL FILL MATERIAL IS TO BE IN PLACE, AND
COMPACTED BEFORE INSTALLATION OF PROPOSED
UTILITIES.
4. CONTRACTOR SHALL NOTIFY THE UTILITY
COMPANIES 72 HOURS BEFORE CONNECTING TO
ANY EXISTING LINE.
5. IN THE EVENT OF A VERTICAL CONFLICT BETWEEN
WATERLINES, SANITARY LINES, STORM LINES AND
GAS LINES (EXISTING AND PROPOSED), THE
CONTRACTOR SHALL NOTIFY THE ENGINEER AS
SOON AS THE CONFLICT IS DISCOVERED.
6. TOPS OF EXISTING UTILITY STRUCTURES SHALL BE
ADJUSTED TO FINISHED GRADE.
7. EXISTING UTILITIES SHALL BE VERIFIED IN FIELD
PRIOR TO INSTALLATION OF ANY NEW LINES.
8. CONTRACTOR IS RESPONSIBLE FOR COMPLYING TO
THE CONSTRUCTION REQUIREMENTS OF THE
UTILITY OWNERS.
9. THE CONTRACTOR IS SPECIFICALLY CAUTIONED
THAT THE LOCATION AND/OR ELEVATION OF
EXISTING UTILITIES AS SHOWN ON THESE PLANS IS
BASED ON RECORDS OF THE VARIOUS UTILITY
COMPANIES, AND WHERE POSSIBLE, MEASUREMENTS
TAKEN IN THE FIELD. THE INFORMATION IS NOT TO
BE RELIED ON AS BEING EXACT OR COMPLETE. THE
CONTRACTOR MUST CALL THE APPROPRIATE
UTILITY COMPANIES AT LEAST 72 HOURS BEFORE
ANY EXCAVATION TO REQUEST EXACT FIELD
LOCATION OF UTILITIES. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO
RELOCATE ALL EXISTING UTILITIES WHICH
CONFLICT WITH THE PROPOSED IMPROVEMENTS
SHOWN ON THE PLANS.
10. CONTRACTOR SHALL REFER TO ARCHITECTURAL
PLANS AND SPECIFICATIONS FOR ACTUAL
LOCATION AND ELEVATIONS OF ALL UTILITY
ENTRANCES TO INCLUDE SANITARY SEWER
LATERALS, DOMESTIC AND FIRE PROTECTION
WATER SERVICE, ELECTRICAL, TELEPHONE, AND
GAS SERVICE. CONTRACTOR SHALL COORDINATE
INSTALLATION OF UTILITIES, IN SUCH A MANNER AS
TO AVOID CONFLICTS AND ASSURE PROPER
DEPTHS ARE ACHIEVED AS WELL. AS
COORDINATING WITH UTILITY REQUIREMENTS AS
TO LOCATION AND SCHEDULING FOR
TIE-INS/CONNECTIONS PRIOR TO CONNECTING
TO EXISTING UTILITIES.
11. THE CONTRACTOR SHALL CONDUCT ALL
REQUIRED TESTS TO THE SATISFACTION OF THE
RESPECTIVE UTILITY COMPANIES AND THE OWNER'S
INSPECTING AUTHORITIES.
12. CONTRACTOR SHALL COMPLY TO THE FULLEST
EXTENT WITH THE LATEST STANDARDS OF OSHA
DIRECTIVES OR ANY OTHER AGENCY HAVING
JURISDICTION FOR EXCAVATION AND TRENCHING
PROCEDURES. THE CONTRACTOR SHALL USE
SUPPORT SYSTEMS, SLOPING, BENCHING, AND
OTHER MEANS OF PROTECTION. THIS TO INCLUDE
BUT NOT LIMITED FOR ACCESS AND EGRESS FROM
ALL EXCAVATION AND TRENCHING.
CONTRACTOR IS RESPONSIBLE TO COMPLY WITH
PERFORMANCE CRITERIA FOR OSHA.
13. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING
PIPE SIZES AND INVERTS ELEVATIONS BEFORE
ORDERING MANHOLE AND CATCH BASIN
STRUCTURES.
14. ALL UTILITIES BELOW PAVED AREAS SHALL BE
BACKFILLED WITH 100% GRANULAR MATERIAL (OR
APPROVED OTHER) AND COMPACTED TO 95% OF
ITS MAXIMUM UNIT WEIGHT.
15. ALL RIM ELEVATIONS IN OUTLAWN AREAS ARE
APPROXIMATE ONLY AND SHALL BE ADJUSTED BY
THE CONTRACTOR AFTER FINAL GRADES ARE
ESTABLISHED.
UTILITY LEGEND:
PROPOSED UNDERGROUND ELECTRIC
0 10 20 30 FT
1" = 10' SCALE BAR C-300
GRADING NOTES
1. REFER TO EROSION AND SEDIMENT CONTROL
PLAN FOR REQUIRED EROSION AND SEDIMENT
CONTROL MEASURES.
2. CONTRACTOR SHALL BE RESPONSIBLE FOR THE
MAINTENANCE AND REMOVAL OF TEMPORARY
SEDIMENTATION CONTROLS. EROSION CONTROL
MEASURES SHALL NOT BE REMOVED BEFORE
VEGETATION HAS OCCURRED COMPLETELY.
3. ALL SILT FENCE TO BE REPLACED WHENEVER THEY
BECOME CLOGGED OR INOPERABLE AND SHALL BE
REPLACED AT A MINIMUM OF EVERY 3 MONTHS.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
RESTORATION OF TOPSOIL TO ALL DISTURBED
AREAS. IT IS THE CONTRACTOR'S RESPONSIBILITY
TO MAINTAIN EROSION CONTROL MEASURES AT
ALL TIMES.
5. SILT FENCE, JUTE MESH, AND/OR EROSION
CONTROL BLANKETS WILL BE USED ON STEEP
SLOPES AND WHEREVER NECESSARY TO CONTROL
EROSION AND SILTATION OF EXISTING DRAINAGE
SYSTEMS AS ORDERED BY THE ENGINEER OR
SPECIFIED ON PLANS.
6. THE CONTRACTOR SHALL DESIGNATE A MEMBER
OF HIS/HER FIRM TO BE RESPONSIBLE TO MONITOR
EROSION CONTROL, EROSION CONTROL
STRUCTURES, TREE PROTECTION AND
PRESERVATION THROUGHOUT CONSTRUCTION.
7. ALL DISTURBED AREAS SHALL BE PROTECTED FROM
EROSION EITHER BY MULCH OR TEMPORARY
SEEDING WITHIN 2 WEEKS OF DISTURBANCE.
8. ALL SITE GRADING MUST BE PERFORMED TO
INSURE POSITIVE DRAINAGE ACROSS THE ENTIRE
SITE, THROUGHOUT THE PERIOD OF
CONSTRUCTION AND AFTER PROJECT
COMPLETION.
9. ALL SEDIMENTATION AND SOIL EROSION
CONTROL MEASURES SHALL BE CONSTRUCTED
PRIOR TO THE COMMENCEMENT OF SITE
GRADING AND MUST CONFORM TO PART 91 OF
ACT 451 OF THE PUBLIC ACTS OF 1994 AS
AMENDED. ALL APPLICABLE PERMITS SHALL BE
OBTAINED BEFORE IMPLEMENTING THESE
MEASURES. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR MAINTAINING THE
SEDIMENTATION AND SOIL EROSION CONTROL
MEASURES THROUGHOUT CONSTRUCTION.
10. IN GENERAL, EARTHWORK AND PAVEMENT
CONSTRUCTION SHOULD BE PERFORMED IN
ACCORDANCE WITHE THE LATEST MDOT
STANDARD SPECIFICATIONS FOR CONSTRUCTION,
UNLESS OTHERWISE NOTED.
11. REMOVE ANY EXISTING TOPSOIL, ORGANIC SOILS,
UNSUITABLE FILL, VEGETATION, TREES AN OTHER
DELETERIOUS MATERIALS TO EXPOSE THE
SUBGRADE SOIL, TREE ROOTS SHOULD BE
COMPLETELY REMOVED.
12. EXCAVATE TO THE DEPTH OF THE FINAL
SUBGRADE ELEVATION TO ALLOW FOR GRADE
CHANGES AND THE PLACEMENT OF THE
RECOMMENDED PAVEMENT SYSTEM.
13. ON SITE FILL MATERIAL CAN BE USED IF THE
SPECIFIED COMPACTION REQUIREMENTS CAN BE
ACHIEVED. IF ON SITE MATERIAL IS USED, IT
SHOULD BE CLEAN AND FREE OF FROZEN SOIL,
ORGANICS, OR OTHER DELETERIOUS MATERIALS.
14. THE FINAL SUBGRADE SHOULD BE THOROUGHLY
PROOFROLLED USING A LOADED TANDEM AXLE
TRUCK UNDER THE OBSERVATION OF
GEOTECHNICAL/PAVEMENT ENGINEER. LOOSE OR
YIELDING AREAS THAT CANNOT BE
MECHANICALLY STABILIZED SHOULD BE REMOVED
AND REPLACED WITH ENGINEERED FILL OR AS
DICTATED BY FIELD CONDITIONS.
15. THE AGGREGATE BASE SHOULD BE COMPACTED
TO ACHIEVE A MINIMUM OF 95 PERCENT OF THE
MAXIMUM MODIFIED PROCTOR DRY DENSITY. THE
BASE AND SUBGRADE COMPACTION SHOULD
EXTEND A MINIMUM OF 12 INCHES BEYOND THE
PAVED EDGE OR BACK OF CURB.
PROPOSED TOP OF CURB / BOTTOM OF CURB
ELEVATION
PROPOSED SPOT ELEVATION
TC=78.01
BC=77.51
77.73
76 PROPOSED MINOR CONTOUR
72 EXISTING CONTOUR
75 PROPOSED MAJOR CONTOUR
PROPOSED SLOPE
PROPOSED TOP OF GRATE ELEVATIONTG=77.73
RIDGE LINE
PROPOSED TOP OF WALL / BOTTOM OF WALLTW/BW=152.50
PROPOSED HIGH POINT ELEVATIONHP=77.73
FINISHED FLOOR ELEVATIONFF=77.73
2.5%
GRADING LEGEND:
EXISTING ELEVATIONEG=77.73
SS
EXISTING LIGHT POLE
EXISTING UTILITY POLE
EXISTING ELECTRICAL MANHOLE
EXISTING STORMWATER MANHOLE
EXISTING SANITARY SEWER MANHOLE
EXISTING UTILITY BOX
EXISTING SPEAKER
EXISTING SCALE PIT
EXISTING AIR CONDITIONER
EXISTING BREAKER BOX
EXISTING NATURAL GAS TANK
EXISTING WELL
SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
SS
S51
S51
S62
PROPOSED
STAGING
AREA
E6 E8
E6 E8
E6 E8
REFERS TO THE APPROPRIATE M.D.M.B. S.E.S.C.
KEYING SYSTEM DETAIL
SILT FENCE
LIMITS OF EARTH DISTURBANCE (0.06 ACRES)
UDORTHENTS AND UDIPSAMMENTS, NEARLY LEVEL
PROPOSED EROSION BLANKET W/ SEED
SOIL TYPES:
SESC LEGEND:
0 10 20 30 FT
1" = 10' SCALE BAR
SEQUENCE OF CONSTRUCTION NOTES:
NOTE: THIS TEXT IS NOT INTENDED TO DICTATE A METHODS AND MEANS
TO THE CONTRACTOR. IT IS THE SUGGESTED PROCESS FOR
CONSTRUCTION ACTIVITIES IN ORDER TO MINIMIZE THE AMOUNT
OF SOIL EROSION TO THE SITE AND TO COMPLY WITH THE
REQUIREMENTS OF THE SOIL EROSION AND SEDIMENTATION
CONTROL PERMIT. AS PART OF THE PERMIT CONDITIONS, THE
CONTRACTOR WILL BE HELD TO THIS SCHEDULE AND TO THE SOIL
EROSION PLAN. IF THE CONTRACTOR SEES FIT, HE OR SHE MAY
AMEND THIS SCHEDULE AND/OR PLAN, BUT A REVISED WRITTEN
SEQUENCING SCHEDULE AND/OR SOIL EROSION PLAN MUST BE
SUBMITTED TO THE DTMB FOR APPROVAL PRIOR TO DEVIATING TO
THIS SCHEDULE AND/OR PLAN.
STEP 1: INSTALL TEMPORARY SOIL EROSION CONTROL MEASURES
STEP 2: ROUGH GRADING: STRIPPING AND STOCKPILING TOPSOIL. AREAS
THAT WILL NOT BE FURTHER DISTURBED DURING THE COURSE OF
CONSTRUCTION SHALL BE IMMEDIATELY SEEDED WITH MULCH.
EXCESS MATERIAL SHALL EITHER BE STOCKPILED IN THE AREAS
SHOWN ON THE DRAWINGS, LEVELED ON SITE, OR DISPOSED OF
OFF-SITE IN A LEGAL MANNER. STOCKPILES SHALL BE TEMPORARILY
STABILIZED WITH SILT FENCE AND/OR TEMPORARY SEEDING.
STEP 3: UNDERGROUND UTILITIES. EXCAVATED MATERIAL FOR UTILITIES
SHALL EITHER BE STOCKPILED, LEVELED ON SITE, OR DISPOSED OF
OFF-SITE IN A LEGAL MANNER.
STEP 4: BUILDING CONSTRUCTION
STEP 5: FINAL GRADING (1): AREAS OUTSIDE THE INFLUENCE OF FURTHER
CONSTRUCTION ACTIVITIES SHALL BE FINAL GRADED AND
STABILIZED WITH PERMANENT SEED AND MULCH.
STEP 6: PAVING.
STEP 7: FINAL GRADING (2): ALL REMAINING AREAS SHALL BE SEEDED
AND MULCHED WITHIN 5 DAYS OF FINAL GRADING.
STEP 8: TEMPORARY SOIL EROSION CONTROL MEASURES ARE TO BE
REMOVED WHEN PERMANENT MEASURES ARE IN PLACE AND THE
AREA IS STABILIZED.
CONTINUED MAINTENANCE OF ALL PERMANENT SOIL EROSION AND
SEDIMENTATION CONTROL MEASURES SHALL BE THE RESPONSIBILITY OF THE
OWNER. MAINTENANCE RESPONSIBILITIES SHALL BECOME A PART OF ANY
SALES OR EXCHANGE AGREEMENT FOR THE LAND ON WHICH THE PERMANENT
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES ARE LOCATED.
SOIL EROSION/SEDIMENTATION CONTROL OPERATION TIME SCHEDULE
C-310
PROPOSED TRACKIOUT CONTROL MAT
SESC KEYING SYSTEM
SESC NOTES:
1. CONTRACTOR IS TO CONTACT THE DTMB OFFICE AT LEAST THREE (3)
DAYS PRIOR TO THE START OF CONSTRUCTION.
2. CONTRACTOR IS RESPONSIBLE FOR INSTALLING AND MAINTAINING ALL
SOIL EROSION CONTROL MEASURES DURING CONSTRUCTION. SESC
MEASURES SHOULD BE CHECKED DAILY AND AFTER STORM EVENTS FOR
EFFECTIVENESS. OWNER SHALL MAINTAIN ALL PERMANENT SESC
MEASURES AFTER CONSTRUCTION IS COMPLETE. ALL SESC MEASURES
SHALL BE CHECKED MONTHLY FOR ONE YEAR FOR EFFECTIVENESS. ANY
MEASURES THAT HAVE FAILED SHALL BE REPAIRED AND/OR REPLACED.
3. ALL TEMPORARY S.E.C. MEASURES SHALL BE MAINTAINED 30 DAYS AFTER
CONSTRUCTION IS COMPLETE OR UNTIL GRADED AREAS ARE
STABILIZED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVING
TEMPORARY SESC MEASURES.
4. ALL GRADED AREAS EXPOSED FOR MORE THAN 20 DAYS SHALL HAVE
STRAW MULCH APPLIED AT THE RATE OF 3 TONS / ACRE. AREAS NOT AT
FINISHED GRADE AND WHICH WILL BE DISTURBED AGAIN WITHIN ONE
YEAR MUST BE SEEDED AND MULCHED WITH QUICK GROWING
TEMPORARY SEEDING MIXTURE AND MULCH. AREAS WHICH ARE AT
FINISHED GRADE AND WILL NOT BE DISTURBED FOR A YEAR MUST BE
SEEDED AND MULCHED WITH A PERMANENT SEED MIXTURE.
5. ONLY LIMITED DISTURBANCE WILL BE PERMITTED TO PROVIDE ACCESS
TO THE SITE FOR GRADING AND TO CONSTRUCT SEDIMENT BASINS,
SEDIMENT TRAPS, DIVERSION TERRACES, INTERCEPTOR CHANNELS,
AND/OR CHANNELS OF CONVEYANCE AS APPROPRIATE.
6. EROSION AND SEDIMENTATION CONTROLS MUST BE CONSTRUCTED,
STABILIZED, AND FUNCTIONAL BEFORE SITE DISTURBANCE WITH THE
TRIBUTARY AREAS OF THOSE CONTROLS.
7. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENTATION MUST
BE MAINTAINED PROPERLY. MAINTENANCE MUST INCLUDE INSPECTIONS
OF ALL EROSION AND SEDIMENTATION CONTROL ON A DAILY BASIS
AND AFTER EACH STORM EVENT. ALL PREVENTATIVE AND REMEDIAL
MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT,
REGRADING, RESEEDING, REMULCHING, AND RENETTING, MUST BE
PERFORMED IMMEDIATELY.
8. APPROVAL OF THE SOIL EROSION PERMIT DOES NOT AUTHORIZE ANY
EARTH DISTURBANCE ACTIVITY OFF-SITE WITHOUT WRITTEN
PERMISSION FOR THAT EARTH DISTURBANCE ACTIVITY FROM THE
LANDOWNER.
9. NO DEWATERING IS PLANNED FOR THIS PROJECT. IF DEWATERING IS
REQUIRED, THE CONTRACTOR SHALL SUBMIT A DEWATERING PLAN FOR
APPROVAL TO THE DTMB AND/OR EGLE AS REQUIRED. NO DEWATERING
SHALL COMMENCE UNTIL APPROVAL HAS BEEN OBTAINED.
SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
S62 TRACKOUT CONTROL MAT
GENERAL INFORMATION
THE TRACKOUT CONTROL SYSTEM IS DESIGNED TO BE USED
AS A TEMPORARY CONSTRUCTION ENTRANCE WHICH
PROVIDES SITE ACCESS WHILE MINIMIZING SEDIMENT LEAVING
THE SITE. THE TOP SURFACE OF THE MAT IS A
GEOMETRIC PATTERN FORMED IN THE SHAPE OF PYRAMIDS.
THE MATS ARE UNIDIRECTIONAL AND ARE MEANT TO HAVE THE
STAGGERED PYRAMIDS IN THE DIRECTION OF TRAVEL.
INDIVIDUAL MATS ARE CONNECTED TOGETHER WITH
HARDWARE TO FORM VARIOUS CONFIGURATIONS TO FIT YOUR
JOBSITE.
INSTALLATION
TRACKOUT CONTROL SYSTEM SHOULD BE INSTALLED NEAR
THE SITE EXIT POINT, AS CLOSE TO THE LOCATION WHERE
VEHICLES ENTER THE ROADWAY AS SAFELY AS POSSIBLE.
MATS SHOULD NOT BE INSTALLED AT A LOW POINT ON THE
SITE WHERE WATER WILL POOL.
SUITABLE INSTALLATION SUBSTRATE
· UN-EXCAVATED SOIL
· EXCAVATED SOIL (MIN CBR: 4)
· ASPHALT
· CONCRETE
CLEANING/ MAINTENANCE
· SKID-STEER BROOM ATTACHMENT
· STREET SWEEPER (REQUIRES ADJUSTED BRISTLE HEAD
· PRESSURE WASHER (MUST HAVE ABILITY TO CONTAIN
WATER) WATER TRUCK (MUST HAVE ABILITY TO CONTAIN
WATER)
NTS
SPACING 6-10' MAX.
1' MIN.
6" ANCHOR TRENCH
FENCE POSTS DRIVEN INTO
GROUND 1' MIN.
SILT FENCE B
SILT FENCE A
FABRIC TO BE
WRAPPED AROUND
FENCE POST
1' MIN.
UNDISTURBED VEGETATION
GEOTEXTILE FILTER FABRIC
FASTENED ON UPHILL SIDE,
TOWARDS EARTH
DISRUPTION
RIDGE OF COMPACTED
EARTH ON UPHILL SIDE OF
FILTER FABRIC
SHEET FLOW
6"x6" ANCHOR TRENCH
ROLL JOINTS
ROLL JOINT
INSTALLATION
1. INSTALL PARALLEL TO A CONTOUR.
2. THE SILT FENCE SHOULD BE MADE OF WOVEN GEOTEXTILE FABRIC.
3. SILT FENCE SHOULD ACCOMODATE NO MORE THAN 1/2 TO 1 ACRE OF DRAINAGE PER 100' OF FENCE AND ON SLOPES LESS
THAN 1:2 (V:H).
4. DIG A 6" TRENCH ALONG THE AREA WHERE THE FENCE IS TO BE INSTALLED.
5. PLACE 6" OF THE SILT FENCE BOTTOM FLAP INTO THE TRENCH.
6. BACKFILL THE TRENCH WITH SOIL AND COMPACT THE SOIL ON BOTH SIDES. CREATE A SMALL RIDGE ON THE UP-SLOPE SIDE
OF THE FENCE.
7. INSTALL WOODEN STAKES 6 - 10' APART AND DRIVE INTO THE GROUND A MINIMUM OF 12".
8. STAPLE THE GEOTEXTILE FABRIC TO THE WOODEN STAKES.
9. JOIN SECTIONS OF SILT FENCE BY WRAPPING ENDS TOGETHER (SEE DRAWING).
MAINTENANCE
· INSPECT FREQUENTLY AND IMMEDIATELY AFTER EACH STORM EVENT. CHECK SEVERAL TIMES DURING PROLONGED STORM
EVENTS. IF NECESSARY, REPAIR IMMEDIATELY.
· IF THE SEDIMENT HAS REACHED 1/3 THE HEIGHT OF THE FENCE, THE SOIL SHOULD BE REMOVED AND DISPOSED OF IN A
STABLE UPLAND SITE.
· THE FENCE SHOULD BE RE-INSTALLED IF WATER IS SEEPING UNDERNEATH IT OR IF THE FENCE HAS BECOME INEFFECTIVE.
· SILT FENCE SHOULD BE REMOVED ONCE VEGETATION IS ESTABLISHED AND UP-SLOPE AREA HAS STABILIZED.
· SILT FENCE MAY CAUSE TEMPORARY PONDING AND COULD FAIL IF TOO MUCH WATER FLOWS THROUGH THE AREA.
· DO NOT USE IN AREAS WITH CONCENTRATED FLOWS.
· CHANCE OF FAILURE INCREASES IF FENCE IS INSTALLED INCORRECTLY OR IF SEDIMENT ACCUMULATION IS NOT REMOVED.
DESCRIPTION
SILT FENCE IS THE MOST COMMON TEMPORARY SEDIMENT BARRIER AND CONSISTS OF A GEOTEXTILE FABRIC THAT IS ATTACHED TO SUPPORTING POSTS AND TRENCHED OR SLICED INTO THE GROUND. SEDIMENT-LADEN RUNOFF PONDS UPHILL FROM THE SILT FENCE AND RUNOFF IS TEMPORARILY STORED TO ALLOW SEDIMENT TO SETTLE OUT OF THE WATER. THIS PRACTICE APPLIES WHERE SHEET EROSION OCCURS ON SMALL DISTURBED AREAS. SILT FENCE IS INTENDED TO INTERCEPT AND DETAIN SMALL AMOUNTS OF SEDIMENT FROM DISTURBED AREAS IN ORDER TO PREVENT SEDIMENT FROM LEAVING THE SITE. SILT FENCES CAN ALSO PREVENT SHEET EROSION BY DECREASING THE VELOCITY OF THE RUNOFF. SILT FENCE IS NOT INTENDED TO BE USED IN CONCENTRATED FLOW PATHS.
NTS
S51 SILT FENCE
NTS
E8 PERMANENT STABILIZATION/SEEDING
PERMANENT SEEDING
1. SUBSOILER, PLOW, OR OTHER IMPLEMENT SHALL BE USED TO REDUCE SOIL COMPACTION AND ALLOW MAXIMUM INFILTRATION. (MAXIMUM INFILTRATION WILL HELP CONTROL BOTH RUNOFF RATE AND WATER QUALITY.) SUBSOILING SHOULD BE DONE WHEN THE SOIL MOISTURE IS LOW ENOUGH TO ALLOW THE SOIL TO CRACK OR FRACTURE. SUBSOILING SHALL NOT BE DONE ON SLIP-PRONE AREAS WHERE SOIL PREPARATION
SHOULD BE LIMITED TO WHAT IS NECESSARY FOR ESTABLISHING VEGETATION.
2. THE SITE SHALL BE GRADED AS NEEDED TO PERMIT THE USE OF CONVENTIONAL EQUIPMENT FOR SEEDBED PREPARATION AND SEEDING.
3. 6" OF TOPSOIL SHALL BE APPLIED WHERE NEEDED TO ESTABLISH GERMINATION OF SEED. GENERAL ON-SITE TOPSOIL SHALL BE ¼ ORIGINAL ON-SITE
SOIL AND ¾ SANDY LOAM OR LOAM SOIL AS DEFINED BY THE USDA SOIL CONSERVATION SERVICE SOIL CLASSIFICATION SYSTEM. TOPSOIL SHALL BE FREE FROM ADMIXTURE OF SUBSOIL, HEAVY CLAY, COARSE SAND, PLANTS, ROOTS, STICKS, AND OTHER FOREIGN MATERIALS AS PER ASTM D 5268-92. 95% OF TOPSOIL SHALL PASS A 2.0 MIL SIEVE. ORGANIC CONTENT SHALL BE 4% TO 12% OF TOTAL DRY WEIGHT.
4. LIMESTONE SHALL BE APPLIED TO ACID SOIL AS RECOMMENDED BY A SOIL TEST. IN LIEU OF A SOIL TEST. LIME SHALL BE GROUND LIMESTONE CONTAINING NOT LESS THAN 85% OF TOTAL CARBONATES AND SHALL BE GROUND TO SUCH FINENESS THAT 50% WILL PASS THROUGH A 200-MESH SIEVE AND 90% WILL PASS THROUGH A 900-MESH SIEVE. LIME SHALL BE APPLIED AT THE RATE OF 100 POUNDS PER 1,000 FT. OR 2 TONS PER ACRE.
5. FERTILIZER SHALL BE APPLIED AS RECOMMENDED BY A SOIL IN PLACE OF A SOIL TEST, FERTILIZER SHALL BE APPLIED AT A RATE OF 25 POUNDS PER
1,000 SQ. FT. OR 1,000 POUNDS PER ACRE OF A 10-10-10 OR 12-12-12 ANALYSES.
6. THE LIME AND FERTILIZER SHALL BE WORKED INTO THE SOIL WITH A DISK HARROW, SPRING-TOOTH HARROW, OR OTHER SUITABLE FIELD IMPLEMENT TO A DEPTH OF 3 INCHES. ON SLOPING LAND, THE SOIL SHALL BE WORKED ON THE CONTOUR.
7. GENERAL USE / LAWN SEED MIX SHALL BE USED FROM PERMANENT SEEDING CHART AND SHALL BE APPLIED IN A RATE PER THE CHART.
8. SEEDING SHOULD BE DONE APRIL 1 TO MAY 15 OR OCTOBER 1 TO NOVEMBER 15. IF SEEDING OCCURS OUTSIDE OF THE ABOVE-SPECIFIED DATES, ADDITIONAL MULCH AND IRRIGATION MAY BE REQUIRED TO ENSURE A MINIMUM OF 80% GERMINATION. TILLAGE FOR SEEDBED PREPARATION SHOULD BE DONE WHEN THE SOIL IS DRY ENOUGH TO CRUMBLE AND NOT FORM RIBBONS WHEN COMPRESSED BY FOR WINTER SEEDING, SEE THE
FOLLOWING SECTION ON DORMANT SEEDING.
9. THE FOLLOWING METHODS MAY BE USED FOR "DORMANT SEEDING":
· FROM NOVEMBER 15 THROUGH APRIL 1, WHEN SOIL CONDITIONS PERMIT, PREPARE THE SEEDBED, LIME AND FERTILIZE, APPLY THE
SELECTED SEED MIXTURE, MULCH AND ANCHOR. INCREASE THE SEEDING RATES BY 50% FOR THIS TYPE OF SEEDING.
· APPLY SEED UNIFORMLY WITH A CYCLONE SEEDER, DRILL, CULTIPACKER SEEDER, OR HYDRO-SEEDER (SLURRY MAY INCLUDE SEED AND
FERTILIZER) ON A FIRM, MOIST SEEDBED.
· WHERE FEASIBLE, EXCEPT WHEN A CULTIPACKER TYPE SEEDER IS USED, THE SEEDBED SHOULD BE FIRMED FOLLOWING SEEDING
OPERATIONS WITH A CULTIPACKER. ROLLER, OR LIGHT DRAG. ON SLOPING LAND, SEEDING OPERATIONS SHOULD BE ON THE CONTOUR
WHERE FEASIBLE.
10. PERMANENT SEEDING SHALL INCLUDE IRRIGATION TO ESTABLISH VEGETATION DURING DRY WEATHER OR ON ADVERSE SITE CONDITIONS, WHICH REQUIRE ADEQUATE MOISTURE FOR SEED GERMINATION AND PLANT GROWTH. IRRIGATION SHALL BE MONITORED TO PREVENT EROSION AND
DAMAGE TO SEEDED AREAS FROM EXCESSIVE RUNOFF.
DESCRIPTION
FINAL STABILIZATION OF DISTURBED AREAS MUST BE INITIATED WHERE CONSTRUCTION ACTIVITY HAS PERMANENTLY STOPPED AND COMPLETED NO LATER THAN 14 DAYS WHENEVER ALL LAND DISTURBING CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED. AT THE COMPLETION OF GROUND-DISTURBING ACTIVITIES THE ENTIRE SITE MUST HAVE PERMANENT VEGETATIVE COVER, MEETING VEGETATIVE DENSITY REQUIREMENTS IN ALL
AREAS NOT COVERED BY HARDSCAPE.
IN AREAS WHERE FINAL STABILIZATION WILL OCCUR, VEHICLE AND EQUIPMENT ACCESS WILL BE RESTRICTED IN ORDER TO MINIMIZE COMPACTION. IN ADDITION, THE SOIL MAY NEED TO BE CONDITIONED FOR SEEDING OR PLANTING. SEEDED AREAS SHALL BE PROTECTED WITH STRAW MULCH, HYDRAULIC
MULCH OR A ROLLED EROSION CONTROL PRODUCT.
FINAL SITE STABILIZATION IS ACHIEVED WHEN PERENNIAL VEGETATIVE COVER HAS BEN ESTABLISHED WITH A DENSITY OF AT LEAST 70% OF COVER FOR THE UNPAVED AREAS AND AREAS NOT COVERED BY PERMANENT STRUCTURES OR THAT EMPLOY EQUIVALENT PERMANENT STABILIZATION MEASURES.
THIS AREA IS EXCLUSIVE OF AREAS THAT ARE COVERED WITH ROCK (CRUSHED GRANITE, GRAVEL, ETC.) OR LANDSCAPE MULCH, PAVED OR HAVE A
BUILDING OR OTHER PERMANENT STRUCTURE ON THEM.
SWPPP NOTES:
1. THE CONTRACTOR SHALL MAINTAIN A COPY OF THE SWPPP ON THE SITE FOR THE DURATION OF
CONSTRUCTION.
2. THE CONTRACTOR SHALL ADHERE TO THE SWPPP DURING CONSTRUCTION OPERATIONS.
3. THE SWPPP INCLUDES SPECIFICATION SECTION 01150, THE SWPPP NARRATIVE AND ASSOCIATED APPENDICES, AND THE SWPPP DRAWINGS AND ASSOCIATED DETAIL SHEETS.
4. IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAINTAIN AND REPAIR ALL BMPS DURING CONSTRUCTION.
5. ALL EARTH-DISTURBING CONSTRUCTION ACTIVITIES SHALL BE PERFORMED WITHIN THE LIMITS OF
DISTURBANCE AS INDICATED ON THE SWPPP DRAWINGS.
6. THE CONTRACTOR IS RESPONSIBLE FOR REVIEWING THE LIMITS OF DISTURBANCE SHOWN ON THE
DRAWINGS AND FIELD-STAKING THE LIMITS OF DISTURBANCE LINE PRIOR TO THE START OF
CONSTRUCTION.
7. PERIMETER EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE INSTALLED PRIOR TO THE START OF
ANY LAND CLEARING OR GRADING ACTIVITIES.
8. THE CONTRACTOR SHALL APPLY TEMPORARY EROSION AND SEDIMENTATION CONTROL MEASURES WHEN REQUIRED BY THESE PLAN DRAWINGS AND IMPLEMENT ADDITIONAL MEASURES AS DICTATED BY SITE
CONDITIONS.
9. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY SEDIMENTATION RESULTING FROM WORK ON THIS SITE IS CONTAINED ON THE SITE AND NOT ALLOWED TO COLLECT ON ANY OFF-SITE AREAS OR IN
WATERWAYS.
10. SLOPES ARE TO BE LEFT IN A ROUGHENED CONDITION DURING THE GRADING PHASE TO REDUCE RUNOFF
VELOCITIES AND EROSION.
11. CONTRACTOR LAYDOWN, STAGING AND STOCKPILE AREAS ARE TO BE LOCATED WITHIN THE PERMITTED
LIMITS OF DISTURBANCE.
12. SILT FENCE IS TO BE INSTALLED AROUND THE PERIMETER OF ON-SITE SOIL STOCKPILE AREAS AS DICTATED BY SITE CONDITIONS. ADDITIONALLY, INACTIVE PORTIONS OF THE STOCKPILE AREAS ARE TO BE STABILIZED AS
REQUIRED HEREIN.
13. THE CONTRACTOR IS RESPONSIBLE FOR REGULARLY CHECKING SEEDED AREAS TO SEE THAT A GOOD STAND OF VEGETATION IS ESTABLISHED. AREAS SHOULD BE FERTILIZED, WATERED, AND RESEEDED AS NEEDED. THE CONTRACTOR IS RESPONSIBLE TO ENSURE VEGETATION IS ESTABLISHED FOR A WARRANTY PERIOD OF TWO
FULL GROWING SEASONS.
14. TRACKING OF SOIL AND SEDIMENT ONTO OFF-SITE ROADWAYS SHALL BE MINIMIZED THROUGH THE USE OF
APPROPRIATE MEASURES.
THE CONTRACTOR SHALL IMMEDIATELY REMOVE ANY SOIL OR SEDIMENT TRACKED ONTO THE ROADWAYS.
15. THE CONTRACTOR SHALL BRING TO THE SITE AND USE ONLY EQUIPMENT THAT IS WELL-MAINTAINED AND
WITHOUT LEAKS.
16. THE CONTRACTOR SHALL CHECK ALL SESC MEASURES WEEKLY AND AFTER A HALF INCH OR MORE STORM
EVENT. REPAIR OR REPLACE
ANY MEASURE IF DAMAGED.
17. CLEAN AND REINSTALL INLET PROTECTION WEEKLY.
LARGE AREAS OF SOIL THAT ARE DENUDED OF VEGETATION AND HAVE NO PROTECTION FROM PARTICLES BEING PICKED UP AND CARRIED BY WIND SHOULD BE PROTECTED WITH A TEMPORARY COVER OR KEPT UNDER CONTROL WITH WATER OR OTHER SOIL ADHERING PRODUCTS TO LIMIT WIND TRANSPORTED PARTICLES EXITING THE SITE PERIMETER.
WATER TRUCKS OR OTHER DUST CONTROL AGENTS ARE TO BE USED AS NEEDED DURING CONSTRUCTION TO MINIMIZE DUST GENERATED ON THE SITE. TACKIFIERS MAY BE USED TO HOLD SOIL IN PLACE AND PREVENT DUST. MANUFACTURER RECOMMENDATIONS FOR APPLICATION RATES MUST BE USED FOR DUST CONTROL APPLICATIONS. DUST CONTROL MUST BE PROVIDED BY THE CONTRACTOR TO A DEGREE THAT IS IN COMPLIANCE WITH APPLICABLE LOCAL AND STATE DUST CONTROL
REGULATIONS.
NTS
E5 DUST CONTROL
When
Why
Where
How
When areas are subject to erosive surface sheet flows or severe wind.
Temporarily protects seeded areas and slopes against erosion from rain or wind.
Holds soil moisture to allow for seed germination and reduces wind dessication of germinated seeds. Inhibits seed consumption by birds.
Use on exposed slopes, newly seeded areas and other areas subject to erosion.
MULCHING SPECIFICATIONS
Prepare surface to proper grade and compaction requirements.
If treatment area is to be revegetated immediately, spread or drill seed, or install vegetative sprigs into planting surface.
Select mulch material appropriate for site characteristics, including grade, level of traffic, installation method, and accessibility.
Other surface runoff control measures should be installed prior to mulching.
Mulches should not be applied if free surface water is present but may be applied to wet soil.
Straw - Most common and widely used material. Provides organic matter as it breaks down. Effectiveness of sediment reduction high for at least 3 months.
Subject to windblow and washout. For straw, apply a minimum of 2 tons/acre or approx. 50 lbs./1000 sq.ft. to cover the surface. Increase application rates 50% for dormant seeding.
Rock - Crushed stone and gravel maintain effectiveness indefinitely if maintained to repair compaction. Cover 2-3" in depth (approx. 2.27 tons/1000 sq. ft.).
Wood chips/bark - Chips decompose slowly but may require nitrogen fertilizer application to avoid nutrient deficiency. Tend to wash down slopes over 6% and may clog inlet grates.
Cover 2-3" in depth.
2.
3.
4.
1.
5.
When
Why
Where
How
When areas are subject to erosive surface sheet flows or severe wind.
Temporarily protects seeded areas and slopes against erosion from rain or wind. Holds soil moisture to allow for seed germination and reduces wind dessication of germinated seeds.
Inhibits seed consumption by birds.
Use on exposed slopes, newly seeded areas and other areas subject to erosion.
Prepare surface to proper grade and compaction requirements.
If treatment area is to be revegetated immediately, spread or drill seed, or install vegetative sprigs into planting surface.
Select mulch material appropriate for site characteristics, including grade, level of traffic, installation method, and accessibility.
Other surface runoff control measures should be installed prior to mulching.
Mulches should not be applied if free surface water is present but may be applied to wet soil.
Straw - Most common and widely used material. Provides organic matter as it breaks down.
Effectiveness of sediment reduction high for at least 3 months. Subject to windblow and washout. For straw, apply a minimum of 2 tons/acre or approx. 50 lbs./1000 sq.ft. to cover the surface. Increase application rates 50% for dormant seeding.
Rock - Crushed stone and gravel maintain effectiveness indefinitely if maintained to repair compaction. Cover 2-3" in depth (approx. 2.27 tons/1000 sq. ft.).
Wood chips/bark - Chips decompose slowly but may require nitrogen fertilizer application to avoid nutrient deficiency. Tend to wash down slopes over 6% and may clog inlet grates. Cover 2-3" in depth.
2.
3.
4.
1.
5.
NTS
E6 MULCHING SPECIFICATIONS
C-311SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
C-700
EXPANSION JOINT
WITH JOINT FILLER
CONTRACTION JOINT
FINISHED GRADE
COMPACTED SUBGRADE
1 12 2 2
STIFF BRISTLE-BROOM
FINISH
PERPENDICULAR TO
PEDESTRIAN TRAFFIC
6" SUBBASE COURSE
4" 3,500 PSI CONCRETEWIDTH VARIES (REFER TO PLAN)
25' MAX.
5', TYP.
6"
2% MAX.
A1
CONCRETE SIDEWALK DETAIL
N.T.S.
SH
EE
TI
DE
NT
IF
IC
AT
IO
N
NO
IS
SU
ED
F
OR
DA
TE
FI
LE
N O
C O N
TR
AC
T N O
PE
RM
IT
SE
T
BI
D
SE
T
FI
N
AL
RE
C O
RD
DE
SI
GN
ED
DR
AW
N
CH
EC
KE
D
AP
PR
OV
ED
ST
AT
E
OF
M
IC
HI
GA
N
D
ES
IG
N
A N
D C
O N
ST
RU
CT
IO
N D
IV
IS
IO
N
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
F
A
CI
LI
TI
ES
A
D M
IN
IS
TR
A
TI
O
N
BU
IL
D
IN
G R
EN
O
VA
TI
O N
S
FO
R
A D W
A D W
R
FB
R
FB
1/2
.C
AK
Y2
G
R
AS
S
LA
KE
S
C
AL
E E/
B I-9
JA
C
KS
O N
M
IC
H
IG
AN
G R
A S
S L
A K
E W
E
IG
H S
TA
TI
O N
O
FF
IC
E
A D
D
IT
IO
N
W es t S ag in aw
H w y.
S ui te
La ns in g, M I 4 of fic e:
7.
2.
fa x:
7.
2.
w w w .c ol lie rs en gi ne er in g.
co m
AD
AM
P
. L
AC
H, R
A, D
IR
EC
GENERAL NOTESGENERAL STRUCTURAL SYMBOLS ABBREVIATIONSDESIGN CRITERIA
DRAWING SYMBOLS LEGEND
SCALE :
1 1/8" = 1'-0"
VIEW NAME
VIEW TITLES
A101
VIEWING DIRECTION
SECTIONS MARK
SECTION #
DRAWING #
LEVEL
EVEL
ELEVATION NOTATION
X KEYNOTE
N
NORTH ARROW
(SHOWN IN KEYPLAN)
FOOTING STEPHI
LOW
SLAB STEP
SLAB STEP MOMENT CONNECTION
SLAB RAMP
WALL STEPHI
LOW
BREAK MARK
XXX EXISTING COLUMN ID
XXX NEW COLUMN ID
1Ref
S000
1Ref
Re f S000 1
Re f
1 Ref
DETAIL #
DRAWING #
ELEVATION MARKER
DETAIL CALLOUT
A101
SIM
DETAIL #
DRAWING #
A. GOVERNING CODES
a. BUILDING CODE 2015 MICHIGAN BUILDING CODE
b. GENERAL DESIGN LOADS ASCE 7-10
c. CONCRETE ACI 318-14
d. STEEL FRAMING AISC 360-10 & AISC 341-10
e. COLD-FORMED STEEL FRAMING AISI S100-12
f. WOOD AWC NDS-2015 & SDPWS-08
g. MASONRY TMS 402-2013
B. RISK CATEGORY II
C. ROOF
a. DEAD LOAD
• ROOFING AND INSULATION 05 PSF
• SHEATHING 03 PSF
• MEP 05 PSF
• MISC 05 PSF
• TRUSS SELF WEIGHT PER MFR
• TOTAL ROOF DEAD LOAD 18 PSF + TRUSSES
b. LIVE LOAD 20 PSF
D. GROUND FLOOR (SLAB-ON-GRADE)
a. LIVE LOAD 100 PSF
E. SNOW LOADS
a. GROUND SNOW LOAD Pg 25 PSF
b. FLAT ROOF SNOW LOAD Pf 17.5 PSF
F. WIND LOADS
a. WIND VELOCITY 115 MPH
b. EXPOSURE CATEGORY C
c. ENCLOSURE CLASSIFICATION ENCLOSED
G. SEISMIC DESIGN DATA
a. SEISMIC DESIGN CATEGORY B
b. SEISMIC IMPORTANCE FACTOR 1.0
c. SEISMIC SITE CLASS (SOILS) D
d. SEISMIC RESISTING SYSTEM
• BEARING WALL SYSTEMS
• LIGHT-FRAME (WOOD) WALLS SHEATHED WITH WOOD STRUCTURAL PANELS RATED FOR SHEAR
RESISTANCE
e. RESPONSE MODIFICATION FACTOR 6.5
f. DEFLECTION AMPLIFICATION FACTOR 4.0
g. EARTHQUAKE SPECTRAL RESPONSE
• ACCELERATION AT SHORT PERIODS Ss = 0.120
h. EARTHQUAKE SPECTRAL RESPONSE
• ACCELERATION, PERIOD = 1 SECOND S1 = 0.054
i. DESIGN 5% DAMPED, SPECTRAL RESPONSE
• ACCELERATION AT SHORT PERIODS SDS = 0.097
j. DESIGN 5% DAMPED, SPECTRAL RESPONSE
ACCELERATION, PERIOD = 1 SECOND SD1 = 0.077
k. SEISMIC BASE SHEAR V = CsW
l. ANALYSIS PROCEDURE EQUIVALENT LATERAL FORCE PROCEDURE
STRUCTURAL DESIGN CRITERIA
DEFLECTION CRITERIA
FRAMING ELEMENT
ALLOWABLE DEFLECTION
LOADING DEFLECTION LIMIT
ROOF MEMBER
DEAD+LIVE
LIVE
L/240 L/360
GENERAL
1. FOUNDATION DESIGN IS BASED ON GEOTECHNICAL REPORT, DATED MARCH 7, 2025 PREPARED BY SME REPORT #
098907.00. SOIL BEARING PRESSURE NOT TO EXCEED 2000 PSF FOR FOOTINGS WITHIN BUILDING FOOTPRINT.
REFER TO GEOTECHNICAL REPORT FOR ALL PROJECT REQUIREMENTS PERTAINING TO EARTHWORK, INCLUDING
BUT NOT LIMITED TO, EXCAVATION, BACKFILLING, COMPACTION, AND MATERIALS.
2. FOUNDATION SYSTEM - CONCRETE WALLS, SLABS-ON-GRADE AND SPREAD FOOTINGS.
3. EXTERIOR CONSTRUCTION SHALL BE FOUNDED BELOW FINISHED GRADE AT A MINIMUM DEPTH OF 3'-6", UNLESS
NOTED OTHERWISE.
4. FOUNDATION UNITS SHALL BE CENTERED UNDER SUPPORTED STRUCTURAL MEMBERS, UNLESS NOTED
OTHERWISE ON THE DRAWINGS.
5. REFER TO THE GEOTECHNICAL REPORT FOR ACCEPTABLE FOUNDATION BACKFILL AND SLAB-ON-GRADE
SUBGRADE MATERIAL. DO NOT PLACE FILL UNTIL SUBMITTAL FOR FILL MATERIAL IS APPROVED BY
ARCHITECT/ENGINEER.
6. REFER TO THE GEOTECHNICAL REPORT FOR BACKFILL AND FILL REQUIREMENTS.
7. ALL FOUNDATION ELEMENTS ARE TO BE PLACED ON UNDISTURBED APPROVED NATIVE SOIL OR ON 1'-0" MINIMUM
APPROVED COMPACTED STRUCTURAL FILL. STRUCTURAL FILL SHALL EXTEND 1'-0" MINIMUM BEYOND THE FOUNDATION ELEMENT AND THEN DOWNWARD TO NATURAL SOILS AT A SLOPE OF 2 HORIZ. TO 1 VERT.
8. EACH PRIME CONTRACTOR SHALL PROVIDE ALL TRENCHING WORK REQUIRED FOR ITS CONTRACT, INCLUDING TRENCH EXCAVATION, AND BACKFILL (WITH ACCEPTABLE FILL, SEE GEOTECHNICAL REPORT) TO WITHIN 1'-0" OF FINISH GRADE/FLOOR. ALL TRENCHING WORK WITHIN THE BUILDING FOOTPRINT SHALL BE COORDINATED WITH THE GENERAL CONTRACTOR. GENERAL CONTRACTOR MUST ACCEPT, IN WRITING, THE QUALITY OF THE TRENCH BACKFILL OF OTHER PRIME CONTRACTORS BEFORE BEGINNING WORK OVER THE TOP OF THE TRENCH.
9. EXCAVATION AND BACKFILL OPERATIONS SHALL BE MAINTAINED IN A DRY CONDITION. SURFACE AND INFILTRATING WATER SHALL BE REMOVED BY SITE GRADING AND PUMPING FROM SUMPS AS REQUIRED.
10. NO FOUNDATION CONCRETE SHALL BE PLACED IN WATER OR ON FROZEN SUBGRADE MATERIAL.
11. PROTECT IN-PLACE FOUNDATIONS AND SLABS FROM FROST PENETRATION UNTIL THE PROJECT IS COMPLETED.
12. THE CONTRACTOR IS RESPONSIBLE FOR EXCAVATION SAFETY. EXCAVATIONS MUST BE PERFORMED IN
ACCORDANCE WITH THE CURRENT OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.
13. PROVIDE TEMPORARY OR PERMANENT SUPPORTS WHETHER SHORING, SHEETING OR BRACING SO THAT NO
HORIZONTAL MOVEMENT OR VERTICAL SETTLEMENT OCCURS TO EXISTING STRUCTURES, STREETS OR UTILITIES
ADJACENT TO THE PROJECT SITE.
FOUNDATION NOTES
1. ALL WORK SHALL BE PERFORMED IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF THE GOVERNING LOCAL MUNICIPAL CODES AND SPECIFICATIONS (INCLUDING SUPPLEMENTS) FOR THIS TYPE OF CONSTRUCTION. THE STRUCTURE HAS BEEN DESIGNED IN ACCORDANCE WITH THE GOVERNING CODES AND
REFERENCED STANDARDS LISTED BELOW.
2. THE STRUCTURAL DRAWINGS ARE INTENDED TO BE USED IN CONJUNCTION WITH THE ARCHITECTURAL DRAWINGS AND ALL OTHER APPLICABLE DISCIPLINE DRAWINGS. ANY CONFLICT BETWEEN NOTES, DETAILS, AND SPECIFICATIONS, THE MOST RIGID REQUIREMENTS SHALL GOVERN.
3. THE CONTRACTOR SHALL NOT MAKE DEVIATIONS FROM THE DESIGN DOCUMENTS WITHOUT WRITTEN APPROVAL FROM THE ARCHITECT AND/OR ENGINEER OF RECORD (EOR). CHANGES BY THE CONTRACTOR, DUE TO CONTRACTOR PROPOSED ALTERNATIVES OR TO CORRECT CONTRACTOR ERRORS/OMISSIONS, MUST BE SUBMITTED TO THE ARCHITECT/E.O.R FOR APPROVAL. THE CONTRACTOR IS RESPONSIBLE FOR ALL COSTS INCLUDING ENGINEERING FEES FOR REVIEW, OBSERVATIONS, STRUCTURAL CALCULATIONS, AND REVISIONS.
THE CONTRACTOR SHALL ALSO PROCESS THE REVISED PLANS REFLECTING ALL SUBSTITUTIONS THROUGH
THE APPROPRIATE OFFICE OF ALL GOVERNING AGENCIES.
4. THE STRUCTURE IS DESIGNED AS SELF…
This is the start of the file's text. The full file is on GovTribe.