Drawing Instructions for Contract 542-26-109: Replace Flat Roof Building 57
This document provides detailed drawing instructions and specifications for the replacement of a flat EPDM roof on Building 57 at the Coatesville VA Medical Center. The project encompasses complete demolition of the existing flat EPDM roofing system, including all insulation, flashing, and associated roof equipment, followed by installation of new EPDM roofing materials with updated equipment.
Demolition and Construction Scope:
The contractor must demolish all existing flat EPDM roofing and remove associated equipment including the exhaust hood over the elevator exhaust, the building exhaust updraft fan, the attic exhaust fan and hood, and lightning protection connected to roof equipment. All debris removal must occur via crane or lift to prevent falling debris. Upon removal, the contractor shall investigate and repair any major damage to the concrete roof deck below to prevent water penetration. Construction activities include installation of new EPDM roof material with copper flashing at railing wall junctions, replacement of insulation and pitching for proper drainage, and replacement of all roof cants. The contractor must replace the exhaust updraft fan with a unit meeting minimum specifications of 2765 CFM, 2.0" static pressure, 20" wheel diameter, 1480 max RPM, direct drive, 3 HP motor, 208V/3Ph, and replace the elevator exhaust hood with a new mushroom hinged vent hood with weather-resistant coating. Equipment curbs must be raised to a minimum of 12 inches, and both roof deck penetrations must be filled with concrete decking. All contractor personnel shall park in Lot A only, and the job site must be secured with chain link fencing. Interior elevators are prohibited for material transport.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 542-26-109 Specifications.pdf | ||
| Attachment 6 - Construction Safety Standards.pdf | ||
| EOC-20.pdf | ||
| VHA ICRA 542-26-109 - Signed.pdf | ||
| Attachment 5 - GEMS Contractor training.doc | DOC document | |
| 36C24426B0013_1.docx | DOCX document | |
| VHA PCRA 542-26-109 - Signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- Drawing Instructions – 542-26-109 Replace Flat Roof Building 57
General Notes –
- Contractor to certify and perform all tests needed to fully meet requirements set by the TIL and government standards.
- Contractor to field verify measurements at site. (Including, but not exclusive to the height of the building, square footage, etc.)
- Coordinate shutdown of entrances and exits within the vicinity of potential falling debris during demolition and construction.
- All debris and materials for construction are to be removed and supplied via a crane or lift to the roof of Building 57. Inside elevators are prohibited from use by the contractors as per the specifications.
- Contractors are not to park in patient or employee spaces near building 57 and instead are to park in lot A.
- The job site and lay‐down space is to be secured via chain link fence.
Demolition ‐
- Demolish all flat EPDM roofing for Building 57 shown in the drawing below. All EPDM, insulation, flashing, and other materials used for the flat EPDM roof is to be removed.
- Remove debris designated to be demolished with a crane or lift and prevent any of the debris from falling off the roof.
- Remove all flat EPDM roofing and roofing materials upon the roof without allowing any of the debris to fall off the roof.
- Remove the exhaust hood over the elevator exhaust and the building exhaust updraft fan.
- Remove the lightning protection connected to the roof equipment up to the railing connections.
- Remove the attic exhaust fan and exhaust hood.
Construction –
- Investigate the concrete roof deck below removed flat EPDM roof and repair any major damage to the concrete deck to prevent water penetration.
- Replace all demolished flat EPDM roof with new EPDM roof material.
- Install copper flashing at all locations where the EPDM meets the railing wall and where it needs to be added as detailed in the
TIL and specifications.
- Replace all insulation and pitching for the EPDM to allow for proper drainage to the roof drains denoted below.
- Replace all cants for the EPDM flat roof where the edges of the railing and roof meet as per specifications and the TIL.
- Replace the exhaust updraft fan with a fan meeting the minimum requirements of 2765 CFM, 2.0” SP, 20” wheel diameter, 1480 max RPM, direct drive, 3 HP motor, 208V/3Ph.
- Replace the exhaust hood over the elevator exhaust with a new mushroom hinged vent hood with a weather resistant coating.
The air flow requirements for the new vent must meet that of the existing hood.
- Replace the removed lightning protection to the new exhaust hood and exhaust fan.
- Raise all equipment curbs to a minimum of 12 inches.
- Fill in both roof deck penetrations with concrete roof decking to meet specification and TIL requirements.
Equipment Notes –
- All dimensions are not to size and are to be field verified by contractor.
- Location map, designated building, and roadways below.
1) Highlighted flat EPDM roof to be replaced in entirety. Includes flashing, roof insulation, pitching, and cants.
2) Highlighted flat EPDM roof to be replaced in entirety.
Includes flashing, roof insulation, pitching, and cants.
3) Highlighted loading dock to be used for lay-down space and crane placement.
Roof Equipment –
- The following pictures are of the roof equipment in place that will need to be removed, replaced, and worked around when handling the roof curbs and re-roofing of the flat EPDM roof.
This exhaust fan is to be replaced with an exhaust fan with a minimum specification of 2765 CFM, 2.0” SP, 20” wheel diameter, 1480 max RPM, direct drive, 3 HP motor, 208V/3Ph.
Replace the exhaust hood over the elevator exhaust with a new mushroom hinged vent hood with a weather resistant coating. The air flow requirements for the new vent must meet that of the existing hood.
Remove this attic exhaust fan in full including the electrical wiring below to the panel. One of the two roof penetrations that will be filled in the concrete decking is below this fan and hood.
Roof penetration below the EPDM flat roof that will need to be filled with concrete decking.