528-18-109 Buffalo VAMC - 9C Project Schedule (1).pdf
PDF 134 KB Posted
- Solicitation number
- 36C24223Q0887
About this file
This document contains a project schedule and submittal cover sheet for renovations to the 9th floor of the Buffalo VA Medical Center. The schedule outlines 75 tasks over 475 days starting in May 2023 through March 2025. Key phases include submittals, abatement and demolition on the 9th floor, mechanical, electrical and plumbing rough-ins, installation of drywall, ceilings, flooring and finishes. Concurrent work is scheduled on other floors including abatement and restoration on the 7th, 8th, 10th and 11th floors from December 2023 through August 2024. The related federal contract opportunity is a solicitation from the Department of Veterans Affairs for air monitoring services to support the 9C Renovation project at the Buffalo VAMC. Responses are due by the date listed on the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24223Q0887.docx | DOCX document | |
| 528-18-109 Air Monitor Drawing Set.pdf | ||
| 528-18-109 9C Abatement Air Monitoring 23JUN23 SOW.docx | DOCX document | |
| 528-18-109 Air Montor Specifications for 9C Renovations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Mode
Task Name Duration Start Finish
1 VAMC Buffalo 9C Renovation 475 days Wed 5/24/23 Tue 3/18/25
2 Submittals 80 days Wed 5/24/23 Tue 9/12/23
3 Mobilization and Install of ICRA Measures 15 days Wed 7/19/23 Tue 8/8/23
4 Abatement of 9th Floor 20 days Wed 8/9/23 Tue 9/5/23
5 General Demolition of 9th Floor 20 days Wed 9/6/23 Tue 10/3/23
6 MEP Demolition 25 days Wed 10/18/23 Tue 11/21/23
7 Layout of 9th Floor 10 days Wed 11/22/23 Tue 12/5/23
8 LGMF Installation on 9th Floor 25 days Wed 12/6/23 Tue 1/9/24
9 HVAC Rough-In 35 days Wed 1/10/24 Tue 2/27/24
10 Plumbing Rough-In 45 days Wed 1/10/24 Tue 3/12/24
11 Coodinated 8th Floor Above Ceiling Work 175 days Wed 12/6/23 Tue 8/6/24
12 Electrical Rough-In 30 days Wed 1/10/24 Tue 2/20/24
13 Sprinkler Rough-In 15 days Wed 1/10/24 Tue 1/30/24
14 Structural Steel Work 25 days Wed 1/31/24 Tue 3/5/24
15 HVAC & Plumbing Insulation Install 20 days Wed 3/13/24 Tue 4/9/24
16 In-wall MEP Inspections 5 days Wed 4/10/24 Tue 4/16/24
17 Install Patient- Lift Track Strucutural Steel 5 days Wed 4/10/24 Tue 4/16/24
18 Pre- Drywall Photo Documentation 5 days Wed 4/17/24 Tue 4/23/24
19 Hang & Finish Drywall 20 days Wed 4/24/24 Tue 5/21/24
20 Demo and Install New Windows? 40 days Wed 5/22/24 Tue 7/16/24
21 Prime Painting 10 days Wed 5/22/24 Tue 6/4/24
22 Install ACT Grid 15 days Wed 5/29/24 Tue 6/18/24
23 Install Patient-Lift Tracking and Motors 5 days Wed 6/19/24 Tue 6/25/24
24 Install Sprinkler Heads 5 days Wed 6/19/24 Tue 6/25/24
25 Above Ceiling MEP Inspections 5 days Wed 6/26/24 Tue 7/2/24
26 Abover Ceiling Photo Documentation 5 days Wed 6/26/24 Tue 7/2/24
27 Hang New Lighting 15 days Wed 7/3/24 Tue 7/23/24
28 Install ACT Tiles 15 days Wed 7/24/24 Tue 8/13/24
29 Install Casework - Furnishings 25 days Wed 8/14/24 Tue 9/17/24
30 Install HVAC Finishes 20 days Wed 8/14/24 Tue 9/10/24
31 Install Plumbing Fixtures 30 days Wed 9/18/24 Tue 10/29/24
32 Install Electrical Finishes /Data/Fire Alarm 30 days Wed 9/18/24 Tue 10/29/24
33 Install New Head Walls 15 days Wed 9/18/24 Tue 10/8/24
34 Floor Prepartions for Finished Flooring 10 days Wed 10/16/24 Tue 10/29/24
35 Install Ceramic Tile/ Porcelain Tile 20 days Wed 10/30/24 Tue 11/26/24
36 Install Finished Flooring (Epoxy, Resilient Tile) 25 days Wed 11/27/24 Tue 12/31/24
37 Install Doors and Hardware 15 days Wed 1/1/25 Tue 1/21/25
38 Install Aluminum Framed Entrances and Storefronts 15 days Wed 1/1/25 Tue 1/21/25
39 Install Signage 10 days Wed 1/1/25 Tue 1/14/25
40 Install Wall and Door Protection 15 days Wed 1/22/25 Tue 2/11/25
41 Install Bathroom and Speciality Accessories 15 days Wed 1/1/25 Tue 1/21/25
42 Finish Painting 10 days Wed 1/22/25 Tue 2/4/25
43 Punchlist 20 days Wed 2/5/25 Tue 3/4/25
44 Demobilize/ Final Cleaning 10 days Wed 3/5/25 Tue 3/18/25
45 Work Plans on Other Floors 175 days Wed 12/6/23 Tue 8/6/24
46 Demolition of Ceiling 7th Floor 5 days Wed 12/6/23 Tue 12/12/23
47 Abatement 8th Floor Part 1 - Phase 2 10 days Wed 12/6/23 Tue 12/19/23
48 Restoration 8th Floor Part 1 - Phase 2 5 days Wed 12/20/23 Tue 12/26/23
49 VA Moving Period- Prep for Next Phase 5 days Wed 12/27/23 Tue 1/2/24
50 Abatement 8th Floor Part 1 - Phase 3 10 days Wed 1/3/24 Tue 1/16/24
51 Restoration 8th Floor Part 1 - Phase 3 5 days Wed 1/17/24 Tue 1/23/24
52 VA Moving Period- Prep for Next Phase 5 days Wed 1/24/24 Tue 1/30/24
53 Abatement 8th Floor Part 1 - Phase 4 10 days Wed 1/31/24 Tue 2/13/24
54 Restoration 8th Floor Part 1 - Phase 4 5 days Wed 2/14/24 Tue 2/20/24
55 VA Moving Period- Prep for Next Phase 5 days Wed 2/21/24 Tue 2/27/24
56 Abatement 8th Floor Part 1 - Phase 5 10 days Wed 2/28/24 Tue 3/12/24
57 Restoration 8th Floor Part 1 - Phase 5 5 days Wed 3/13/24 Tue 3/19/24
58 VA Moving Period- Prep for Next Phase 5 days Wed 3/20/24 Tue 3/26/24
59 Abatement 8th Floor Part 1 - Phase 6 10 days Wed 3/27/24 Tue 4/9/24
60 Restoration 8th Floor Part 1 - Phase 6 5 days Wed 4/10/24 Tue 4/16/24
61 VA Moving Period- Prep for Next Phase 5 days Wed 4/17/24 Tue 4/23/24
62 Abatement 10th Floor Part 1 - Phase 2 10 days Wed 4/24/24 Tue 5/7/24
63 Restoration 10th Floor Part 1 - Phase 2 5 days Wed 5/8/24 Tue 5/14/24
64 VA Moving Period- Prep for Next Phase 5 days Wed 5/15/24 Tue 5/21/24
65 Abatement 10th Floor Part 1 - Phase 5 10 days Wed 5/22/24 Tue 6/4/24
66 Restoration 10th Floor Part 1 - Phase 5 5 days Wed 6/5/24 Tue 6/11/24
67 VA Moving Period- Prep for Next Phase 5 days Wed 6/12/24 Tue 6/18/24
68 Abatement 10th Floor Part 1 - Phase 6 10 days Wed 6/19/24 Tue 7/2/24
69 Restoration 10th Floor Part 1 - Phase 6 5 days Wed 7/3/24 Tue 7/9/24
70 VA Moving Period- Prep for Next Phase 5 days Wed 7/10/24 Tue 7/16/24
71 Abatement 11th Floor and Demo 10 days Wed 7/17/24 Tue 7/30/24
72 Restoration 11th Floor 5 days Wed 7/31/24 Tue 8/6/24
SMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSM MayMayJun Jun Jun Jun Jul 2Jul 9Jul Jul Jul 3AugAugAugAugSep Sep Sep Sep Oct Oct Oct Oct Oct NovNovNovNovDec Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb MarMa MarMarMarApr Apr Apr Apr MayMayMayMayJun Jun Jun Jun Jun Jul 7Jul Jul Jul 2AugAugAugAugSep Sep Sep Sep Sep Oct Oct Oct Oct NovNovNovNovDec Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb MarMa MarMa MarApr Apr Apr Apr MayMayMayMayJun Jun Jun Jun Jun Jul 6Jul Jul 2J
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: VAMC Buffalo 9C Proje Date: Thu 5/25/23
| Buffalo VA 9C Renovations - Submittal Cover Sheet.pdf |
| SUBMITTAL COVER SHEET |
| OWNER: |
| VA MEDICAL CENTER |
| WELCH CONSTRUCTION, INC. |
| PATHFINDER ENGINEERS & ARCHITECTS |
File details come from the government source that posted it. Updated .