This is a Statement of Work (SOW) for sterndrive replacement services on the USCGC JUNIPER (WLB 201), a 24'6" hull length Coast Guard vessel located in Honolulu, Hawaii. The contractor shall provide a Certified Mercury Technician, all required gaskets, equipment, tools, and facilities to remove and replace the transom assembly, gimbal bearing, sterndrive assembly (3040-01-661-0628, PN 5237300TP B1X 1.65:1 Drive), propeller (PN 48-19838A46), and exhaust bellows in accordance with Mercury service manuals and alignment procedures. The contractor must also troubleshoot and correct excessive play in the steering system, with steering casualty parts to be determined following a deeper inspection. The Coast Guard will provide the sterndrive, transom assembly, o-rings, gimbal bearing, bellows, seal, and propeller. Work shall commence by an agreed-upon date following contract award in 2026 and must be completed diligently thereafter.
The associated solicitation (52000PR270001125) is a Request for Quote (RFQ) issued by the U.S. Coast Guard for commercial services under PSC J020 and NAICS 336611. This is a 100% Small Business Set-Aside with evaluation criteria based on technical capability, past performance, and fair and reasonable pricing. The contract type is Firm Fixed Price Purchase Order. Points of contact include COR Robert Shinagawa, Secondary Unit POC MKC Jose Sanchez, and Contracting Officer Joshua Richardson. Upon completion, the contractor must arrange for inspection and acceptance of work with the Unit POC and ensure all hazardous waste, trash, and debris are removed from the site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 52000PR270001125.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK (SOW)
FOR
Commanding Officer
USCGC JUNIPER (WLB 201)
400 Sand Island PKWY.
Honolulu, HI 96819
PH: (808) 842-2865
1. SCOPE: Contractor shall provide a Certified Mercury Technician, all required parts listed below, equipment, tools, and facilities to replace the transom assembly, gimbal bearing, sterndrive assembly, propeller and exhaust bellows. The contractor shall also troubleshoot and correct any excessive play in the steering system. Parts for steering casualty are TBD until a deeper inspection can be performed.
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: Upon acceptance, the contractor shall commence work by an agreed upon date established after the award has been issued. 2026 and work diligently to complete the entire project.
3. INFORMATION AND REQUIREMENTS:
Physical Characteristics of Vessel
1. Hull Length 24’ 6”
2. Length Overall on trailer 31’ 10”
3. Beam Overall 7’ 11”
4. Highest Points: Fixed on trailer 12’ 0”
4. REQUIRED PARTS FROM CONTRACTOR:
Misc Gaskets if required in accordance with Mercury Service Manual
5. REQUIRED PARTS PROVIDED BY COAST GUARD
Sterndrive- 3040-01-661-0628, PN: 5237300TP (B1X 1.65:1 Drive) Transom Assembly PN: 62000025P O-Ring Coupler (3)- 015016327 (25-35027) O-Ring Gimbal (2)- 015016329 (25-29845) Gimbal Bearing- 015018673 (879194A01) Bellows- 015018391 (8M0062406) Seal- 011251078 (26-88416) Prop- 015771672 (48-19838A46)
Mercury Bravo 1 Sterndrive Replacement
1. Certified Mercury technicians shall remove and replace the transom assembly, sterndrive, gimbal bearing, bellows and all required/damaged/worn O-rings/seals/components in accordance with the Mercury parts breakdown, service manual and alignment procedures for the B1X 1.65:1 sterndrive.
2. Certified Mercury technician shall install replacement propeller and all worn/damaged- components in accordance with Mercury parts breakdown and service manual for propeller PN: 48-1938A46.
3. Certified Mercury technician shall adjust steering in accordance with Mercury service and Steyr Manual for proper operation.
4. Technicians shall diagnose and provide additional estimates for replacement parts or additional repairs for the CFR if required.
5. Technician shall verify proper operation of steering and all sterndrive components once replacement and repairs are complete. To include underway sea trials with representative from the Coast Guard. Contractor shall organize and provide CFRs as needed.
6. CONDITIONS AFFECTING THE WORK: If additional work items are found, contractor shall report findings immediately before work continues via CFR along with commercial estimate of necessary work to be completed outside the original scope.
7. AFTER AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s representative of intended start date. The work shall be done in accordance with the specification.
8. ORAL MODIFICATION: No oral statement of any person other than the Contracting Officer shall, in any manner or degree, modify or otherwise affect the terms of this contract.
9. WORKMANSHIP: All work shall be accomplished with a Certified Mercury Technician and shall be satisfactory to the Contracting Officer Representative (COR)/CG on site representative.
10. PERMITS: The contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state, and local laws.
11. CLEAN UP: All HAZWASTE, trash and debris shall be removed from the site and or recycled as applicable. The job site shall be left in a clean and neat manner.
12. UPON COMPLETION OF WORK: Contact the Unit POC to arrange for inspection/acceptance of work.
13. POINTS OF CONTACT:
Unit POC Primary MK1 Cam Fageol Phone: 619-987-4725 Email: Cameron.l.fageol@uscg.mil
Secondary MKC Jose Sanchez Phone: 305-469-3796 Email: Jose.V.Sanchez@uscg.mil