STA Coos Bay_MLB 47302 Rudder Post Renewal_Scope Of Work (002).docx
DOCX document 27 KB Posted
- Attached to
- Rudder Stock Assembly Renew
- Solicitation number
- 52000PR260000644
About this file
This document is a Scope of Work (SOW) for the U.S. Coast Guard Station Coos Bay, detailing the renewal of rudder stock housing assemblies for a 47' MLB (Motor Life Boat) Class C vessel. The project requires the contractor to haul out the vessel, remove and crop existing rudder components, conduct visual and non-destructive testing, renew stiffeners and housing components, and reinstall rudders according to specific Coast Guard technical drawings.
The work must be completed within 28 working days of scheduled haul-out, with the contractor responsible for providing labor, welding equipment, and materials. Key requirements include following specific USCG docking and welding guidelines, gas-freeing the lazarette, performing detailed inspections, and conducting a full power trial with Coast Guard personnel. The solicitation is a Firm Fixed Price Purchase Order issued by the U.S. Coast Guard Surface Forces Logistics Center, to be awarded on a Lowest Priced Technically Acceptable basis with no down payments or advanced payments permitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 47B-MLB_801_002 Docking Plan.pdf | ||
| 47302 STBD Rudder post.jpg | JPG image | |
| 47302 PORT Rudder post.jpg | JPG image | |
| FL_85_2_1_-_D Hotwork Diagram.pdf | ||
| 47C-MLB_561_020 Rudder Housing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK (SOW)
FOR
U.S. Coast Guard Station Coos Bay MLB Class C 47302
1. SCOPE:
Contractor shall provide general facilities, labor, and welding equipment/materials necessary to Crop and Renew a section of the P&S Rudder Stock Housing Assemblies on a 47’ MLB IAW all applicable Coast Guard Drawings and Technical Publications.
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
Upon acceptance, the contractor shall commence work within 15 days and work diligently to complete the entire project and have vessel ready for use by 28 working days from scheduled haul-out after contract award.
3. INFORMATION AND REQUIREMENTS:
Physical Characteristics of Vessel
1. Length Overall 48’ 11” (w/ Rubrails)
2. Beam Overall 15’0” (w/ Rubrails)
3. Highest Points: Fixed 18’ 6” (Radar), Unfixed 28’ 4”
4. Hoisting condition 40,000 LBS (boat, full fuel, outfit; no crew or cargo)
SCOPE OF WORK:
1. Haul out and stage asset IAW USCG Drawing 47B-MLB-801-002 Docking Plan. Contractor must follow General Note 8 on drawing 47B-MLB-801-002 ensuring the rudder is able to be removed at the specified docking height.
2. Remove the P&S Rudders.
3. Remove all interferences.
4. Gas Free the Lazarette IAW USCG Drawing FL_85_2_1_-_C GFE Hotwork Diagrams.
5. Crop Item #1 (Stiffeners), Item #2 (Pipe), and Item #4 (Upper Bearing Housing) IAW USCG Drawing 47C MLB 561-020 for the P&S Rudder Stock Housing Assembly.
6. Conduct visual inspection on Item #4 (Upper Bearing Housing). If item cannot be re-used, submit CFR to the COR.
7. Renew Item #1 (Stiffeners), Item #2 (Pipe), and Item #4 (Upper Bearing Housing) returning P&S Rudder Stock Housing Assembly to original configuration as outlined in USCG Drawing 47C MLB 561-020.
8. Conduct satisfactory NDT of all welds on the STBD Rudder Stock Assembly.
9. Re-install the P&S Rudders.
10. Re-install all interferences.
11. Launch and conduct satisfactory Full Power Trial with USCG personnel.
**CG Personnel shall electrically isolate the asset before hot-work commences and undo the isolation at the completion of hot-work IAW MLB WELD DISCONNECT SERVICE WORK INSTRUCTION.
4. CONDITIONS AFFECTING THE WORK:
If additional work items are found. Contractor shall report findings immediately before work continues via CFR along with commercial estimate of necessary work to be completed outside the original SOW.
5. AFTER AWARD OF THE CONTRACT:
The contractor must immediately notify the contracting officer’s representative of his intended start date. The work shall be done in accordance with the specification.
6. ORAL MODIFICATION:
No oral statement of any person other than the contracting officer shall in any manner or degree, modifies or otherwise affect the terms of this contract.
7. WORKMANSHIP:
All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer Representative (COR).
8. PERMITS:
The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state, and local laws.
9. CLEAN UP:
All HAZWASTE, trash and debris shall be removed from the site and or recycled as applicable. The job site shall be left in a clean and neat manner.
10. UPON COMPLETION OF WORK:
Contact the COR to arrange for inspection/acceptance of work.
11. POINTS OF CONTACT:
Unit Contacts:
MKC David S. Young Engineering Petty Officer CG Station Coos Bay
12. Enclosures: All supporting documentation will be attached via email.