Questions & Answers

Repair Perimeter Fence, RAF Molesworth, United Kingdom 501RCO_CON0001

1. Attachment 3 – cost breakdown – you have included columns for labour and materials however there is no area to include for plant and equipment – can you advise where this should be included?

If you have extra cost elements that are not included within attachment 3, please include them appropriately.

2. Section K – form 1442 – can you please confirm which parts need to be completed?

If your company is registered within sam.gov than this section is not necessary.

3. There is no stated completion date or maximum duration on site – do you have a requirement for this or will it be based on what we determine is required to complete the works?

Page 1. box 11 of the 1442 states the following:

The contractor shall begin performance within 30 calendar days and complete it within

180 calendar days after receiving award, notice to proceed.