50013-BTB2858.pdf
PDF 11 MB Posted
- Attached to
- ENGINEERING ANNEX ROOF - addendum 2
- Solicitation number
- 50013-BTB2858
- Issued by
- Orleans Parish, New Orleans City, Louisiana
About this file
This is a comprehensive set of bid documents for the Engineering Annex Roof Replacement project at the University of New Orleans, involving the State of Louisiana, Facility Planning and Control, and Holly & Smith Architects. The project involves a complete roof replacement for the Engineering Annex building located at 2000 Lakeshore Drive in New Orleans, covering approximately 29,500 square feet of roof area. The bid documents were issued on February 7, 2025, with sealed bids due on April 30, 2025, at 2:00 PM. A mandatory pre-bid conference is scheduled for April 17, 2025, at 10:00 am in the Engineering Auditorium. The contract requires full completion within 90 consecutive calendar days, with liquidated damages of $300 per day for each day beyond the contract completion date. Contractors must be licensed in Louisiana for Building Construction or Roofing and Sheet Metal/Siding.
The project will utilize a State of Louisiana approved 20-year, 2-ply SBS modified bitumen roofing system, including removal of the existing ballasted, insulated built-up roof system down to the concrete roof deck. The roofing system will include tapered polyisocyanurate insulation, a gypsum cover board, and associated flashings and accessories. The project is funded through the State of Louisiana and will be executed under a single prime contract. Bidders are encouraged to participate in the Small Entrepreneurship (SE) Program and the Veteran-Owned Small Entrepreneurships Program. The project requires comprehensive documentation, including warranties, manufacturer certifications, and adherence to specific installation guidelines. Bid security of 5% is required, and the contract will be awarded to the lowest responsive and responsible bidder meeting all specified requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 50013-BTB2858-2.pdf | ||
| 50013-BTB2858-1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENGINEERING ANNEX ROOF
REPLACMENT - UNIVERSITY OF NEW
ORLEANS
H/S PROJECT No. 24054
BIDDING DOCUMENTS
02/07/2025
Table of Contents TOC - 1
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
ADVERTISEMENT FOR BIDS
INSTRUCTIONS TO BIDDERS
LOUISIANA UNIFORM PUBLIC WORK BID FORM
BID BOND
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION, AIA A201-2017
SUPPLEMENTARY CONDITIONS
CONTRACT BETWEEN OWNER AND CONTRACTOR AND PERFORMANCE AND PAYMENT BOND
ATTESTATION AFFIDAVIT
PRE-CONSTRUCTION CONFERENCE AGENDA
SCHEDULE OF VALUES
CHANGE ORDER
RECOMMENDATION OF ACCEPTANCE
PARTIAL OCCUPANCY
RECOMMENDED AGENDA FOR ROOFING CONFERENCES
ROOFING GUARANTEE R-1
ROOFING GUARANTEE R-2
MANUFACTOR’S NDL WATERTIGHTNESS MEMBRANE ROOFING SYSTEM WARRANTY
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 011000 – SUMMARY
SECTION 012200 – UNIT PRICES
SECTION 012300 - ALTERNATES
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
SECTION 012900 - PAYMENT PROCEDURES
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014000 - QUALITY REQUIREMENTS
SECTION 014200 - REFERENCES
SECTIOM 014339 - MOCKUPS
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
SECTION 016000 - PRODUCT REQUIREMENTS
SECTION 017300 - EXECUTION
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 017700 - CLOSEOUT PROCEDURES
SECTION 017823 - OPERATION AND MAINTENANCE DATA
SECTION 017839 - PROJECT RECORD DOCUMENTS
SECTION 017900 - DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
SECTION 024119 - SELECTIVE DEMOLITION
ENGINEERING ANNEX ROOF
REPLACMENT - UNIVERSITY OF NEW
ORLEANS
H/S PROJECT No. 24054
BIDDING DOCUMENTS
02/07/2025
Table of Contents TOC - 2
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
SECTION 061000 – ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 070150.19 – PREPARATION FOR REROOFING
SECTION 075500 – SBS-MODIFIED BITUMEN MEMBRANE ROOFING
SECTION 076200 – SHEEET METAL FLASHING AND TRIM
SECTION 077200 – ROOF ACCESSORIES
SECTION 079200 – JOINT SEALANTS
DIVISION 09 - FINISHES
SECTION 099114 – EXTERIOR PAINTING (MPI STANDARDS)
DIVISION 22 – PLUMBING
SECTION 221423 – STORM DRAINAGE PIPING SPECIALITIES
DIVISION 26 – ELECTRICAL
SECTION 264113 – LIGHTING PROTECTION SYSTEM
ADVERTISEMENT FOR BIDS
Sealed bids will be received at the University of New Orleans Purchasing Office, Administration Annex Building, Room 1004G, New
Orleans, LA 70148. The deadline for receipt of bids is 2:00 PM, Wednesday, April 30, 2025, at which time bids will be publicly opened and read aloud in a public meeting in the Administration Building, Conference Room 101 for the following:
FOR: Engineering Annex Roof Replacement 1st Floor
University of New Orleans
New Orleans, Louisiana
UNO BTB 2858, SP5286
PROJECT NUMBER: 01-107-24-05, F.01004598
Complete Bid Documents for this project are available in electronic form. They may be obtained without charge and without deposit from Holly & Smith Architects, APAC. Printed copies are not available from the Designer, but arrangements can be made to obtain them through most reprographic firms. Plan holders are responsible for their own reproduction costs. Questions about this procedure shall be directed to the Designer at:
Holly & Smith Architects, APAC
2302 Magazine St., New Orleans, LA 70130
504.585-1315 ray@hollyandsmith.com
All bids shall be accompanied by bid security in an amount of five percent (5.0%) of the sum of the base bid and all alternates. The form of this security shall be as stated in the Instructions to Bidders included in the Bid Documents for this project.
The successful Bidder shall be required to furnish a Performance and Payment Bond written as described in the Instructions to Bidders included in the Bid Documents for this project.
A PRE-BID CONFERENCE WILL BE HELD
at 10:00 am on Thursday, April 17, 2025 at University of New Orleans, Engineering Auditorium, Room 101, 2000
Lakeshore Drive, New Orleans, LA 70148
Bids shall be accepted from Contractors who are licensed under LA. R.S. 37:2150-2192 for the classification of Building
Construction or Roofing and Sheet Metal/Siding. Bidder is required to comply with provisions and requirements of LA R.S.
38:2212(B)(5). No bid may be withdrawn for a period of forty-five (45) days after receipt of bids, except under the provisions of LA.
R.S. 38:2214.
The Owner reserves the right to reject any and all bids for just cause. In accordance with La. R.S. 38:2212(B)(1), the provisions and requirements of this Section; and those stated in the bidding documents shall not be waived by any entity.
University of New Orleans is a participant in the Small Entrepreneurship (SE) Program (the Hudson Initiative) and the Veteran-
Owned and Service-Connected Disabled Veteran-Owned (LaVet) Small Entrepreneurships Program. Bidders are encouraged to consider participation. Information is available from the University of New Orleans Purchasing Office.
If you have a disability and would like to request an accommodation in order to participate in this meeting, please contact Melanie
Champagne at mmchamp2@uno.edu or (504) 280-3237 as soon as possible but no later than 48 hours before the scheduled meeting.
Ad Dates: April 2, 2025
April 6, 2025
April 13, 2025 mmchamp2 Rectangle
June 2024 IB -1
INSTRUCTIONS TO BIDDERS
COMPLETION TIME:
The Bidder shall agree to fully complete the contract within (90) consecutive calendar days, subject to such extensions as may be granted under Paragraph 8.3, in the General Conditions and the Supplementary
Conditions, and acknowledges that this construction time will start on or before the date specified in the written
“Notice to Proceed” from the Owner.
LIQUIDATED DAMAGES:
The Bidder shall agree to pay as Liquidated Damages the amount of Three hundred Dollars ($300.00) for each consecutive calendar day for which the work is not complete, beginning with the first day beyond the contract completion date stated on the “Notice to Proceed” or as amended by change order.
ARTICLE 1
DEFINITIONS
1.1 The Bid Documents include the following:
Advertisement for Bids
Instructions to Bidders
Bid Form
Bid Bond
General Conditions of the Contract for
Construction, AIA Document A201, 2017 Edition
Supplementary Conditions
Contract Between Owner and Contractor and Performance and Payment Bond
Affidavit
User Agency Documents (if applicable)
Change Order Form
Partial Occupancy Form
Recommendation of Acceptance
Asbestos Abatement (if applicable)
Other Documents (if applicable)
Specifications & Drawings
Addenda issued during the bid period and acknowledged in the Bid Form
1.2 All definitions set forth in the General Conditions
of the Contract for Construction, AIA Document
A201 and the Supplementary Conditions are applicable to the Bid Documents.
1.3 Addenda are written and/or graphic instruments
issued by the Architect prior to the opening of bids, which modify or interpret the Bid Documents by additions, deletions, clarifications, corrections and prior approvals.
1.4 A bid is a complete and properly signed proposal
to do the work or designated portion thereof for the sums stipulated therein supported by data called for by the Bid Documents.
1.5 Base bid is the sum stated in the bid for which the
Bidder offers to perform the work described as the base, to which work may be added, or deleted for sums stated in alternate bids.
1.6 An alternate bid (or alternate) is an amount stated
in the bid to be added to the amount of the base bid if the corresponding change in project scope or materials or methods of construction described in the
Bid Documents is accepted.
1.7 A Bidder is one who submits a bid for a prime
Contract with the Owner for the work described in the Bid Documents.
1.8 A Sub-bidder is one who submits a bid to a
Bidder for materials and/or labor for a portion of the work.
1.9 Where the word "Architect" is used in any of the
documents, it shall refer to the Prime Designer of the project, regardless of discipline.
ARTICLE 2
PRE-BID CONFERENCE
2.1 A Pre-Bid Conference shall be held at least 10
days before the date for receipt for bids. The
Architect shall coordinate the setting of the date, time and place for the Pre-Bid Conference with the User
Agency and shall notify in writing the Owner and all who have received sets of the Bid Documents to
June 2024 IB -2 attend. The purpose of the Pre-Bid Conference is to familiarize Bidders with the requirements of the
Project and the intent of the Bid Documents, and to receive comments and information from interested
Bidders. If the Pre-Bid Conference is stated in the
Advertisement for Bids to be a Mandatory Pre-Bid
Conference, bids shall be accepted only from those bidders who attend the Pre-Bid Conference.
Contractors who are not in attendance for the entire
Pre-Bid Conference will be considered to have not attended.
2.2 Any revision of the Bid Documents made as a
result of the Pre-Bid Conference shall not be valid unless included in an addendum.
ARTICLE 3
BIDDER'S REPRESENTATION
3.1 Each Bidder by making his bid represents that:
3.1.1 He has read and understands the Bid
Documents and his bid is made in accordance therewith.
3.1.2 He has visited the site and has familiarized
himself with the local conditions under which the work is to be performed.
3.1.3 His bid is based solely upon the materials, systems and equipment described in the Bid
Documents as advertised and as modified by addenda.
3.1.4 His bid is not based on any verbal
instructions contrary to the Bid Documents and addenda.
3.1.5 He is familiar with Code of Governmental
Ethics requirement that prohibits public servants and/or their immediate family members from bidding on or entering into contracts; he is aware that the
Designer and its principal owners are considered
Public Servants under the Code of Governmental
Ethics for the limited purposes and scope of the
Design Contract with the State on this Project (see
Ethics Board Advisory Opinion, No. 2009-378 and
2010-128); and neither he nor any principal of the
Bidder with a controlling interest therein has an immediate family relationship with the Designer or any principal within the Designer’s firm (see La. R.S.
42:1113). Any Bidder submitting a bid in violation of this clause shall be disqualified and any contract entered into in violation of this clause shall be null and void.
3.2 The Bidder must be fully qualified under any
State or local licensing law for Contractors in effect at the time and at the location of the work before submitting his bid. In the State of Louisiana, Revised
Statutes 37:2150, et seq. will be considered, if applicable.
The Contractor shall be responsible for determining that all of his Sub-bidders or prospective
Subcontractors are duly licensed in accordance with law.
ARTICLE 4
BID DOCUMENTS
4.1 Copies
4.1.1 Bid Documents may be obtained from the
Architect for a deposit as stated in the Advertisement for Bids. The deposit will be refunded as stated in the
Advertisement for Bids. No deposits will be refunded on Bid Documents returned later than ten days after receipt of bids.
4.1.1.2 As an alternative method of distribution, the
Designer may provide the Bid Documents in electronic format. They may be obtained without charge and without deposit as stated in the
Advertisement for Bids.
4.1.1.2.1 If electronic distribution is available, printed copies will not be available from the
Designer, but arrangements can be made to obtain them through most reprographic firms and/or plan rooms.
4.1.1.2.2 If electronic distribution is available, the
reproduction cost on the first paper plan set acquired by bona fide prime bidders will be fully refunded by the Designer upon delivery of the documents to the
Designer in good condition no later than ten days after receipt of bids.
4.1.1.2.3 If electronic distribution is available, all
other plan holders are responsible for their own reproduction costs.
June 2024 IB -3
4.1.2 Complete sets of Bid Documents shall be
used in preparing bids; neither the Owner nor the
Architect assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bid Documents.
4.1.3 The Owner or Architect in making copies of
the Bid Documents available on the above terms, do so only for the purpose of obtaining bids on the work and do not confer a license or grant for any other use.
4.2 Interpretation or Correction of Bid Documents
4.2.1 Bidders shall promptly notify the Architect
of any ambiguity, inconsistency or error which they may discover upon examination of the Bid
Documents or of the site and local conditions.
4.2.2 Bidders requiring clarification or
interpretation of the Bid Documents shall make a written request to the Architect, to reach him at least seven days prior to the date for receipt of bids.
4.2.3 Any interpretation, correction or change of
the Bid Documents will be made by addendum.
Interpretations, corrections or changes of the Bid
Documents made in any other manner will not be binding and Bidders shall not rely upon such interpretations, corrections and changes.
4.3 Substitutions
4.3.1 The materials, products and equipment
described in the Bid Documents establish a standard of required function, dimension, appearance and quality to be met by any proposed substitution. No substitutions shall be allowed after bids are received.
4.3.2 No substitution will be considered unless
written request for approval has been submitted by the Proposer and has been received by the Architect at least fourteen (14) working days prior to the opening of bids. (La. R.S. 38:2295(C)) Each such request shall include the name of the material or equipment for which it is to be substituted and a complete description of the proposed substitute including model numbers, drawings, cuts, performance and test data and any other information necessary for an evaluation. A statement setting forth any changes in other materials, equipment or work that incorporation of the substitute would require shall be included. It shall be the responsibility of the proposer to include in his proposal all changes required of the Bid Documents if the proposed product is used. Prior approval, if given, is contingent upon supplier being responsible for any costs which may be necessary to modify the space or facilities needed to accommodate the materials and equipment approved.
4.3.3 If the Architect approves any proposed
substitution, such approval shall be set forth in an addendum. Bidders shall not rely upon approvals made in any other manner.
4.4 Addenda
4.4.1 Addenda will be transmitted to all who are
known by the Architect to have received a complete set of Bid Documents.
4.4.2 Copies of addenda will be made available for
inspection wherever Bid Documents are on file for that purpose.
4.4.3 Except as described herein, addenda shall
not be issued within a period of seventy-two (72) hours prior to the advertised time for the opening of bids, excluding Saturdays, Sundays, and any other legal holidays. If the necessity arises of issuing an addendum modifying plans and specifications within the seventy-two (72) hour period prior to the advertised time for the opening of bids, then the opening of bids shall be extended at least seven but no more than twenty-one (21) working days, without the requirement of re-advertising. University of New
Orleans shall be consulted prior to issuance of such an addendum and shall approve such issuance. The revised time and date for the opening of bids shall be stated in the addendum.
4.4.4 Each Bidder shall ascertain from the
Architect prior to submitting his bid that he has received all addenda issued, and he shall acknowledge their receipt on the Bid Form.
4.4.5 The Owner shall have the right to extend the
bid date by up to (30) thirty days without the requirement of re-advertising. Any such extension shall be made by addendum issued by the Architect.
ARTICLE 5
June 2024 IB -4
BID PROCEDURE
5.1 Form and Style of Bids
5.1.1 Bids shall be submitted on the Louisiana
Uniform Public Work Bid Form provided by the
Architect for this project.
5.1.2 The Bidder shall ensure that all applicable
blanks on the bid form are completely and accurately filled in.
5.1.3 Bid sums shall be expressed in both words
and figures, and in case of discrepancy between the two, the written words shall govern.
5.1.4 Any interlineation, alteration or erasure must
be initialed by the signer of the bid or his authorized representative.
5.1.5 Bidders are cautioned to complete all
alternates should such be required in the Bid Form.
Failure to submit alternate prices will render the bid non responsive and shall cause its rejection.
5.1.6 Bidders are cautioned to complete all unit
prices should such be required in the Bid Form. Unit prices represent a price proposal to do a specified quantity and quality of work. Unit prices are incorporated into the base bid or alternates, as indicated on the Unit Price Form, but are not the sole components thereof.
5.1.7 Bidder shall make no additional stipulations
on the Bid Form nor qualify his bid in any other manner.
5.1.8 Written evidence of the authority of the
person signing the bid for the public work shall be submitted in accordance with La. R.S. 38:2212
(B)(5).
5.1.9 On any bid in excess of fifty thousand dollars
($50,000.00), the Contractor shall certify that he is licensed under La. R.S. 37: 2150-2173 and show his license number on the bid above his signature or his duly authorized representative.
5.2 Bid Security
5.2.1 No bid shall be considered or accepted
unless the bid is accompanied by bid security in an amount of five percent (5.0%) of the base bid and all alternates.
The bid security shall be in the form of a certified check or cashier's check drawn on a bank insured by the Federal Deposit Insurance Corporation, or a Bid
Bond written by a surety company licensed to do business in Louisiana and signed by the surety's agent or attorney-in-fact. The Bid Bond shall be written on the Bid Bond Form, and the surety for the bond must meet the qualifications stated thereon. The Bid Bond shall include the legal name of the bidder be in favor of the State of Louisiana, University of New Orleans and shall be accompanied by appropriate power of attorney. The Bid Bond must be signed by both the bidder/principal and the surety in the space provided on the Bid Bond Form. Failure by the bidder/principal or the surety to sign the bid bond shall result in the rejection of the bid.
Bid security furnished by the Contractor shall guarantee that the Contractor will, if awarded the work according to the terms of his proposal, enter into the Contract and furnish Performance and Payment
Bonds as required by these Bid Documents, within fifteen (15) days after written notice that the instrument is ready for his signature.
Should the Bidder refuse to enter into such
Contract or fail to furnish such bonds, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as penalty.
5.2.2 The Owner will have the right to retain the
bid security of Bidders until either (a) the Contract has been executed and bonds have been furnished, or
(b) the specified time has elapsed so that bids may be withdrawn, or (c) all bids have been rejected.
5.3 Submission of Bids
5.3.1 The Bid shall be sealed in an opaque
envelope. The bid envelope shall be identified on the outside with the name of the project, and the name, address, and license number of the Bidder.
The envelope shall not contain multiple bid forms, and will be received until the time specified and at the place specified in the Advertisement for Bids. It shall be the specific responsibility of the Bidder to deliver his sealed bid to the University of New Orleans at the appointed place and prior to the announced time for the opening of bids. Late delivery of a bid for any reason, including late delivery by United States Mail, or express delivery, shall disqualify the bid.
June 2024 IB -5
If the bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope with the notation "Bid Enclosed" on the face thereof. Such bids shall be sent by Registered or Certified Mail, Return Receipt Requested, addressed to:
University of New Orleans - Purchasing
Suite 1004, Room G
Administration Annex Building
2000 Lakeshore Drive
New Orleans, Louisiana 70148
Bids sent by express delivery shall be delivered to:
University of New Orleans - Purchasing
Suite 1004, Room G
Administration Annex Building
6652 Milneburg Road
5.3.2 Bids shall be deposited at the designated
location prior to the time on the date for receipt of bids indicated in the Advertisement for Bids, or any extension thereof made by addendum. Bids received after the time and date for receipt of bids will be returned unopened.
5.3.3 Bidder shall assume full responsibility for
timely delivery at location designated for receipt of bids.
5.3.4 Oral, telephonic or telegraphic bids are
invalid and shall not receive consideration. Owner shall not consider notations written on outside of bid envelope which have the effect of amending the bid.
Written modifications enclosed in the bid envelope, and signed or initialed by the Contractor or his representative, shall be accepted.
5.4 Modification or Withdrawal of Bid
5.4.1 A bid may not be modified, withdrawn or
canceled by the Bidder during the time stipulated in the Advertisement for Bids, for the period following the time and bid date designated for the receipt of bids, and Bidder so agrees in submitting his bid, except in accordance with R.S. 38:2214 which states, in part, "Bids containing patently obvious, unintentional, and substantial mechanical, clerical, or mathematical errors, or errors of unintentional omission of a substantial quantity of work, labor, material, or services made directly in the compilation of the bid, may be withdrawn by the contractor if clear and convincing sworn, written evidence of such errors is furnished to the public entity within forty-eight hours of the bid opening excluding Saturdays, Sundays, and legal holidays".
5.4.2 Prior to the time and date designated for
receipt of bids, bids submitted early may be modified or withdrawn only by notice to the party receiving bids at the place and prior to the time designated for receipt of bids.
5.4.3 Withdrawn bids may be resubmitted up to
the time designated for the receipt of bids provided that they are then fully in conformance with these
Instructions to Bidders.
5.4.4 Bid Security shall be in an amount sufficient
for the bid as modified or resubmitted.
5.5 Prohibition of Discriminatory Boycotts of Israel
By submitting a bid, the bidder certifies and agrees that the following information is correct:
In preparing its bid, the bidder has considered all proposals submitted from qualified, potential subcontractors and suppliers, and has not, in the solicitation, selection, or commercial treatment of any subcontractor or supplier, refused to transact or terminated business activities, or taken other actions intended to limit commercial relations, with a person or entity that is engaging in commercial transactions in Israel or Israel-controlled territories, with the specific intent to accomplish a boycott or divestment of Israel. The bidder has also not retaliated against any person or other entity for reporting such refusal, termination, or commercially limiting actions. The state reserves the right to reject any bid if this certification is subsequently determined to be false and to terminate any contract awarded based on such a false response.
ARTICLE 6
CONSIDERATION OF BIDS
6.1 Opening of Bids
6.1.1 The properly identified Bids received on
time will be opened publicly and will be read aloud, and a tabulation abstract of the amounts of the base bids and alternates, if any, will be made available to
Bidders.
June 2024 IB -6
6.2 Rejection of Bids
6.2.1 The Owner shall have the right to reject any
or all bids and in particular to reject a bid not accompanied by any required bid security or data required by the Bid Documents or a bid in any way incomplete or irregular.
6.3 Acceptance of Bid
6.3.1 It is the intent of the Owner, if he accepts any
alternates, to accept them in the order in which they are listed in the Bid Form. Determination of the Low
Bidder shall be on the basis of the sum of the base bid and the alternates accepted. However, the Owner shall reserve the right to accept alternates in any order which does not affect determination of the Low
Bidder.
ARTICLE 7
POST-BID INFORMATION
7.1 Submissions
7.1.1 At the Pre-Construction Conference, the
Contractor shall submit the following information to the Architect.
7.1.1.1 A designation of the work to be performed
by the Contractor with his own forces.
7.1.1.2 A breakdown of the Contract cost
attributable to each item listed in the Schedule of
Values Form (attached). No payments will be made to the Contractor until this is received.
7.1.1.3 The proprietary names and the suppliers of
principal items or systems of material and equipment proposed for the work.
7.1.1.4 A list of names and business domiciles of all
Subcontractors, manufacturers, suppliers or other persons or organizations (including those who are to furnish materials or equipment fabricated to a special design) proposed for the principal portions of the work. It is the preference of the Owner that, to the greatest extent possible or practical, the Contractor utilize Louisiana Subcontractors, manufacturers, suppliers and labor.
7.1.2 The General Contractor shall be responsible
for actions or inactions of Subcontractors and/or material suppliers.
The General Contractor is totally responsible for any lost time or extra expense incurred due to a
Subcontractor's or Material Supplier's failure to perform. Failure to perform includes, but is not limited to, a Subcontractor's financial failure, abandonment of the project, failure to make prompt delivery, or failure to do work up to standard. Under no circumstances shall the Owner mitigate the
General Contractor's losses or reimburse the General
Contractor for losses caused by these events.
7.1.3 The lowest responsive and responsible
bidder shall submit to the Architect and the Owner within ten days after the bid opening a letter/letters from the manufacturer stating that the manufacturer will issue the roof system guarantee complying with the requirements of Facility Planning and Control based on the specified roof system and include the name of the applicator acceptable to the manufacturer at the highest level of certification for installing the specified roof system. This manufacturer shall be one that has received prior approval or is named in the specifications.
In accordance with La. R.S. 38:2227 [references La
R.S. 38:2212(A)(3)(c)(ii), which has since been renumbered as La R.S. 38:2212(B)(3)], La. R.S.
38:2212.10 and La. R.S. 23:1726(B) the apparent low bidder on this project shall submit the completed Attestations Affidavit (Past Criminal
Convictions of Bidders, Verification of Employees and Certification Regarding Unpaid Workers
Compensation Insurance) form found within this bid package to the University of New Orleans within 10 days after the opening of bids.
ARTICLE 8
PERFORMANCE AND PAYMENT BOND
8.1 Bond Required
8.1.1 The Contractor shall furnish and pay for a
Performance and Payment Bond written by a company licensed to do business in Louisiana, which shall be signed by the surety's agent or attorney-in-fact, in an amount equal to 100% of the
Contract amount. Surety must be listed currently on
June 2024 IB -7 the U. S. Department of Treasury Financial
Management Service List (Treasury List) as approved for an amount equal to or greater than the contract amount, or must be an insurance company domiciled in Louisiana or owned by Louisiana residents. If surety is qualified other than by listing on the Treasury list, the contract amount may not exceed fifteen percent of policyholders' surplus as shown by surety's most recent financial statements filed with the Louisiana Department of Insurance and may not exceed the amount of $500,000. However, a Louisiana domiciled insurance company with at least an A- rating in the latest printing of the A. M.
Best's Key Rating Guide shall not be subject to the
$500,000 limitation, provided that the contract amount does not exceed ten percent of policyholders' surplus as shown in the latest A. M. Best's Key Rating
Guide nor fifteen percent of policyholders' surplus as shown by surety's most recent financial statements filed with the Louisiana Department of Insurance.
The Bond shall be signed by the surety's agent or attorney-in-fact. The Bond shall be in favor of the
State of Louisiana.
8.2 Time of Delivery and Form of Bond
8.2.1 The Bidder shall deliver the required bond to
the Owner simultaneous with the execution of the
Contract.
8.2.2 Bond shall be in the form furnished by the
University of New Orleans, entitled CONTRACT
BETWEEN OWNER AND CONTRACTOR AND
PERFORMANCE AND PAYMENT BOND, a copy of which is included in the Bid Documents.
8.2.3 The Bidder shall require the
Attorney-in-Fact who executes the required bond on behalf of the surety to affix thereto a certified and current copy of his power of Attorney.
ARTICLE 9
FORM OF AGREEMENT BETWEEN OWNER
AND CONTRACTOR
9.1 Form to be Used
9.1.1 Form of the Contract to be used shall be
furnished by the University of New Orleans, an example of which is bound in the Bid Documents.
9.2 Award
9.2.1 After award of the Contract, the successful
Bidder, if a corporation, shall furnish to the Owner the most current copy of a Disclosure of Ownership
Affidavit on file with the Secretary of State.
9.2.2 In accordance with Louisiana Law, when the
Contract is awarded, the successful Bidder shall, at the time of the signing of the Contract, execute the
Non-Collusion Affidavit included in the Contract
Documents
9.2.3 When this project is financed either partially
or entirely with State Bonds, the award of this
Contract is contingent upon the sale of bonds by the
State Bond Commission. The State shall incur no obligation to the Contractor until the Contract
Between Owner and Contractor is duly executed.
LOUISIANA UNIFORM PUBLIC WORK BID FORM
TO: University of New Orleans - Purchasing
Suite 1004, Room G
Administration Annex Building
2000 Lakeshore Drive
(Owner to provide name and address of owner)
BID FOR: UNO Engineering Annex Roof Replacement
University of New Orleans Main Campus
2000 Lakeshore Dr.
(Owner to provide name of project and other identifying information)
The undersigned bidder hereby declares and represents that she/he: a) has carefully examined and understands the Bidding
Documents, b) has not received, relied on, or based his bid on any verbal instructions contrary to the Bidding Documents or any addenda, c) has personally inspected and is familiar with the project site, and hereby proposes to provide all labor, materials, tools, appliances and facilities as required to perform, in a workmanlike manner, all work and services for the construction and completion of the referenced project, all in strict accordance with the Bidding Documents prepared by: Holly and Smith Architects and dated:
February 7, 2025.
(Owner to provide name of entity preparing bidding documents.)
Bidders must acknowledge all addenda. The Bidder acknowledges receipt of the following ADDENDA: (Enter the number the
Designer has assigned to each of the addenda that the Bidder is acknowledging) __________________________________________ .
TOTAL BASE BID: For all work required by the Bidding Documents (including any and all unit prices designated “Base Bid”
* but not alternates) the sum of:
Dollars ($ )
ALTERNATES: For any and all work required by the Bidding Documents for Alternates including any and all unit prices designated as alternates in the unit price description.
Alternate No. 1 (Add: High roof – removal and replacement) for the lump sum of:
Dollars ($_______________)
Alternate No. 2 (Add: building connector roof – removal and replacement) for the lump sum of:
Dollars ($ )
Alternate No. 3 (Owner to provide description of alternate and state whether add or deduct) for the lump sum of:
Not Applicable Dollars ($ Not Applicable)
NAME OF BIDDER:
ADDRESS OF BIDDER:
LOUISIANA CONTRACTOR’S LICENSE NUMBER:
NAME OF AUTHORIZED SIGNATORY OF BIDDER:
TITLE OF AUTHORIZED SIGNATORY OF BIDDER:
SIGNATURE OF AUTHORIZED SIGNATORY OF BIDDER **:
DATE: _______________________
THE FOLLOWING ITEMS ARE TO BE INCLUDED WITH THE SUBMISSION OF THIS LOUISIANA
UNIFORM PUBLIC WORK BID FORM:
* The Unit Price Form shall be used if the contract includes unit prices. Otherwise it is not required and need not be included with the form. The number of unit prices that may be included is not limited and additional sheets may be included if needed.
** A CORPORATE RESOLUTION OR WRITTEN EVIDENCE of the authority of the person signing the bid for the public work as prescribed by LA R.S. 38:2212(B)(5).
BID SECURITY in the form of a bid bond, certified check or cashier’s check as prescribed by LA R.S. 38:2218(A) attached to and made a part of this bid.
LOUISIANA UNIFORM PUBLIC WORK BID FORM
UNIT PRICE FORM
TO: University of New Orleans – Main Campus BID FOR: LPAC Bid No. ????
Purchasing Office University of New Orleans
Administration Annex, Room 1004G Engineering Annex Roof Replacement
New Orleans, Louisiana 70148 2000 Lakeshore Dr.
New Orleans, LA 70148
(Owner to provide name and address of owner) (Owner to provide name of project and other identifying information)
UNIT PRICES: This form shall be used for any and all work required by the Bidding Documents and described as unit prices. Amounts shall be stated in figures and only in figures.
DESCRIPTION: Base Bid or ❑ Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)
Additional Roof Plies
1 SF
DESCRIPTION: ❑ Base Bid or Alt.# 1 High Roof – removal and replacement
REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION (Quantity times Unit Price)
Additional Roof
DESCRIPTION: ❑ Base Bid or Alt.# 2 Building connector roof – removal and replacement
Additional Roof
DESCRIPTION: ❑ Base Bid or ❑ Alt.# ___
N/A N/A N/A N/A N/A
Wording for “DESCRIPTION” is to be provided by the Owner.
All quantities are estimated. The contractor will be paid based upon actual quantities as verified by the Owner.
BID BOND
Date:
KNOW ALL MEN BY THESE PRESENTS:
That of , as
Principal, and , as Surety, are held and firmly bound unto the State of Louisiana, University of New Orleans (Obligee), in the full and just sum of five (5%) percent of the total amount of this proposal, including all alternates, lawful money of the United
States, for payment of which sum, well and truly be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally firmly by these presents.
Surety represents that it is listed on the current U. S. Department of the Treasury Financial
Management Service list of approved bonding companies as approved for an amount equal to or greater that the amount for which it obligates itself in this instrument or that it is a Louisiana domiciled insurance company with at least an A - rating in the latest printing of the A. M. Best's Key Rating Guide. If surety qualifies by virtue of its Best's listing, the Bond amount may not exceed ten percent of policyholders' surplus as shown in the latest A. M. Best's Key Rating Guide.
Surety further represents that it is licensed to do business in the State of Louisiana and that this Bond is signed by surety's agent or attorney-in-fact. This Bid Bond is accompanied by appropriate power of attorney.
THE CONDITION OF THIS OBLIGATION IS SUCH that, whereas said Principal is herewith submitting its proposal to the Obligee on a Contract for:
NOW, THEREFORE, if the said Contract be awarded to the Principal and the Principal shall, within such time as may be specified, enter into the Contract in writing and give a good and sufficient bond to secure the performance of the terms and conditions of the Contract with surety acceptable to the Obligee, then this obligation shall be void; otherwise this obligation shall become due and payable.
PRINCIPAL (BIDDER) SURETY
BY: BY:
AUTHORIZED OFFICER-OWNER-PARTNER AGENT OR ATTORNEY-IN-FACT(SEAL)
July 2021
Document A201® – 2017 General Conditions of the Contract for Construction
Init.
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 16:58:20 CT on 02/07/2025 under Order No.4104243244 which expires on 02/27/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1986545997)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.
For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary Conditions.
for the following PROJECT:
(Name and location or address)
University Engineering Annex Roof Replacement University of New Orleans Main Campus 2000 Lakeshore Drive New Orleans, Louisiana Project Number: 01-107-24-05, F.01004598
THE OWNER:
(Name, legal status and address)
University of New Orleans – Main Campus Purchasing Office Administration Annex, Room 1004G New Orleans, Louisiana 70148
THE ARCHITECT:
(Name, legal status and address)
Holly & Smith Architects, APAC 2302 Magazine St.
New Orleans, Louisiana 70130 H/S Project No.: 24054
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 OWNER
3 CONTRACTOR
4 ARCHITECT
5 SUBCONTRACTORS
6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
7 CHANGES IN THE WORK
8 TIME
9 PAYMENTS AND COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 INSURANCE AND BONDS
12 UNCOVERING AND CORRECTION OF WORK
Init.
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 16:58:20 CT on 02/07/2025 under Order No.4104243244 which expires on 02/27/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1986545997)
13 MISCELLANEOUS PROVISIONS
14 TERMINATION OR SUSPENSION OF THE CONTRACT
15 CLAIMS AND DISPUTES
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 16:58:20 CT on 02/07/2025 under Order No.4104243244 which expires on 02/27/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1986545997)
INDEX
(Topics and numbers in bold are Section headings.)
Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3 Acceptance of Work 9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3 Access to Work 3.16, 6.2.1, 12.1 Accident Prevention Acts and Omissions 3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2 Addenda 1.1.1 Additional Costs, Claims for 3.7.4, 3.7.5, 10.3.2, 15.1.5 Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.4 Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6 Administration of the Contract 3.1.3, 4.2, 9.4, 9.5 Advertisement or Invitation to Bid 1.1.1 Aesthetic Effect 4.2.13 Allowances 3.8 Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10 Approvals 2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1 Arbitration 8.3.1, 15.3.2, 15.4
ARCHITECT
Architect, Definition of 4.1.1 Architect, Extent of Authority 2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1 Architect, Limitations of Authority and Responsibility 2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2 Architect’s Additional Services and Expenses 2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4 Architect’s Administration of the Contract 3.1.3, 3.7.4, 15.2, 9.4.1, 9.5 Architect’s Approvals 2.5, 3.1.3, 3.5, 3.10.2, 4.2.7
Architect’s Authority to Reject Work 3.5, 4.2.6, 12.1.2, 12.2.1 Architect’s Copyright 1.1.7, 1.5 Architect’s Decisions 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2 Architect’s Inspections 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4 Architect’s Instructions 3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2 Architect’s Interpretations 4.2.11, 4.2.12 Architect’s Project Representative 4.2.10 Architect’s Relationship with Contractor 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2 Architect’s Relationship with Subcontractors 1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3 Architect’s Representations 9.4.2, 9.5.1, 9.10.1 Architect’s Site Visits 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4 Asbestos 10.3.1 Attorneys’ Fees 3.18.1, 9.6.8, 9.10.2, 10.3.3 Award of Separate Contracts 6.1.1, 6.1.2 Award of Subcontracts and Other Contracts for Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements 1.1.1 Binding Dispute Resolution 8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1 Bonds, Lien 7.3.4.4, 9.6.8, 9.10.2, 9.10.3 Bonds, Performance, and Payment 7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5 Building Information Models Use and Reliance 1.8 Building Permit 3.7.1 Capitalization 1.3 Certificate of Substantial Completion 9.8.3, 9.8.4, 9.8.5
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 16:58:20 CT on 02/07/2025 under Order No.4104243244 which expires on 02/27/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1986545997)
Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4 Certificates of Inspection, Testing or Approval 13.4.4 Certificates of Insurance 9.10.2 Change Orders 1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2 Change Orders, Definition of 7.2.1
CHANGES IN THE WORK
2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5 Claims, Definition of 15.1.1 Claims, Notice of 1.6.2, 15.1.3
CLAIMS AND DISPUTES
3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4 Claims and Timely Assertion of Claims 15.4.1 Claims for Additional Cost 3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5 Claims for Additional Time 3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6 Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages 3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7 Claims Subject to Arbitration 15.4.1 Cleaning Up 3.15, 6.3 Commencement of the Work, Conditions Relating to 2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5 Commencement of the Work, Definition of 8.1.2 Communications 3.9.1, 4.2.4 Completion, Conditions Relating to 3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2
COMPLETION, PAYMENTS AND
Completion, Substantial 3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2 Compliance with Laws 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3
Concealed or Unknown Conditions 3.7.4, 4.2.8, 8.3.1, 10.3 Conditions of the Contract 1.1.1, 6.1.1, 6.1.4 Consent, Written 3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2 Consolidation or Joinder 15.4.4
CONSTRUCTION BY OWNER OR BY
SEPARATE CONTRACTORS
1.1.4, 6 Construction Change Directive, Definition of 7.3.1 Construction Change Directives 1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1 Construction Schedules, Contractor’s 3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2 Contingent Assignment of Subcontracts 5.4, 14.2.2.2 Continuing Contract Performance 15.1.4 Contract, Definition of 1.1.2
CONTRACT, TERMINATION OR
SUSPENSION OF THE
5.4.1.1, 5.4.2, 11.5, 14 Contract Administration 3.1.3, 4, 9.4, 9.5 Contract Award and Execution, Conditions Relating to 3.7.1, 3.10, 5.2, 6.1 Contract Documents, Copies Furnished and Use of 1.5.2, 2.3.6, 5.3 Contract Documents, Definition of 1.1.1 Contract Sum 2.2.2, 2.2.4, 3.7.4, 3.7.5, 3.8, 3.10.2, 5.2.3, 7.3, 7.4, 9.1, 9.2, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.5, 12.1.2, 12.3, 14.2.4, 14.3.2, 15.1.4.2, 15.1.5, 15.2.5 Contract Sum, Definition of 9.1 Contract Time 1.1.4, 2.2.1, 2.2.2, 3.7.4, 3.7.5, 3.10.2, 5.2.3, 6.1.5, 7.2.1.3, 7.3.1, 7.3.5, 7.3.6, 7, 7, 7.3.10, 7.4, 8.1.1, 8.2.1, 8.2.3, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 12.1.2, 14.3.2, 15.1.4.2, 15.1.6.1, 15.2.5 Contract Time, Definition of 8.1.1
CONTRACTOR
Contractor, Definition of 3.1, 6.1.2 Contractor’s Construction and Submittal Schedules 3.10, 3.12.1, 3.12.2, 4.2.3, 6.1.3, 15.1.6.2
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 16:58:20 CT on 02/07/2025 under Order No.4104243244 which expires on 02/27/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1986545997)
Contractor’s Employees 2.2.4, 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.3, 14.1, 14.2.1.1 Contractor’s Liability Insurance 11.1 Contractor’s Relationship with Separate Contractors and Owner’s Forces 3.12.5, 3.14.2, 4.2.4, 6, 11.3, 12.2.4 Contractor’s Relationship with Subcontractors 1.2.2, 2.2.4, 3.3.2, 3.18.1, 3.18.2, 4.2.4, 5, 9.6.2, 9.6.7, 9.10.2, 11.2, 11.3, 11.4 Contractor’s Relationship with the Architect 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5.1, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.4, 15.1.3, 15.2.1 Contractor’s Representations 3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2 Contractor’s Responsibility for Those Performing the Work 3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8 Contractor’s Review of Contract Documents 3.2 Contractor’s Right to Stop the Work 2.2.2, 9.7 Contractor’s Right to Terminate the Contract 14.1 Contractor’s Submittals 3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3 Contractor’s Superintendent 3.9, 10.2.6 Contractor’s Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 7.3.6, 8.2, 10, 12, 14, 15.1.4 Coordination and Correlation 1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1 Copies Furnished of Drawings and Specifications 1.5, 2.3.6, 3.11 Copyrights 1.5, 3.17 Correction of Work 2.5, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2, 12.3, 15.1.3.1, 15.1.3.2, 15.2.1 Correlation and Intent of the Contract Documents 1.2 Cost, Definition of 7.3.4 Costs 2.5, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.4, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.2, 12.1.2, 12.2.1, 12.2.4, 13.4, 14 Cutting and Patching 3.14, 6.2.5
Damage to Construction of Owner or Separate Contractors 3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damage to the Work 3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damages, Claims for 3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.3.2, 11.3, 14.2.4, 15.1.7 Damages for Delay 6.2.3, 8.3.3, 9.5.1.6, 9.7, 10.3.2, 14.3.2 Date of Commencement of the Work, Definition of 8.1.2 Date of Substantial Completion, Definition of 8.1.3 Day, Definition of 8.1.4 Decisions of the Architect 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.4.2, 14.2.2, 14.2.4, 15.1, 15.2 Decisions to Withhold Certification 9.4.1, 9.5, 9.7, 14.1.1.3 Defective or Nonconforming…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .