5-Parkways Mill Overlay Maps.pdf

PDF 883 KB Posted

Attached to
Mill and Overlay (5 Locations) for Milwaukee County Highway Department
Solicitation number
ITB-2026-Mill and Overlay (5 Locations) for Milwaukee County Highway Department
Issued by
Milwaukee County, Mattoon Village, Wisconsin

About this file

This overlay map document supports a Mill and Overlay project for the Milwaukee County Highway Department involving road resurfacing work at five locations across Milwaukee County, Wisconsin. The project encompasses two County Trunk Highway (CTH) roads and three parkway locations. The CTH work includes W. Silver Spring Drive, extending approximately 250 feet west of N. 103rd Street eastward to N. 95th Street (both lanes), and W Beloit Road, beginning approximately 100 feet west of S. Wollmer Street and extending east to S. 103rd Street (both lanes). The three parkway projects, typically 26 feet wide, include Oak Creek Parkway near Grant Park (beginning at Mill Road in South Milwaukee and extending approximately 50 feet north of the trail crossing), Whitnall Park Drive near Boerner Botanical Gardens (from the entrance at the Boerner Parking Lot to the next parkway intersection), and Park Drive at Greenfield Park (beginning at Lincoln Avenue and extending approximately 175 feet south before the parking lot entrance to Picnic Area 3A). An optional on-site bidders meeting was scheduled for Thursday, April 9, at 11:00 AM, with a site visit order beginning at W. Silver Spring Drive (10310 W Silver Spring Drive, Milwaukee, WI 53225) and proceeding to locations 5, 2, 4, and 3.

The overlay maps provided in this document visually depict the specific project boundaries and locations for each of the five work areas, serving as reference materials for bidders to understand the scope and extent of the milling and overlay work required at each site.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project to begin at Mill Rd & E Oak

Creek Pkwy in South Milwaukee.

Project #3 Parkway: Oak Creek Pkwy near Grant Park

Project to end approximately 50ft north of the trail crossing

Project #4 Parkway: Whitnall Park Dr near Boerner Botanical Gardens

Project will begin at the Entrance to Whitnall

Park Drive from the Boerner Parking Lot

Project will end at the next Parkway intersection.

Project #5 Parkway: Park Dr. at Greenfield Park

Project at the Lincoln Ave Entrance

Project will end approximately 175ft from the entrance of the parkinglot

File details come from the government source that posted it. Updated .