5-JOC-WO-Template.pdf

PDF 248 KB Posted

Attached to
RFP Phase 1: Job Order Contract (JOC) - Statewide
Solicitation number
J26-01 & J26-02
Issued by
Washington

About this file

This is a Work Order Form template used by the Washington State Department of Enterprise Services (DES) for administering Job Order Contract (JOC) work requests within the statewide JOC program. The form serves as the primary document for requesting and authorizing individual work orders under an existing JOC agreement. The template captures essential project information including work title, location, desired start date, substantial completion date, and schedule requirements with provisions for liquidated damages. The form requires identification of the funding agency, JOC project manager, cost engineer contact information, and detailed scope of work descriptions with supporting sketches, plans, and photographs. Special requirements sections address design specifications, dimensions, quantities, materials, finishes, and component types or brands. The form includes fields for modification requests with specific change reasons including design errors, design omissions, latent conditions, code requirement changes, and value engineering proposals.

The pricing structure is organized by CSI divisions with line-item entries capturing bare costs, material prices, labor hours, unit labor prices, overhead and profit (OH&P), and total item prices. The form accommodates both items listed in the unit price book and items not listed in the price book, with the latter limited to no more than twenty percent of the total work order value. Additional provisions address apprenticeship requirements per RCW 39.10.450(8) for work orders exceeding $350,000 and 600 single trade man-hours, hazardous material abatement insurance requirements, and Washington State sales tax calculations. Authorization occurs upon signature by the Agency Project Manager (APM) and includes fields for notice to proceed dates and contractor coefficient documentation.

View the file

Other files

File Type Posted
8-C-BidProposalAndForm.pdf PDF
2-E-SampleForms.pdf PDF
1-F-PointofContact.docx DOCX document
6-J26 JOC Manual Final.pdf PDF
7-J26-01 J26-02-RFP.pdf PDF
3-A-DiverseBusinessInclusionPlanCriteria.pdf PDF
4-B-InstructionsToJOCBidders.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DES Work Order Form

Work Title:

Location*:

Section 1: Work Order Request

Date of Request:

Schedule of Work: Desired start date, substantial completion date, other dates that are required by Agency/Requester*

* Include Liquidated Damages as part of Schedule of Work if they are to be applied to this Work Request

CONTRACT TIME:

FPS Management

Approval of change in contract time Initials Date

Special Requirements: Design requirements, dimensions, quantities, materials, finishes, component types or brands

Contacts Phone Agency

JOC Project Manager

Owner/DES PM

Cost Engineer 360 280 2781 page 1 revised Oct 17, 2025

Brief Description of Work: Agency/Requester requirements consisting of an overall statement of work and objectives. Attach any sketches, plans, and/or photos, exclusions, and a detailed Scope of Work

□ Increase □ Decrease Calendar Days

JOC Contractor Ref.:

Other Agency Ref.:

Work Order No.:*include zip code of work location

Funding Agency:

A/E for this Work Order:

Apprenticeship RCW 39.10.450 (8) Conditions apply for Apprenticeship (WO >$350k & >600 Single Trade Man Hours)

Apprenticeship n/a

Brian Thomas

Organization Email Name

DES brian.thomas@des.wa.gov

Modification No.:

Job Order Contract No.:

DES Project No.:

MODIFICATION REASON FOR CHANGE: □Design Errors □Design Omissions □Agency □Latent Conditions □Code Req. □Value Engineering

A/E not utilized

Scope includes hazardous material abatement and associated Insurance Requirements (JOC Manual Section 2.02.B.5)

Hazardous Waste

Work Title:

Location*:

*include zip code of work location

Funding Agency:

Date of Proposal:

Completion (Days from NTP): JOC Firm:

Liquidated Damages:

CSI or item #

Bare Cost Total

City Cost Index

Division Total Price

-$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00 -$ $0.00

$0.00

Item No

Units Qty Unit Material

Price Labor Hours

Unit Labor Price

OH&P Item Price

1 -$ -$ -$ 2 -$ -$ -$ 3 -$ -$ -$ 4 -$ -$ -$ 5 -$ -$ -$

$0.00

$0.00

$0.00

Date:

revised Oct 17, 2025

DES Project No.:

DES Work Order Form

JOC Contractor Ref.:

Other Agency Ref.:

Work Order No.:

Job Order Contract No.:

Total of all base items listed is Price Book:

Labor Materials

Work Order Items Not Listed in Unit Price Book (This cannot exceed 20% of the total work order.)

FPS Management All originals and Mods > $10k)

Project Manager

Client Authorized Funding

JOC Contractor

Cost Engineer

Total Funding Amount

Total Work Order/Modification Amount

Tax Rate

Previous Work Order Total

Brief Description of Work: additional information can be found on the attached Scope of Work or on page 1

Modification No.:

CSI / Summary of Work Order Items Listed in Unit Price Book

Notice to Proceed (NTP) DATE ____________

Washington State Sales Tax

Work Item Description: Include type of material, manufacture name, part number, type of work…

Total of all items not listed in Price Book

Description of Base Bid Items

Approved signatures

Note: 1: This Work Order Proposal becomes an authorized Work Order when signed by APM.

Contractor Coefficient

File details come from the government source that posted it. Updated .