This combined synopsis and solicitation requests quotes for construction technical inspection services. The Colorado Air National Guard seeks to issue a firm fixed price contract for five years to provide inspection of maintenance and construction projects at Buckley Air Force Base. Over the past five years, the agency has averaged four to six projects annually valued at approximately $12 million total. Services include inspection of aircraft maintenance facilities, range control structures, corrosion control, and space control facilities. Quotes are due by September 15, 2020 and pricing must remain valid for 120 days thereafter. The solicitation is set aside exclusively for small businesses with a size standard of $16.5 million. Offerors must demonstrate employee qualifications and provide past performance from relevant government contracts within the past five years to be evaluated.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Workload/Level of Effort

13 August 2020

The lists below represent the number of projects, with their project titles and disclosures of magnitude for each of the last five years. These numbers reflect the typical workload expected for the next five years in the 140th COANG. Some projects may be listed in multiple years, because their period of performance bridges fiscal years, or spans more than one year in length.

Over the course of 5 years, we expect to have 4-6 active projects per year, with a total yearly value averaging about $12,000,000.

2015:

1. ASE Maintenance Facility Type A- $100,000 to $250,000

2. Range Control Construction- $1,000,000 to $5,000,000

3. ASE Maintenance Facility Type B- $250,000 to $500,000

4. Range Control Type C- $100,000 to $250,000

2016:

1. Range Control Construction- $1,000,000 to $5,000,000

2. ASE Maintenance Facility Type A- $100,000 to $250,000

3. ASE Maintenance Facility Construction- $5,000,000 to $10,000,000

2017:

1. Range Control Construction- $1,000,000 to $5,000,000

2. Space Control Facility Design- $500,000 to $1,000,000

3. Corrosion Control Design- $500,000 to $1,000,000

2018:

1. Space Control Facility Design- $500,000 to $1,000,000

2. Corrosion Control Design- $500,000 to $1,000,000

3. Range Control Construction- $1,000,000 to $5,000,000

4. ASE Maintenance Facility Construction- $5,000,000 to $10,000,000

2019:

1. ASE Maintenance Facility Construction- $5,000,000 to $10,000,000

2. Space Control Facility Construction- $5,000,000 to $10,000,000

2020:

1. ASE Maintenance Facility Construction- $5,000,000 to $10,000,000

2. Space Control Facility Construction- $5,000,000 to $10,000,000