This solicitation is for the replacement of the Lower Cow Creek Bridge located on the Sierra National Forest in Fresno County, California. The project includes demolishing the existing bridge and constructing a new bridge with precast concrete slabs, approach railings, guard rails, retaining walls, asphalt paving, and erosion control work. The estimated price range for the project is between $250,000 and $500,000, with a performance period of 120 days. Requests for additional information are due by April 30, 2020 and sealed bids for the project are due to the USDA Forest Service Pacific Southwest Region by May 14, 2020. The opportunity is set aside for total small business participation.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section – C 1
LOWER COW CREEK BRIDGE REPLACEMENT PROJECT
Sierra National Forest
Fresno County
SECTION C-DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK
C.1 DESCRIPTION OF WORK
The project includes all labor, materials, equipment, supplies, supervision and incidentals necessary for the replacement of the Lower Cow Creek Bridge located on the High Sierra Ranger District. The work includes but is not limited to: Construction of a bridge with precast, pre-stressed, voided concrete slabs, including railings and other associated parts. Approach guard rails, gabion retaining wall, object markers, asphalt paving at approaches. The project also includes the demolition and removal of the existing glulam stringer bridge, dewatering and erosion control.
All work shall be in accordance with the contract requirements and within the contract time of 120 days.
Contractor shall, without additional expense to the government, be responsible for obtaining any necessary licenses, permits, which comply with any federal, State and municipal laws, codes and regulations applicable to the performance of the work.
C.2 APPLICABLE SPECIFICATIONS AND DRAWINGS
In addition to the specifications which are part of the base contract, the following specifications and drawings apply:
a. Project Plans, drawing sheets R-1679-01 - R-1679-08.
b. Sierra NF Fire Plan dated August 2013.
A detailed “Work Schedule Plan” and “Traffic Plan” will be required prior to start of work.
a. Shop Drawings and Submittals:
The following submittals shall be submitted for approval:
Title Referenced by
Specification No.
Copies to
Submit
Time Allowed for
Government Review After
Submittal
TRAFFIC CONTROL PLAN 156 2 14
EROSION CONTROL PLAN 157 2 14
GABION BASKET 253 2 14
ASPHALT CONCRETE 403 2 14
STRUCTURAL CONCRETE 552 2 21
PRECAST CONCRETE
VOIDED SLABS
553 2 21
REINFORCING STEEL 554 2 21
BRIDGE RAILING 556 2 21
ELASTOMERIC BEARING
DEVICE
564 2 14
GEOCOMPOSITE SHEET
DRAIN
605 2 14
APPROACH RAILING 617 2 21
OBJECT MARKERS, TYPE 3 633 2 14
Section – C 2
b. General Guidelines for Submittals:
Submittals are required by their corresponding specifications (basis reference & detailed requirement).
Work Required submittals shall not begin until submittals have been approved.
Submittals shall include the following:
• Date and Revision Dates
• Project Name and Contract Number
• Names of Contractor, Subcontractor, Supplier, and Manufacturers
• Field Dimensions and Relation to Adjacent Structures
• Contractor’s Stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents
Samples:
Physical samples shall illustrate materials, equipment, or workmanship, and establish standards by which completed work shall be judged. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of product or material, with integrally related parts and devices.
Manufacturer’s Requirements:
Supply manufacturer’s catalog sheets or brochures with diagrams, schedules, or performance charts.
Illustrations shall be clearly marked to identify pertinent materials or models, dimensions, and clearances required. Supplement standard drawings to provide information unique to this project.
Approval or Rejection Time Allowance:
Submittals will be reviewed and either approved or rejected within a minimum of 14 calendar days of their receipt by the Contracting Officer or COR.
C.3 PROJECT LOCATION
The project is located on the High Sierra Ranger District of the Sierra National Forest. From Fresno, CA get onto State Route 168 and continue east on State Route 168 for 32.1 miles. Turn left at the three-way intersection to stay on State Route 168 and proceed for 14.5 miles and turn right onto Dinkey Creek Rd.
Continue on Dinkey Creek Rd. for approximately 9.1 miles and turn left onto Rock Creek Road (9S09) and proceed for 6.0 miles and turn right onto 9S10, proceed on 9S10 for 1.3 miles to the project location.
C.4 CONTRACT TIME
Estimated start work date is June 1, 2020. The contract time will be 120 days. Contract time includes delays for weather; locating and transporting supplies and materials; and final site cleanup.
C.5 PROJECT SITE CLEAN UP
Project site cleanup includes the removal and proper disposal of all construction trash, debris, and residue off of National Forest Land.
All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed according to all Local, State, and Federal rules, regulations, and laws governing such disposal.
During the Work the Contractor is required to furnish dumpsters or other trash receptacles and to empty such containers either as they become full or weekly, whichever is more frequent. The Contractor shall not place materials of any kind into private or Government trash bins or dumpsters.
C.6 PRICE RANGE
The price range of this project is between $250,000 and $500,000.
Section – C 3
C.7 SPECIAL CONDITIONS AFFECTING THE WORK
a. Physical Conditions. The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys performed by the Government.
b. Weather. Average low temperatures at the project sites range from temperatures of less than 37
ºF in December and January to lows of 66 ºF in July and August. Average high temperatures range from 57 ºF in December and January to over 98 ºF in July and August. The annual precipitation at the project sites varies from less than 12 inches per year including snow fall in the valley to several feet of snow in the mountains. Winter snow storms and freezing temperatures will occur during the winter months that result in a winter project shutdown at higher elevations.
Icy conditions on local roads and highways can occur during the fall, winter and spring. Highway curves in shaded areas will remain covered with ice or frost for weeks.
c. Work Hours. Work hours are from 7:00 am to 5:00 pm Monday through Friday. Weekend equipment work is not allowed at any time during the Work. Dogs and pets are not allowed on the project site at any time.
d. Safety, Emergency Communications and Evacuation. Contractor is responsible for the safety of the Contractor’s employees including Subcontractors employees, Government employees associated with the project, and any visitors to the site both Government and private. The
Contractor shall submit a project safety plan to the Contracting Officer for review prior to commencement of Work. The project safety plan shall comply with the appropriate California
OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.
e. Highway Permits. Contractor is responsible for securing any overload or over width limit permits required for the transport of materials or equipment to the project site. The Contractor is responsible for conducting a thorough reconnaissance of all routes leading to the site.
f. Toilets. No toilet or shower facilities are available on site. Contractor shall provide toilet facilities for its employees.
g. Camping. Contractor may use a self-contained travel trailer or recreational vehicle to camp on
National Forest System lands near the project sites subject to the approval of the Contracting
Officer. All waste material must be transported off-site to a station equipped to handle such waste.
h. Security. Contractor is responsible for the Contractor’s equipment and materials supplied to the site. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools and other equipment shall be secured at the end of each working day. On Fridays all construction debris, trash, and refuse shall be properly stored in dumpsters or trash bins or removed from the site.
i. Burning Permits. Contractor is subject to all rules and regulations governing the on site burning of slash and other debris. Contractor shall obtain a burning permit from the jurisdiction having control over burning. The Contractor shall comply with Fire Plan for Construction and Service
Contracts included in the Contract.
j. Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site to remove weeds, mud, grease and oil buildup from the tires, wheels, tracks, engines and engine compartments, and other surfaces. Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with all applicable rules, Section – C 4 regulations and laws. Contractor shall submit a project spill response plan at the pre-work meeting for review by the Contracting Officer.
C.8 EQUIPMENT CLEANING
Unless the entire project area is already infected with noxious weeds, the contractor shall ensure that prior to moving on to another part of the project area all off-road equipment, which last operated in areas known by Forest Service to be infected with noxious weeds, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Contractor shall certify in writing that off-road equipment is free of noxious weeds prior to each start-up of operations and for subsequent moves of equipment to other project areas. Measures taken to ensure that off-road equipment is free of noxious weeds will be identified. “Off-road equipment” includes all equipment operating off of paved roadways. A Current list of noxious weeds of concern to Forest Service is available at the Forest Supervisor’s office. Contractor shall clean off-road equipment prior to moving between project areas with known infestations with noxious weeds and other project areas, if any, which are free of such weeds. Project area maps show areas known by Forest Service that contain specific noxious weeds species of concern. Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required. Contractor shall notify Forest Service at least 24 hours prior to beginning of work in area designated as a noxious weed area, unless otherwise agreed. Notification shall include the location of the equipment’s most recent operations. If the prior location of the off-road equipment cannot be identified, forest service may assume that it was infested with noxious weed seeds. Upon request of Forest Service, Contractor must arrange for forest Service to inspect each piece of off-road equipment prior to it being placed into service. If Contractor desires to clean off-road equipment on national forest land, such as at the end of a project or prior to moving to a new unit that is free from noxious weeds, Contractor and
Forest Service shall agree on methods of cleaning, locations for the cleaning, and control of off-site impacts, if any. New infestations of noxious weeds, of concern to Forest Service and identified by either
Contractor or Forest Service, within the project area or on the haul route, shall be promptly reported to the other party.