5-23-011Change Order Notice V.25.1.pdf
PDF 1 MB Posted
- Solicitation number
- 26-422DNR-REALT-B-52352
- Issued by
- Illinois
About this file
This is a Change Order Notice issued by the Illinois Department of Natural Resources (IDNR) for the Fox Creek Wetland Berms Rehabilitation project. The change order modifies an existing contract to address project modifications and scope adjustments necessary to complete the wetland restoration work as originally intended.
The contract value has been increased from $188,000.00 to $230,419.56, representing an additional investment of $42,419.56 to accommodate changes germane to the original contract scope. This adjustment reflects modifications required during project execution to ensure proper completion of the wetland berm rehabilitation objectives at the Fox Creek site.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| CurrentPage: |
| PageCount: |
| DropDownList1: DNR - Natural Resources |
| ProcurementTitle: DNR Fox Creek - Rehabilitate Wetland Berms |
| BBREFNO.: 26-422DNR-REALT-B-52352 |
| thedetails: This project consists of rehabilitating two existing earthen wetland berms at the Fox Creek State Fish and Wildlife Area in Wayne County; original purchase order #26-422DNR-REALT-P-92125. This Change Order proposes an increase of $42,419.56 for additional work necessary to complete the project. Added work consists of three components: dewatering of north impoundment area that was originally to be completed by DNR prior to construction; installation of DNR purchased water control structure at north impoundment; purchase/installation of large aluminum water control structure for south impoundment. |
| CheckBox1: 0 |
| CheckBox2: 1 |
File details come from the government source that posted it. Updated .