4PA0480 USAO Allentown Post Award Schedule.pdf
PDF 76 KB Posted
- Attached to
- Lease of Office Space within Region 3. Request for Lease Proposals (RLP) #25REG00 – 4PA0480 Office Space
- Solicitation number
- 4PA0480
About this file
This document is a Post-Award Schedule attachment for a federal lease solicitation (4PA0480) for office space in Allentown, Pennsylvania. The schedule outlines a detailed timeline for post-lease award activities, including a 10-working day design kick-off meeting, 30 days for design intent drawings, 45 days for construction document preparation, 20 days for tenant improvement and building specific amortized capital (BSAC) price proposal submission, and 75 days for lessor completion of construction work. The total timeline from lease award to space acceptance is approximately 180 working days, with specific milestones for design, documentation, pricing, and construction progression.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Delineated Area Map ad attachment.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Design Kick Off Meeting 10
Lessor-Provides Design Intent Drawings 30
Lessor Preparation and Submission of Construction Documents 45
Lessor Preparation and Submission of the TI and BSAC Price Proposal 20
Lessor Completes Construction of TIs and Completion of Other Required Construction Work 75