This is a federal contract and procurement package for a Vacuum Furnace System to be supplied to Brookhaven National Laboratory (BNL), operated by Brookhaven Science Associates (BSA), a contractor to the U.S. Department of Energy (DOE). The contract number is 481391, designated as Firm Fixed Price, with BSA's contractual representative Jayce Blood serving as the primary point of contact. The overall contract value amount, payment terms, and final price are marked as "TBD" and subject to finalization. The furnace will serve as an addition to the NSLS-II Vacuum Processing Facility to perform vacuum brazing, annealing, and firing of components for ultra-high vacuum environments supporting NSLS-II operations and other BNL projects including the EIC project.
The contract specifies key milestones with due dates: Preliminary Design Review at 5 weeks, Final Design Review at 10 weeks, Acceptance Testing at Contractor's facility at 30 weeks, and Receipt of Equipment at BNL at 36 weeks after contract execution. Payment will be made in four installments upon BSA receipt and acceptance of deliverables: Preliminary Design Review, Final Design Review, factory acceptance testing, and the complete Vacuum Furnace System. The Statement of Work (Attachment A, dated July 16, 2026) and Technical Specification (Attachment B, NSLSII-VAC-SPC-003, dated July 16, 2026) define comprehensive requirements including a horizontal double-wall vacuum chamber rated to 1200°C, multi-zone heating elements with independent control, high-vacuum pumping system achieving <2×10⁻⁷ Torr, argon gas cooling system, PLC-based control with HMI display, and complete safety interlock systems. The furnace must meet industry standards including NFPA 86, AMS 2750, ASME Section VIII, and UL 508A. Supplier Quality Assurance Requirements (BNL-QA-101) mandate ISO 9001 compliance, configuration management, Manufacturing/Inspection/Test Plans, Factory Acceptance Testing documentation, and comprehensive quality controls. Freight terms are Freight Prepaid FOB Destination or DAP to Brookhaven National Laboratory, 98 Rochester Street, Upton, New York, with detailed packing, labeling, and shipping notification requirements specified. Electronic invoice submission is preferred to apinvoices@bnl.gov, with hard copies directed to BSA's Accounts Payable Department. The contractor is responsible for all tooling, fixtures, test equipment, spare parts, documentation, and operator training. Warranty coverage extends two years from final acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.1 Enclosure 4 Form W-9.pdf | ||
| B.1 Request for Quote.pdf | ||
| B.1 Enclosure 3 Form W-8.pdf | ||
| B.1 Enclosure 2 AMS-Form-050.pdf | ||
| B.1 Enclosure 6 Quotation Pricing Sheet.docx | DOCX document | |
| B.1 Enclosure 7 AMS-Form-001, Subcontracting Plan Waiver.docx | DOCX document | |
| B.1 Enclosure 5 Vendor ACH Authorization Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 9, 2025 1 Rev. 10
BSA’s Contractual Representative
Overall Value Amount
Contract Type Contract Number
Jayce Blood TBD Firm Fixed Price 481391
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor
CONTRACT
This Contract (the “Contract”) is between the party named above (the “Contractor”), and Brookhaven Science Associates, LLC (“BSA”), the latter acting under a Prime Contract, DE- SC0012704, with the United States of America (the “Government”) represented by the United States Department of Energy (“DOE”).
I. SCOPE OF WORK
The Contractor shall provide a Vacuum Furnace System to serve as an addition to the NSLS-II Vacuum Processing Facility.
All work shall be conducted in strict accordance with the attached Statement of Work and Technical Specification documents, Attachment A and B respectively.
A. Deliverables: The Contractor shall provide the all deliverables identified within
Attachment A, Statement of Work, to BSA’s Technical Representative.
II. PERIOD OF PERFORMANCE
This Contract shall be effective as of the date executed by both parties. It shall remain in effect through TBD.
Scheduled Milestone Due Date
1. Preliminary Design Review 5 weeks after date of contract
2. Final Design Review 10 weeks after date of contract
3. Acceptance test at Contractor’s facility 30 weeks after date of contract
4. Receipt of equipment at BNL 36 weeks after date of contract
III. FIRM FIXED PRICE AND PAYMENT
A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder, BSA shall pay the Contractor the firm fixed price of TBD U.S. Dollars ($TBD).
The said sum shall constitute full compensation for all services and materials
April 9, 2025 2 Rev. 10 furnished hereunder.
B. Payment: Payment will be made upon receipt and approval of properly certified invoices. Payment will be in accordance with the following deliverable payment schedule:
Description Amount BSA receipt and acceptance of the Preliminary Design Review.
TBD
BSA receipt and acceptance of the Final Design Review.
BSA receipt and acceptance of the factory acceptance testing.
BSA receipt and acceptance of the Vacuum Furnace System.
Payment terms are Net TBD.
Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail.
Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal.
Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov.
Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D.
The Contractor shall indicate the final invoice by clearly marking such invoice as “FINAL.” A copy of the final invoice must be submitted to BSA’s Contractual Representative.
C. Freight: Freight terms shall be:
Freight Prepaid, FOB Destination, Brookhaven National Laboratory, 98 Rochester Street, Upton, Long Island, New York.
- OR -
Freight Prepaid, “DAP” Delivered At Place, Brookhaven National Laboratory, 98 Rochester Street, Upton, Long Island, New York.
D. Labelling, Packing, and Notification Requirements:
More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.
Labeling Requirements mailto:apinvoices@bnl.gov https://www.bnl.gov/shipping/ mailto:WarehouseOperations@bnl.gov
April 9, 2025 3 Rev. 10
All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:
Brookhaven National Laboratory Brookhaven’s Contract Number 98 Rochester St.
Upton, NY 11973 Box Number / Number of Boxes
Packing List Requirements
Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:
• Ship from company name and address
• Supplier contact name
• Supplier telephone number
• Ship to address as instructed by Buyer/Contracts Specialist
• Brookhaven’s Contract number
• Part number, description, quantity, unit of measure, and corresponding BNL
Contract line number
Special Notification of Delivery
If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall provide a minimum of 3 days’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received. Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.
Marking of Outer Package
Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.
Protection of Material and Equipment
The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage. Such protection https://www.astm.org/Standards/D3951.htm
April 9, 2025 4 Rev. 10 shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951-10, Standard Practice for Commercial Packaging.
Unacceptable Packing Material
Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.
Ocean Shipments
Foreign shipments transported via ocean freight must use the 10+2 REQUIREMENTS Form (PDF). The form must be completed by the Contractor 72 hours before departure of the vessel. Send form to the following:
Interfreight Harmonized Logistics, Inc.
Fax: 516-371-6880 bnl@interfreight.net
Brookhaven National Laboratory WarehouseOperations@bnl.gov
Once the form is submitted to customs, an acceptance number will be provided.
Freight will not be loaded onto a vessel without an acceptance number. Failure to submit the 10+2 form may result in fines. It is the Contractor's responsibility to make sure the 10+2 form is submitted 72 hours prior to the vessel sailing. BSA shall withhold payment from the Contractor's final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor.
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative: TBD, telephone no. TBD, TBD (email), is BSA's Technical Representative, and shall act as liaison between BSA and the Contractor in technical matters only.
B. BSA’s Contractual Representative: Jayce Blood, telephone no. (631) 344-
2627, jblood@bnl.gov (email), is BSA's Contractual Representative. Any change or modification in the terms and conditions of this Contract shall require the https://www.astm.org/Standards/D3951.htm https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf mailto:bnl@interfreight.net mailto:jblood@bnl.gov
April 9, 2025 5 Rev. 10 written approval of BSA's Contractual Representative or designee.
C. Contractor’s Technical Representative: TBD, telephone no. TBD, TBD (email), is the Contractor’s authorized Technical Representative, and shall act as point of contact between BSA and the Contractor in technical matters only.
D. Contractor’s Contractual Representative: TBD, telephone no. TBD, TBD
(email), is the Contractor’s authorized Contractual Representative and shall act as liaison between BSA and the Contractor.
V. RESERVED
VI. RESERVED
VII. ADDITIONAL TERMS
The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Commercial Items and Services, (Rev.25 and Sep 2026) are incorporated herein and made a part hereof.
Article 18 entitled “Warranty” is modified to reflect a two (2) year warranty. The contractor shall warranty the equipment against failure and defects for a period of two (2) years from final acceptance by BSA.
This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental Terms and Conditions listed above, which are incorporated herein by reference. The complete text of these terms and conditions can be viewed at PPM | Terms and Conditions. Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Buyer or Contracts Specialist immediately.
The following documents attached hereto and made a part hereof, contain additional provisions of this Contract:
Attachment A: Statement of Work, dated July 16, 2026 Attachment B: Specifications, dated July 16, 2026 Attachment C: BNL QA 101
This Contract does not bind nor purport to bind the Government of the United States.
ACCEPTED:
TBD BROOKHAVEN SCIENCE ASSOCIATES,
LLC
By: _______________________________ By: ____________________________________
Name: ____________________________ Name: __________________________________
Title: _____________________________ Title: ___________________________________
Date: _____________________________ Date: ___________________________________ https://www.bnl.gov/ppm/terms-and-conditions.php https://www.bnl.gov/ppm/terms-and-conditions.php
April 9, 2025 6 Rev. 10
Should you accept this Contract without exception or alteration, a copy of the Contract shall be returned to BSA's Contractual Representative. Should you take any exceptions or attempt to alter the Contract in any manner, BSA’s execution thereof shall be null and void. Should you wish to take exception(s)/alteration(s), you shall notify BSA’s Contractual Representative. BSA will consider the requested exception(s)/alteration(s) and notify you accordingly. No Contract shall exist unless and until such differences are resolved.
Brookhaven National Laboratory Number: NSLSII-VAC-SOW-004 Brookhaven Science Associates Version: 1 National Synchrotron Light Source II (NSLS-II) Effective: 16JUL2026
STATEMENT OF WORK
For the
Vacuum Furnace System QA Category: A-2
Name Title Approver/Reviewer King Wilson NSLS-II Vacuum Engineer Approver Robert Todd NSLS-II Vacuum Group Leader Approver Nicole Magliulo NSLS-II QA Engineer Approver Robert Lee NSLS-II ESH Manager Approver Timur Shaftan NSLS-II Accelerator Division Director Approver Steve Sherwood NSLS-II Liaison Engineer Approver Jake Hawkes NSLS-II Project Management Approver Additional Staff Not Approving Through SharePoint Lacy Jones NSLS-II Operations Engineer (Export Control) Reviewer Jayce Blood Manager, Subcontracts, PPM Procurement Reviewer
This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR Parts 730-774 as EAR99 Technology.
ii National Synchrotron Light Source II
Version 1 ii Brookhaven National Laboratory
VERSION CONTROL SHEET
VERSION DESCRIPTION DATE AUTHOR APPROVED BY
1 First Issue 16 JUL 2026 K. Wilson See cover page.
NSLSII-VAC-SOW-004: NSLS-II Vacuum Furnace System SOW iii
National Synchrotron Light Source II iii 16 JUL 2026
CONTENTS
1 INTRODUCTION AND OVERVIEW
1.1 Background
1.2 Definitions
1.3 Scope
2 REFERENCES
3 REQUIREMENTS
3.1 Contractor Responsibilities
3.1.1 Technical Performance
3.1.2 Tooling/Fixtures/Test Equipment
3.1.3 Spare Parts/Special Tools
3.2 Engineering Analysis: Design and Design Review Requirements
3.2.1 Detailed Analysis Requirements
3.2.2 Detailed Design Requirements
3.2.3 Manufacturing, Inspection and Test Requirements
3.2.4 Acceptance Test Procedures
3.3 Management
3.3.1 Program Plan
3.3.2 Progress Teleconference
3.3.3 Manufacturing/Inspection/Test Plan
3.3.4 Performance Reporting
3.4 Documentation and Data Management
3.4.1 General documentation Requirements
3.4.2 Drawing and Model File Format Requirements
3.4.3 End Item Documentation
3.5 Configuration Management
3.6 Environment, Safety and Health (ESH)
3.6.1 Electrical Safety
3.7 Design Reviews
3.7.1 Preliminary Design Review Meeting
3.7.2 Final Design Review Meeting
3.8 Serialization
3.9 Warranty
3.10 Packaging
4 QUALITY ASSURANCE
4.1 Quality Assurance Requirements
4.2 Inspection and Test Requirements
Version 1 iv Brookhaven National Laboratory
4.3 Material Review Board Authority
4.4 QA Flow-Down
5 DELIVERABLES
6 SCHEDULE
7 VALUE ENGINEERING
Acronyms ASME American Society of Mechanical Engineers ATP Acceptance Test Procedure BNL Brookhaven National Laboratory BSA Brookhaven Science Associates ESH Environmental, Safety and Health FAT Factory Acceptance Test MRB Material Review Board NFPA National Fire Protection Association
NRTL Nationally Recognized Testing Laboratory NSLS-II National Synchrotron Light Source II PPE Personal Protective Equipment SR Storage Ring SOW Statement of Work SPC Specification UHV Ultra-High Vacuum UL Underwriters Laboratories
NSLSII-VAC-SOW-004: Statement of Work for the Vacuum Furnace System
NSLS-II Page 1 of 9 16 JUL 2026
1 INTRODUCTION AND OVERVIEW
1.1 Background
The National Synchrotron Light Source II (NSLS-II) facility is adding a Vacuum Furnace System to serve as an addition to the NSLS-II Vacuum Processing Facility. The furnace will be utilized to perform various processes of vacuum brazing, vacuum annealing, and vacuum firing of components in preparation for installation into ultra-high vacuum (UHV) environments. The system is intended primarily to support current NSLS-II operations, including the development of the NSLS-II Upgrade. In addition, this vacuum furnace is expected to perform services for the EIC project, CAD, and other operational groups within BNL
1.2 Definitions
The supplier of the Vacuum Furnace System specified here shall be referred to as “the Contractor”.
Brookhaven Science Associates, which manages BNL, shall be referred to as BSA. The Technical Specification for the Vacuum Furnace System, NSLSII-VAC-SPC-003 shall be referred to as “the Specification”.
1.3 Scope
This Statement of Work (SOW) will be the basis for the procurement of a Vacuum Furnace System to be used at the National Synchrotron Light Source II at Brookhaven National Laboratory (BNL) managed by Brookhaven Science Associates (BSA). This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.
2 REFERENCES
In the event of a conflict between the Specification and the SOW, the Contractor shall immediately notify the BSA Contractual Representative. Failure to notify the BSA contractual representative of a document conflict shall not relieve the Contractor’s responsibility to ensure full compliance with all requirements.
The following documents are an integral part of the SOW. Unless otherwise specified, that issue date or revision level shall be that in effect at the time of award.
Document Number Document Title
ASME Y14.5 Engineering Drawing and Related Documentation Practices
BNL QA-101 Supplier Quality Assurance Requirements
UL Standard 508 Standard for Safety for Industrial Control Equipment
NSLSII-VAC-SPC-003 Technical Specification for the Vacuum Furnace System
National Synchrotron Light Source II
Version 1 Page 2 of 9 Brookhaven National Laboratory
3 REQUIREMENTS
In accordance with the applicable specifications, referenced documents, and instructions as defined in this Statement of Work, the Contractor shall be responsible for designing, manufacturing, assembly, inspecting, testing and delivering the Equipment.
3.1 Contractor Responsibilities
3.1.1 Technical Performance
The Contractor shall ensure that the resultant design & finished product meets the performance parameters and criteria in accordance with BSA specification NSLSII-VAC- SPC-003 and all other reference documents.
3.1.2 Tooling/Fixtures/Test Equipment
The Contractor shall be responsible for supplying all materials, including (but not limited
to) the construction of all tools, jigs, fixtures, and test equipment required to complete the vacuum chamber. All special tooling and test equipment fabricated or procured by the Contractor shall be the property of BSA and shall be accounted for by the Contractor.
3.1.3 Spare Parts/Special Tools
Delivery of the Equipment shall include spare components recommended by the Contractor and agreed to by the BSA Technical Representative.
3.2 Engineering Analysis: Design and Design Review Requirements
3.2.1 Detailed Analysis Requirements
N/A
3.2.2 Detailed Design Requirements
3.2.2.1 Preliminary Design Review
The Contractor shall be responsible for providing a PDR report that reflects the state of the developed design. The report shall consist of the following items to be addressed in detail and supported by preliminary calculations that shall be presented at the PDR for review and approval.
Preliminary Design and assembly drawings for the chamber and the chamber support system
Proposed schedule outlining the dates for critical milestones
Suggested list of spare parts
3.2.2.2 Final Design Review
The Contractor shall provide an FDR report that includes, in detail, all aspects of the final design for the Vacuum Furnace System. The report shall consist of all technical issues from the PDR in addition to the following items, all of which shall be presented at the FDR for review and approval.
A brief summary of any significant changes since the PDR
Complete schedule showing all milestones and major activities required to meet all contractual requirements
NSLSII-VAC-SOW-002: NEXT-II ARI-SXN EPU Vacuum Chamber SOW
NSLS-II Page 3 of 9 16 JUL 2026
All detailed documentation, including but not limited to: manufacturing drawings, top level assembly drawings, parts lists, and schematics
Manufacturing and assembly planning and highlighted concerns
Proposed design improvement upgrades (Section 7)
Provisions for strongback lifting, rigging, transport, survey and/or alignment
Demonstration that all applicable safety codes and standards have been met
Manufacturing/Inspection/Test Plan
Acceptance Test Procedures
Final list of recommended spares
ESH information
Identification of hazards, and their mitigation, during all stages of the life of the Equipment including installation, commissioning, operation, maintenance, and repair.
This information shall be provided to determine ESH compliance and also included in the Equipment manual.
This shall include hazards that may occur during fault conditions and shall include all potentially hazardous materials. This shall include, but not limited to, the following:
• Identify possible hazards, at any part of the life-cycle, onsite at BNL
• Eliminate the hazard, or manage the hazards in the following hierarchy:
o substitute with something less hazardous, or o mitigate the severity of the hazard through engineering, or o use PPE (least desirable).
3.2.2.3 Approval to Proceed
BSA must approve in writing the final design report, including any modifications introduced at the Final Design Review Meeting, before the Contractor proceeds with ordering material and components. Ordering of long-lead-time materials and components prior to the approval of the Final Design Review Report must be reviewed and approved in writing by BSA.
3.2.3 Manufacturing, Inspection and Test Requirements
The Equipment shall be tested at the Contractor’s facility to demonstrate compliance to the Specification in accordance with the FDR report and the SOW. All test data shall be documented and accompany the Equipment at delivery. Acceptance of the test data is contingent upon data review and written approval prior to shipment of the Equipment.
3.2.4 Acceptance Test Procedures
The Contractor shall provide Acceptance Test Procedures that are in accordance with this SOW, the Specification and reference documents noted herein. The ATP shall ensure that all test requirements as defined in the Specification are achieved. The ATP must be approved by BSA prior to use.
Version 1 Page 4 of 9 Brookhaven National Laboratory
3.3 Management
3.3.1 Program Plan
Within two (2) weeks after award of contract, the Contractor must deliver a detailed program plan for each phase, which includes a milestone schedule defining the design validation, manufacturing, inspection and testing phases in sufficient detail to allow regularly scheduled progress monitoring.
3.3.2 Progress Teleconference
Within four (4) weeks after award of contract, bi-weekly program technical and progress teleconferences and/or meetings between the Contractor and BSA shall be held at a mutually scheduled time. The discussions shall include the Contractor’s progress, technical and contractual questions, presentations of analysis or testing results, design reviews, value engineering, trouble shooting, material status, tooling status, resources, and manufacturing issues until deemed no longer necessary by the BSA technical representative.
3.3.3 Manufacturing/Inspection/Test Plan
A manufacturing plan shall be developed which identifies the manufacturing processes of work required to complete all efforts as identified in this SOW. The plan shall be submitted for review at the FDR and approved in writing by BSA. The plan may be a single document, or may make use of existing travelers or other suitable planning and control documents. It shall address the MRP, and at a minimum include manufacturing, inspection, and test steps including identification of critical manufacturing operations and parts/subassemblies showing integrated flow into the end item(s). If the Contractor does not have an MRP system in place, then details for purchasing all raw materials, shop loading (by work center), and a schedule for manufacturing all components and assemblies through packaging and shipping shall be provided by the Contractor.
3.3.4 Performance Reporting
Throughout the life of the contract, the Contractor shall supply a written report by the fifth (5th) of every month to the BSA technical representative and contractual representative clearly detailing progress through the prior month with respect to the program. This shall include milestone charts, detailed progress, open items, problems, recommended solutions, and risk mitigation. The Contract number shall be in the subject line of all correspondence.
3.4 Documentation and Data Management
3.4.1 General documentation Requirements
All the documentation provided by the Contractor shall be in English.
BSA requires detailed drawings to allow installation, maintenance and future upgrade of the Equipment. All engineering drawings shall:
o Be formatted in accordance with ASME Y14.5 o Have views shown in third angle projection o Use metric dimensions and tolerances o Have a separate parts list if not embedded in the drawing o Be provided to BSA in electronic format as defined in section 3.4.2, supplied on a DVD or BSA identified FTP site.
NSLS-II Page 5 of 9 16 JUL 2026
3.4.2 Drawing and Model File Format Requirements
The Contractor shall provide and maintain, as well as have the capability to receive and send, CAD files of all components or assemblies in the following formats:
2D formats: AutoCAD 2D drawings (.DWG format)
3D solid model formats: IAM or IPT (preferably), STP or SAT. IGES files and surface models are not acceptable
3.4.3 End Item Documentation
The Contractor shall provide an electronic copy of the End Item documentation package in accordance with the schedule set forth in this SOW. The End Item documentation package shall consist of the following documentation:
Operations and Maintenance manual for the Vacuum Furnace System
Operations and Maintenance manuals for all applicable sub-system equipment.
Mechanical layout and itemized top assembly drawing with detailed Bills of Materials
All 2D drawings and 3D solid models
Completed travelers
Inspection documents of detail components and completed sub-assemblies
Acceptance test reports and all test documents performed during manufacturing
Material Certifications
Certificate of Conformance
3.5 Configuration Management
The Contractor shall establish and maintain a configuration control system to assure that all end items (including spares) are of the proper configuration, and that all approved configuration changes are incorporated at the specified effectivity points. Records verifying the configuration of each item shall be maintained for a minimum of five (5) years from the date of acceptance of the Equipment by BSA.
3.6 Environment, Safety and Health (ESH)
The Contractor shall design and build all equipment in accordance with ESH requirements in the appropriate specifications, codes, standards, and other documents listed in Section 2 of this SOW.
3.6.1 Electrical Safety
Electrical distribution systems must comply with NFPA 70 the National Electrical Code.
All electrical equipment including components must comply with NFPA 70, be Certified by a NRTL and Labeled with their certification mark. All equipment that is not available for purchase with an NRTL certification must be reviewed and approved by the BSA Authority Having Jurisdiction prior to purchase.
NOTE: The CE marking is only recognized in the European Union and is not an approved NRTL for products sold in the US.
All electrical connections ≥50 volts shall be guarded to protect workers from the risk of electrical shock, Plexiglas® is not acceptable; Lexan® may be used. All Electrical insulation must be Fire Retardant and radiation resistant, Teflon® shall not be used in any application.
Version 1 Page 6 of 9 Brookhaven National Laboratory
3.7 Design Reviews
3.7.1 Preliminary Design Review Meeting
To ensure compliance with the requirements of this SOW, applicable specifications, and interface control drawings a PDR meeting shall be held in accordance with the schedule set forth in Section 6. The Contractor shall provide, no later than five (5) working days prior to the scheduled meeting, a draft PDR report that shall consist of the requirements set forth in Section
3.2.2.1. The findings of this report will be reviewed at the subsequent PDR to be held at the Contractor’s facility, or in video conference format (at the discretion of BSA), and shall cover all pertinent issues relating to the detailed design. The Contractor shall be responsible for maintaining and submitting the minutes of the PDR and shall also incorporate any agreed-to changes into the final PDR report, both of which are to be submitted within ten (10) working days of the PDR for review and approval by BSA.
3.7.2 Final Design Review Meeting
To ensure compliance with the requirements of this SOW, applicable specifications, interface control drawings and to receive approval to proceed to the production phase, an FDR meeting shall be held in accordance with the schedule set forth in Section 6. The Contractor shall provide, no later than five (5) working days prior to the scheduled meeting, a draft FDR report that shall consist of the approved PDR and the requirements as set forth in Section 3.2.2.2. The findings of this report will be reviewed at the subsequent FDR to be held at the Contractor’s facility or in video conference format (at the discretion of BSA), and shall cover all pertinent issues relating to the final detailed design. The Contractor shall be responsible for maintaining and submitting minutes of the FDR and shall also incorporate any agreed-to changes into the final FDR report, both of which are to be submitted within ten (10) working days of the FDR for review and approval by BSA.
Upon approval of the FDR report the design is to be considered “frozen” and no changes are permitted to the design, materials, processes, methods, and tooling, or to component-level substitutions, without written approval by BSA.
3.8 Serialization
Where labeling is required, the position of serialization and/or labeling of the identification number/nameplate shall be agreed upon between the Contractor and BSA.
3.9 Warranty
The Contractor shall warranty the Vacuum Furnace System, against failure and defects for a period of two
(2) years from final acceptance at BNL.
3.10 Packaging
In preparation for shipping, the vacuum chamber, equipment racks, and accessory equipment shall be covered or wrapped for protection against weather elements, dust, and damage to projections, shock loads, impacts, and rubbing. All vacuum flanges on the chambers and taper transitions shall be properly capped with mating blank flanges to protect the sealing surfaces and to prevent contamination. The chamber shall be properly braced and cushioned within the crate so that it cannot shift during handling and shipment. The crate must be designed to withstand a mechanical shock in excess of 2 Gs. Each packing crate shall be fitted with ShockWatch® sensors or an equivalent approved by BSA. Durable materials, such as clean wood, bubble wrap, or similar non-contaminating materials are to be used to support and protect the chambers and strong backs from one another during transit and storage. Peanut-type material shall not be used for
NSLS-II Page 7 of 9 16 JUL 2026 packaging. The crate shall be appropriately labeled with the listing of contents, destination, gross weight, location of the center of gravity, purchase order number and contact information. The crate shall be palletized and include provisions to permit access for a forklift to lift the crate. Prior to shipment, all water shall be removed from the cooling channels and water circuits to prevent freezing and microbial damage. The method of shipping shall be air freight. Each container shall have at least one G-force indicator.
4 QUALITY ASSURANCE
The Contractor shall maintain and apply an effective QA program for the design, manufacture, and testing of all systems and equipment provided. The system shall meet the requirements of the ISO-9001 Standard, “Quality Management System Requirements.” The Contractor shall supply the necessary documentation to demonstrate this compliance. Post-award surveys may be required and shall be supported.
4.1 Quality Assurance Requirements
As set forth in BSA Form BNL-QA-101, “Brookhaven National Laboratory Supplier Quality Assurance Requirements,” as amended herein, forms a part of this statement of work. Specifically, this includes the following sections: 1, 2, 3, 3.1, 3.1.2, 3.2 3.3, 3.4, 3.5, 3.6, 3.7, 4.0, 4.1, 4.2, 4.3,4.4 (as modified below),
4.4.1 4.4.2, 4.4.3, 4.5 (as modified below), 4.6,4.7, 4.7.1, 4.7.3, 4.10, 4.10.1, 4.10.2, 4.10.4, 4.11, 4.12, 4.13,
4.14 (as modified below), 4.16, 4.19, 4.21, 4.31, 4.39, and 4.42.
Clause 4.4: Manufacturing/Inspection/Test Plan is modified as follows: At the FDR, the supplier shall submit for the Buyer’s approval a Manufacturing/Inspection/Test Plan for the item(s) to be produced. Clause 4.5: “Witness” points, is modified as follows: The supplier shall provide BSA with thirty (30) days’ notice in advance of reaching such witness points during the manufacturing and test cycle of each item.
Clause 4.14: Source Inspection/Surveillance is modified as follows: Items to be delivered require inspection, test, or surveillance by the Buyer’s representative at the Supplier’s facility. Thirty (30) days’ notice, for acceptance inspections and tests, shall be given by the Supplier to the Buyer to permit scheduling of source inspection.
4.2 Inspection and Test Requirements
The Contractor shall prepare and maintain a Manufacturing/Inspection/Test Plan, which shall be submitted to the BSA technical representative for written approval by NSLS-II Quality Assurance prior to its required use. This shall consist of a plan, in the Contractor’s format, listing components, subassemblies, and assemblies; identifying inspections and tests planned for the verification of quality;
and identifying documentation/planning to be used for such accomplishment.
The systems shall be tested by the Contractor at the Contractor’s facility, the Contractor’s subcontractor’s facility, or a pre-approved BSA collaborator prior to shipment, using an ATP (as noted in Section 3.2.4) generated by the Contractor and approved by BSA. BSA or its designee retains the right to witness all testing. Final acceptance of the vacuum chamber shall take place following the successful completion of final testing at BNL. The time period for the final testing at BNL shall be within ninety (90) days after delivery of the vacuum chamber to BNL.
4.3 Material Review Board Authority
Unless, and until, Material Review Board (MRB) authority has been requested and received, the Contractor shall be restricted to dispositions of rework, scrap, and return-to-vendor, i.e., the Contractor shall not use nonconforming materials via unique or standard repair processes, nor via use-as-is-dispositions.
Version 1 Page 8 of 9 Brookhaven National Laboratory
The Contractor shall not delegate MRB authority to suppliers without the prior knowledge and written approval of BSA.
BSA may delegate MRB Authority to the Contractor, when requested by the supplier. Such request shall be accompanied by: 1) the Contractor’s procedure for the identification, evaluation, disposition, and control of non-conformances; and 2) the resumes of personnel to be assigned as MRB members.
All non-conformances requiring MRB action shall be documented and sent to the BSA technical representative within five (5) working days of the decision.
4.4 QA Flow-Down
The Contractor shall ensure a proper and complete flow-down of all applicable QA requirements to its suppliers and sub-tier suppliers.
5 DELIVERABLES
The Contractor shall supply the following:
Item Deliverable Due BSA Approval
1 Program plan 2 weeks after award of contract Yes 2 Technical and progress teleconference 4 weeks after award of contract/Bi-weekly No 3 Performance reports 5th of each month after receipt of Program Plan No Draft PDR report 5 working days prior to PDR Yes
4 Final PDR report and PDR minutes 10 working days after PDR Yes Draft FDR report 5 working days prior to PDR Yes
5 Final FDR report and FDR minutes 10 working days after FDR Yes 6 ATP report 5 working days after acceptance testing Yes 7 Delivery of equipment and spares at BNL As set forth in contract Yes 8 End Item documentation package With Equipment delivery Yes
6 SCHEDULE
The following schedules are for planning purposes only. Schedule requirements set forth in the contract take precedence.
Milestone Calendar weeks after award
Preliminary design review 5 Final design review 10 Acceptance test at Contractor’s facility prior to shipment 30 Receipt of equipment at BNL 36
NSLS-II Page 9 of 9 16 JUL 2026
7 VALUE ENGINEERING
The Contractor is encouraged to make recommendations for changes that might lead to an improvement in performance, reliability, quality, safety, and/or reduction in cost. Simplicity in operation, ease of maintenance, and an improvement in the performance and reliability of the specific functions beyond the requirements of this specification are objectives which shall be considered in the production. Where it appears a substantial improvement in simplicity of design, performance, ease of maintenance or reliability can result from the use of materials, parts and processes other than those specified, it is desirable that their use be investigated. When investigations point to advantages that may be realized, the recommendation for change shall be presented to BSA for review and, if approved, authorized in writing.
NATIONAL SYNCHROTRON LIGHT SOURCE II
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
Document Number Date
NSLS-II Vacuum Furnace System Technical Specification
QA Category: A-2
Name Title Approver/Reviewer King Wilson NSLS-II Vacuum Engineer Approver Robert Todd NSLS-II Vacuum Group Leader Approver Nicole Magliulo NSLS-II QA Engineer Approver Robert Lee NSLS-II ESH Manager Approver Timur Shaftan NSLS-II Accelerator Division Director Approver Steve Sherwood NSLS-II Liaison Engineer Approver Jake Hawkes NSLS-II Project Management Approver Additional Staff Not Approving Through SharePoint Lacy Jones NSLS-II Operations Engineer (Export Control) Reviewer Jayce Blood Manager, Subcontracts, PPM Procurement Reviewer
This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR Parts 730-774 as EAR99 Technology.
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
VERSION CONTROL SHEET
VERSION DESCRIPTION DATE AUTHOR APPROVED BY
1 First Release 16JUL2026 K. Wilson See cover sheet.
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
Contents
1 Introduction
1.1 Overview
1.2 Definitions
1.2.1 General
1.2.2 Applicable Documents
2 Scope
2.1 Project Scope
3 VACUUM FURNACE REQUIREMENTS
3.1 Vacuum Furnace Chamber
3.1.1 General Overview
3.1.2 Chamber Construction
3.1.3 Doors
3.1.4 Viewport(s)
3.1.5 Ports and Flanges
3.1.6 Gas Cooling System
3.1.7 Process Manifold
3.1.8 Leak Rate/Test
3.2 Working Hot-Zone
3.3 General
3.3.1 Work Zone Dimensions
3.3.2 Heating Elements
3.3.3 Heat Shielding / Insulation
3.3.4 Temperature and Uniformity Performance
3.3.5 Hearth
3.4 Heating Power Supply and Control System
3.4.1 General
3.4.2 System Rating
3.4.3 Standards
3.4.4 Power Supply
3.4.5 Power Delivery
3.4.6 Safety and Protective Features
3.4.7 Interfaces
3.5 Vacuum and Gas Systems
3.5.1 General
3.5.2 High Vacuum Pumping System
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
3.5.3 Vacuum Manifolding and Valving
3.5.4 Vacuum Gauging
3.5.5 Gas System
3.5.6 Venting
3.5.7 Safety Interlocks
3.5.8 Performance Requirements
3.6 Controls and Instrumentation
3.6.1 General Requirements
3.6.2 Control Rack and Electrical System
3.6.3 Safety Interlock System
3.6.4 Operator Interface / HMI
3.6.5 Recipe and Process Control
3.6.6 Data Acquisition and Trending
3.6.7 Utility Monitoring
3.7 Utility Requirements
3.7.1 General Requirements
3.7.2 Electrical
3.7.3 Water Cooling
3.7.4 Compressed Air
3.7.5 Process Gases
3.7.6 Additional Utility Requirements
3.7.7 Utility Connection Points
3.7.8 Consumption Data
3.7.9 Safety Shutdown
4 Factory Acceptance Test (FAT)
4.1 Vacuum Leak Rate
4.2 Ultimate Vacuum Level
4.3 Pump-Down Performance (
4.4 Temperature Uniformity Survey (TUS)
4.5 Heating Ramp Rate
4.6 Temperature Stability (Soak)
4.7 Multi-Zone Heating Control
4.8 Gas Cooling Performance
4.9 Safety Interlocks and Alarms
4.10 Control System and HMI Functionality
4.11 Video Monitoring System (if purchased)
4.12 Mechanical Operation
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
4.13 Instrumentation Accuracy
4.14 Utility Interlocking
Acronyms
A Amperes AMS Aerospace Material Specification ASA American Standard Association Flange ASME American Society of Mechanical Engineers ASTM American Society for Testing and Materials BNL Brookhaven National Laboratory BSA Brookhaven Science Associates BTU British Thermal Unit dB Decibel DOE Department of Energy ESH Environmental, Safety and Health GPM Gallons per Minute HMI Human-Machine Interface NEMA National Electrical Manufacturers Assoc.
NFPA National Fire Protection Association NRTL National Recognized Testing Laboratory
NSLS-II National Synchrotron Light Source II NW NW (vacuum flange standards) PID Proportional-Integral-Derivative (control) PLC Programmable Logic Controller PSIG Pounds per Square Inch Gauge QA Quality Assurance RGA Residual Gas Analyzer SOW Statement of Work SPC Specification SCFM Standard Cubic Feet per Minute TUS Temperature Uniformity Survey UHV Ultra High Vacuum UL Underwriters Laboratories W Watts V Volts
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
1 INTRODUCTION
1.1 Overview
This document defines the NSLS-II Specifications for a Vacuum Furnace System being acquired to serve as an addition to the NSLS-II Vacuum Processing Facility. The furnace will be utilized to perform various processes of vacuum brazing, vacuum annealing, and vacuum firing of components in preparation for installation into ultra-high vacuum (UHV) environments. The system is intended primarily to support current NSLS-II operations, including the development of the NSLS-II Upgrade. In addition, this vacuum furnace is expected to perform services for the EIC project, CAD, and other operational groups within BNL.
National Synchrotron Light Source II (NSLS-II) is a state-of-the-art scientific research facility at Brookhaven National Laboratory (BNL) that operates continuously 24 hours per day, 7 days per week, and with capacity to accommodate 58 experimental beamlines and an expected minimum lifetime of 30 years.
1.2 Definitions
1.2.1 General
Terminology as applied in this document will be described in this section.
1.2.2 Applicable Documents
Table 1 - The latest version of the following documents are applicable to this technical specification.
Document Number Document Title
NFPA 70 National Electric Code
NFPA 79 Electrical Standard for Machinery
NFPA 86 Standard for Ovens and Furnaces
ASME B30.26 Rigging Hardware
ASTM Standard D3951-98 Standard Practices for Commercial Packaging
AMS 2750 SAE Aerospace Materials Specification for Pyrometry
BNL-QA-101 Supplier Quality Assurance Requirement
NSLSII-VAC-SOW-004 Statement of Work
ASME Section VIII ASME Boiler and Pressure Code
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
2 SCOPE
2.1 Project Scope
The scope of this specification covers the design, manufacture, testing, delivery, installation support, and commissioning assistance for one (1) horizontal vacuum heat treatment furnace system intended for high-temperature processing of various metal alloys and ceramic materials utilized in UHV environments.
The furnace shall be capable of stable and prolonged operations of up to 1200°C under high vacuum, performing vacuum annealing, tempering, brazing, and inert gas quenching operations in accordance with applicable industry standards and process requirements. The equipment supplied shall include all necessary mechanical, electrical, instrumentation, control, pumping, cooling, and safety systems required for complete and reliable operation.
The supplier shall provide:
• Complete vacuum furnace assembly
• Hot zone and thermal insulation system
• Vacuum pumping system
• Gas quench system
• PLC/HMI-based control system
• Instrumentation and data logging
• Temperature uniformity survey (TUS) capability
• System documentation and manuals
• Factory acceptance testing (FAT)
• Startup and commissioning support
• Operator and maintenance training
The furnace system shall comply with applicable requirements of:
• AMS 2750
• NFPA 86
• NRTL requirements (as applicable)
• Customer-specific process specifications
The supplier shall furnish all drawings, electrical schematics, utility requirements, and recommended spare parts (door O-rings, heater elements, etc.) necessary for installation and long-term operation.
Any deviations from this specification shall be clearly identified by the supplier at the time of quotation.
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
3 VACUUM FURNACE REQUIREMENTS
3.1 Vacuum Furnace Chamber
3.1.1 General Overview
The vacuum furnace shall incorporate a horizontal, double-wall, cold-wall vacuum chamber designed for high-temperature vacuum and partial-pressure (argon) operation. The chamber shall be engineered for reliable, distortion-free performance under repeated thermal cycling and sustained operation at least 1200°C for a minimum of eight (8) continuous hours. All design, materials, fabrication, and testing shall conform to applicable standards including ASME Section VIII (where relevant), NFPA 86, and industry best practices for vacuum heat-treating equipment.
3.1.2 Chamber Construction
The furnace chamber shall be of double-wall construction with an inner process chamber and outer jacket.
Inner walls shall be constructed of 300-series stainless steel (304L or 316L preferred). The design shall be liquid-cooled to maintain a cold-wall configuration, ensuring external surface temperatures remain safe for operator contact. The cooling system shall provide uniform water flow across the chamber walls to minimize thermal gradients and prevent hot spots. The vessel must be designed and tested for full vacuum (10⁻⁵ Torr or lower pressure) and positive pressure up to 2 psig for inert gas backfill and cooling.
All internal welds shall be internal fusion or full penetration, smooth, ground flush, where required, and vacuum-tight. Internal surfaces shall be cleaned and degreased to reduce outgassing. The chamber shall include all necessary reinforcements to maintain structural integrity under vacuum, thermal expansion, and pressure cycling.
3.1.3 Doors
The chamber shall be equipped with both front and rear doors. Each door shall be O-ring sealed for vacuum integrity, hinged with handle and able to open a full 180 degrees, secured with heavy-duty manual clamps or latches providing even sealing pressure, water-cooled where necessary and fitted with safety interlocks to prevent opening under high temperature or other unsafe conditions.
O-ring gasket seals must seal and be leak tight without use of vacuum grease or other sealant material applied to the gasket or mating flange.
3.1.4 Viewport(s)
3.1.4.1 Standard Observation Viewport
An optical viewport shall be provided, angled to view the center of the hot zone, with an externally actuated protective shutter to shield the glass from thermal radiation when not in use. The viewport shutter is preferred to be pneumatically operable; however, manual actuation is acceptable. It shall be made of a high-temperature resistant material suitable for direct exposure to 1200°C conditions during observation. The contractor will note duration of viewport use at elevated temperatures.
3.1.4.2 Camera System Option
Option: Video observation camera system:
• The option of a real-time video monitoring system as a process observation tool, if available.
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
NSLS-II Vacuum Furnace System – Technical Specification
Version 1
NSLSII-VAC-SPC-003 16JUL2026
• The system must enable the Operator to visually monitor braze alloy melting and flow behavior in the temperature range of 800°C to 1100°C.
• The camera system shall be designed for secure mounting on either the primary viewport or a secondary access port, as appropriate for the furnace design.
• The Vendor shall clearly indicate the availability of this option and confirm the following information:
Industrial-grade camera with high-temperature lens assembly capable of clear imaging at temperatures from 800°C to 1100°C in vacuum.
Mounting on a dedicated viewport (separate from or in addition to the standard optical viewport) angled toward the center of the hot zone.
Externally mounted camera housing with integrated air or water cooling to protect the camera electronics and lens from radiant heat.
Manual or automatic protective shutter mechanism to shield the lens when not in use.
Camera shall provide color or monochrome video output with adjustable brightness/contrast for optimal viewing of molten alloy behavior.
Video feed shall be exhibited on the furnace HMI screen or other display.
Camera resolution and sensitivity shall be suitable for clear observation of braze alloy flow and melting characteristics at operating temperature.
• The Vendor shall state in their proposal whether the camera system is offered as a standard option and shall provide details on camera type (e.g., CCD/CMOS with high-temperature optics), maximum operating temperature rating, cooling method, and expected service life of the lens assembly.
3.1.5 Ports and Flanges
• Multiple KF/NW or ASA port flanges shall be provided for instrumentation, gauges, and accessories.
• One NW-200 (8-inch tube size) or ASA equivalent accessory port with blank flange shall be provided on the side of the chamber extending horizontally from the center of the chamber, outfitted with cooling and shielding as necessary.
Port will be utilized to retrofit support equipment by BNL (back up pumping, RGA system, etc.)
• Dedicated flange ports shall be provided for vacuum pumping system connections.
• A thermocouple survey port shall be included for temperature uniformity surveys.
• Provisions shall be made for all necessary electrical power feedthroughs, thermocouple feedthroughs, and instrumentation penetrations. All feedthroughs shall be high vacuum-rated and rated for the maximum operating temperature.
3.1.6 Gas Cooling System
A high-efficiency blower fan system shall be provided for rapid argon gas cooling of the workload. The system shall include:
• Pneumatically actuated shutters or dampers to isolate the blower during vacuum operation.
• Water-cooled heat exchanger for gas recirculation.
• Design shall achieve uniform cooling across the hot zone and workload.
BROOKHAVEN SCIENCE…