B.1_481342 - Enclosure A_DRAFT Contract.pdf
PDF 1 MB Posted
- Attached to
- Helium Purifier
- Solicitation number
- 481342
- Issued by
-
Department of Energy Office of Science
About this file
This document is a contract for the procurement and delivery of one 80K Helium Purifier for the B912 Cryogenic Module Test Facility at Brookhaven National Laboratory. The contract is issued by Brookhaven Science Associates (BSA) on behalf of the Department of Energy and includes a firm-fixed price (amount to be determined at award) with a performance period of thirty calendar weeks from execution. Payment will be made upon satisfactory completion and acceptance of the purifier, with Net 10 payment terms. Invoices must be submitted in PDF format to BSA Accounts Payable at apinvoices@bnl.gov, with the final invoice marked "FINAL" and copied to the contractual representative.
The contractor is responsible for design, manufacturing, testing, and delivery of the 80K Helium Purifier with all accompanying components, including piping interconnections and terminal box connections to interface with BNL's PLC system. Key requirements include compliance with technical specifications (SPEC_CAD-1377), a Statement of Work (CA6000102SOW), and applicable drawings; design and final design reviews with BSA approval required before proceeding with material ordering; factory acceptance testing demonstrating full compliance prior to shipment; and delivery of comprehensive end-item documentation including production drawings, as-built listings, test reports, and certifications. The purifier must achieve inlet impurities of 100 ppmv, outlet purity of 1 ppmv, superficial gas residence time of no less than 28 seconds at 40 g/s flow, pressure drop limits of 300-600 mBar depending on operating conditions, and a startup time under 2 hours. All pressurized components must comply with ASME codes and DOE 10CFR851 safety requirements. Freight is FOB Destination with specific labeling, packing, and notification requirements per BNL procedures; the system must be backfilled with dry nitrogen at 5 psig and sub-contained. A one-year warranty on all parts and labor commences upon BSA acceptance, with remote diagnosis and troubleshooting available within 24 hours during regular workdays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev. 9.4, February 2018 1
BSA Contractual Representative
Funded Amount Contract Number
Cassandra Smith TBD 481342
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor (TBD)
SAM UEI (TBD)
CONTRACT
This Contract (the "Contract") is between the party named above (the "Contractor"), and Brookhaven Science Associates, LLC. ("BSA"), the latter acting under a Prime Contract with the United States of America (the "Government") represented by the United States Department of Energy ("DOE”).
I. SCOPE OF WORK
The Contractor shall furnish one (1) 80K Helium Purifier in accordance with the requirements of this Contract.
All work shall be performed in strict accordance with the Statement of Work, Technical Specification, Drawings, and Supplier Quality Assurance Requirements identified in Article V – Additional Terms, which are incorporated herein and made a part of this Contract.
II. PERIOD OF PERFORMANCE
This Contract shall become effective upon execution by both BSA and the Contractor and shall remain in effect for thirty (30) calendar weeks thereafter, unless otherwise modified in writing by BSA's Contractual Representative.
III. FIRM-FIXED-PRICE AND PAYMENT
A. Firm-Fixed-Price: In full consideration of the Contractor's satisfactory performance of all requirements under this Contract, BSA shall pay the Contractor the firm fixed price of TBD U.S. Dollars ($TBD). The said sum shall constitute full compensation for all materials and services furnished hereunder.
No additional compensation shall be authorized unless approved in writing by BSA's Contractual Representative through a formal Contract modification.
B. Payment: Payment shall be made upon satisfactory completion of the Contract requirements, receipt and approval of a properly certified invoice, and acceptance of the Helium Purifier and applicable deliverables by BSA.
Payment terms are Net ten (10) days.
Invoice submission: Invoices shall be submitted in PDF format via email to the
Rev. 9.4, February 2018 2
BSA Accounts Payable at apinvoices@bnl.gov.
The final invoice must be clearly marked as “FINAL”, and a copy must be submitted directly to the BSA Contractual Representative.
C. Freight: Freight terms shall be FOB Destination, Freight Prepaid to Brookhaven National Laboratory, 98 Rochester Street, Upton, Long Island, New York.
D. Labelling, Packing, and Notification Requirements:
More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.
Labeling Requirements
All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:
Brookhaven National Laboratory BSA Contract Number 98 Rochester St.
Upton, NY 11973 Box Number / Number of Boxes
Packing List Requirements
Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:
• Ship from company name and address
• Supplier contact name
• Supplier telephone number
• Ship to address as instructed by Contractual Representative
• BSA Contract number
• Part number, description, quantity, unit of measure, and corresponding BNL
Contract line number
Special Notification of Delivery
If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall provide a minimum of 3 days’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received. Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.
Marking of Outer Package mailto:apinvoices@bnl.gov https://www.bnl.gov/shipping/ mailto:WarehouseOperations@bnl.gov mailto:WarehouseOperations@bnl.gov
Rev. 9.4, February 2018 3
Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.
Protection of Material and Equipment
The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage. Such protection shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging.
Unacceptable Packing Material
Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative:
Name: ___________________ Telephone: (___) __________ Email: ___________________
The BSA Technical Representative shall serve as the primary point of contact between BSA and the Contractor for technical matters relating to the performance of this Contract. The BSA Technical Representative is not authorized to modify the terms, conditions, scope, price, or period of performance of this Contract.
B. BSA’s Contractual Representative:
Name: Cassandra Smith
Telephone: (907) 888-3142 Email: csmith2@bnl.gov
The BSA Contractual Representative shall serve as BSA's authorized representative for all contractual matters. Any changes or modifications to the terms, conditions, scope, price, or period of performance of this Contract must be https://www.astm.org/Standards/D3951.htm https://www.astm.org/Standards/D3951.htm mailto:csmith2@bnl.gov
Rev. 9.4, February 2018 4 authorized in writing by the BSA Contractual Representative or an authorized designee.
C. Contractor’s Technical Representative:
The Contractor's Technical Representative shall serve as the primary point of contact between BSA and the Contractor for technical matters relating to the performance of this Contract.
D. Contractor’s Contractual Representative:
The Contractor's Contractual Representative shall serve as the Contractor's authorized representative for all contractual matters under this Contract.
V. ADDITIONAL TERMS
The provisions of Brookhaven Science Associates, LLC General Terms and Conditions for Commercial Items and Services, Rev 25.0, Sept. 2026, are incorporated herein and made a part hereof.
This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental terms and conditions listed above which are incorporated herein by reference. The complete text of these terms and conditions can be viewed via the internet at: https://www.bnl.gov/ppm/terms-and-conditions.php.
Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Contractual Representative immediately.
The following documents attached hereto and made a part hereof contain additional provisions of this Contract:
• Attachment 1 – Statement of Work, Document No. CA6000102SOW, dated July 9,
• Attachment 2 – Technical Specification, Document No. SPEC_CAD-1377, dated July 9, 2026
• Attachment 3 – Drawing, Document No. CA6000023, Rev. B
• Attachment 4 – Drawing, Document No. CA6000095 (DRAFT – To Be Provided
Upon Contract Award)
• Attachment 5 – Brookhaven National Laboratory Supplier Quality Assurance
Requirements, Document No. BNL-QA-101, dated April 2025
This Contract does not bind, nor purport to bind, the Government of the United States.
ACCEPTED:
https://www.bnl.gov/ppm/terms-and-conditions.php
Rev. 9.4, February 2018 5
CONTRACTOR BROOKHAVEN SCIENCE ASSOCIATES, LLC
FOR BROOKHAVEN NATIONAL
LABORATORY
Signature: Signature:
Printed Name:
Printed Name: Cassandra Smith
Title: Title: Contractual Representative
Date: Date:
The Contractor shall sign and return one (1) copy of this Contract to the attention of Cassandra Smith, Contractual Representative, Procurement and Property Management Division, at csmith2@bnl.gov.
mailto:csmith2@bnl.gov
Brookhaven National Laboratory Number: CA6000102SOW Brookhaven Science Associates Version: 1
B912 Cryogenic Module Test Facility Effective: 09JUL2026
ATTACHMENT 1
80K Helium Purifier
Statement of Work (SOW)
Contents
1 INTRODUCTION
1.1 Background
1.2 Definitions/Acronyms
2 Applicable Documents
3 REQUIREMENTS
3.1 Contractor Responsibilities
3.1.1Equipment
3.1.2Equipment/Controls and Applicable Work
3.1.3Tooling/Fixtures/Test Equipment
3.2 Design and Design Review Requirements
3.2.1Preliminary Design Review Report
3.2.2Preliminary Design Review Meeting
3.2.3Final Design Review Report
3.2.4Final Design Review Meeting
3.2.5Approval to Proceed
3.3 Manufacturing and Testing Requirements
3.3.1Manufacturing Requirements
3.3.2Acceptance Test Procedures
3.3.3Program Plan
3.3.4Progress Teleconference
3.4 Documentation and Data Management
3.5 Configuration Management
3.6 Environment, Safety and Health (ESH)
3.7 Warranty
3.8 Packaging & Shipping
3.9 Shipping ................................................................................................. Error! Bookmark not defined.
4 QUALITY ASSURANCE
4.1 Quality Assurance Requirements
4.2 QA Flow Down
4.3 Material Review Board (MRB) Authority
5 SCHEDULE
6 DELIVERABLES
7 VALUE ENGINEERING
1 INTRODUCTION
This Statement of Work (SOW) is the basis for the procurement of Helium Purifier for the cryogenics system at the B912 Cryogenic Module Test Facility B912 Cryogenic Module Test Facility at Brookhaven National Laboratory (BNL). The building 912 (hereafter B912) cryogenic system upgrade at Brookhaven National Laboratory is managed by Brookhaven Science Associates (BSA). This document outlines the Contractor’s responsibilities and obligations necessary for completing the requirements as set forth herein.
1.1 Background
The B912 project includes the design, construction, installation, and commissioning of the new liquid helium plant required to facilitate testing of EIC cryomodules. The project includes a Horizontal Test Facility (HTF) capable of testing 2 Cryomodules (CM), a Large Vertical Test Facility (LVTF), and Small Vertical Test Facility (SVTF). The B912 Cryomodule Test Facility Upgrade includes the addition of a new Purifier to maintain low contamination levels within the system. Other equipment that will be added for the B912 system upgrade but is not part of the scope of this SOW is a new cryo-distribution system to the HTF test bunker, Dewar with Sub-cooler, and Cryogenic Refrigeration Plant.
1.2 Definitions/Acronyms
ABL As-Built Listing ATP Acceptance Test Procedure BNL Brookhaven National Laboratory BSA Brookhaven Science Associates BPVC Boiler and Pressure Vessel Code DOE U.S. Department of Energy ESH Environment, Safety & Health FDR Final Design Review GeV Gigaelectron Volt LHe Liquid Helium LN2 Liquid Nitrogen MLI Multi-Layer Insulation MRP Material Requirements Planning P&ID Process and Instrumentation Diagram PDR Preliminary Design Review PLC Programmable Logic Controller QA Quality Assurance RF Radio Frequency R/L Refrigeration/Liquefaction
SAT Site Acceptance Test SC Superconducting SOW Statement of Work SR Storage Ring
2 Applicable Documents
Technical Specification SPEC_CAD-1377
3 REQUIREMENTS
In accordance with the applicable specifications, referenced documents, and envelope drawings as defined in this SOW, the Contractor shall design, manufacture, and deliver the Helium Purifier with all the accompanying components, as set forth herein.
The Contractor offering the design and manufacturing of the Helium Purifier shall have previously and successfully designed and fabricated such components of similar size.
3.1 Contractor Responsibilities
Contractor shall provide the following equipment/controls and work as stated below in accordance with Technical Specification
3.1.1 Equipment
The Contractor shall deliver to BNL a 80K Helium Purifier
3.1.2 Equipment/Controls and Applicable Work
1. The Contractor is responsible for shipment of the Helium Purifier to BNL facility.
2. The Contractor shall delivery all Piping interconnections and other interfaces
3. The Contractor shall be responsible for providing Terminal box connections to interface with BNL PLC in order to communicate with Helium Purifier field devices and instrumentation.
4. BNL will provide PLC hardware to be installed at factory by Contractor. Contractor will provide instrumentation power supply. Contractor will provide inputs/outputs/interface mapping.
3.1.3 Tooling/Fixtures/Test Equipment
The Contractor shall supply all special tooling and test equipment required to complete the installation of components listed in Technical Specification Section 2.3.
3.2 Design and Design Review Requirements
3.2.1 Preliminary Design Review Report
The Contractor shall be responsible for the overall design of Helium Purifier and items listed in section 3.1.2. Prior to the PDR meeting, the Contractor shall prepare and submit a PDR report that includes the following:
1. Preliminary design with a description of Helium Purifier and items in section 3.1.2.
The design data such as adsorber mass, superficial velocity, and residence time at the specified operating pressure shall be submitted.
2. List of hardware to be provided upon delivery to BSA.
3. Methods of the thermal insulation of the cryogenic components (e.g. how many layers of MLI) and the requirements to maintain this insulation (e.g. required vacuum).
4. Protection measures for the pressurized volumes and the vacuum casing, including, but not limited to, relief valves and burst disks where applicable.
5. Layout of interface points.
6. Number and location of field joints.
7. Details of the testing that will be carried out at the factory; see section 3.3.2.
3.2.2 Preliminary Design Review Meeting
A Preliminary Design Review meeting shall be held in accordance with the schedule set forth in section 5. The Contractor shall provide, no later than ten (10) working days prior to the scheduled meeting, a draft PDR report that meets the requirements set forth in section 3.2.1 herein. The findings of this report will be reviewed at the PDR meeting, to be held at the Contractor’s facility or in video conference format (at the discretion of BSA) and shall cover all pertinent issues relating to the detailed design of equipment listed in section 3.1. The Contractor shall maintain and submit the minutes of the PDR meeting and shall also incorporate any agreed-to changes into the final PDR report, both of which are to be submitted within five (5) working days of the PDR meeting for subsequent review and approval by BSA.
3.2.3 Final Design Review Report
The Contractor shall develop the overall design of Helium Purifier and items listed section
3.1.2 in accordance with the applicable specifications and supporting documents as identified herein. The following categorized documents shall be delivered according to the schedule in section 5 of this SOW.
3.2.3.1 Deliverable Documents Prior to FDR Meeting
Prior to the FDR meeting, the Contractor shall prepare and submit an FDR report that includes the following:
1. The final design including mechanical layout, assembly / disassembly drawings with specifications required for the maintenance of components.
2. A planned Schedule for the delivery of Helium Purifier with all the accompanying components listed in section 3.1.
3. Heat leak analyses for Helium Purifier.
4. Test procedures that will be carried out at the factory; see section 3.3.2.
5. Detailed interconnect installation plan.
6. Relief devices sizing calculations.
3.2.4 Final Design Review Meeting
A Final Design Review meeting shall be held in accordance with the schedule set forth in section 5 herein. The Contractor shall provide, no later than ten (10) working days prior to the scheduled meeting, a draft FDR report that shall consist of the requirements set forth in Statement of Work section 3.2. The findings of the FDR report shall be reviewed at the FDR meeting to be held at the Contractor’s facility or in video conference format (at the discretion of BSA) and shall cover all pertinent issues relating to the final detailed design of equipment listed in section 3.1. The Contractor shall maintain and submit minutes of the FDR meeting and shall also incorporate any agreed-to changes into the final comprehensive FDR report, both of which are to be submitted to BSA within five (5) working days of the FDR meeting for subsequent review and approval. After written approval of the FDR report by BSA, the Contractor shall promptly begin manufacturing, testing, and delivery of the equipment listed in Statement of Work section 3.3.
3.2.5 Approval to Proceed
BSA must approve in writing the FDR report, including any modifications introduced at the FDR meeting, before the Contractor proceeds with ordering material and components. BSA will approve the FDR within 5 working days after receiving the report and closure of any action items. Prior to BSA approval of the FDR report, the Contractor may request written approval from BSA to order long-lead or critical components and/or materials.
3.3 Manufacturing and Testing Requirements
3.3.1 Manufacturing Requirements
Where any deviations from the original drawings contained in the manufacturing drawings authorized by BSA occur, the Contractor must note the changes with the date and name of the BSA person who authorized the change. A final set of “as-built” drawings must be provided in the same manner, as required in Statement of Work section 3.3.
3.3.2 Acceptance Test Procedures
The Contractor shall provide Acceptance Test Procedures (ATPs) that are in accordance with this SOW, the specification, and all applicable codes and standards. ATPs shall be provided to BSA Technical Representative within the timeframe listed in Section 5. All tests listed in this section and any additional tests shall be identified and scheduled in both the Program Plan and Manufacturing/Inspection/Test Plan (see sections 3.3.3 and
3.3.5 of this SOW). The Contractor shall perform all ATPs in accordance with the approved FDR report at minimum, but not limited to:
Pressure tests in accordance with requirements in SPEC_CAD-1377 Ref [1] section 2.2, item 1 and 6 and section 2.3.3, items 2, 3 and 4
The performance test in accordance with requirements in SPEC_CAD-1377 Ref.
[1] section 2.2, item 3
The startup time test in accordance with requirements in SPEC_CAD-1377 Ref. [1] section 2.2, item 7
The LN2 consumption test in accordance with requirements in SPEC_CAD-1377 Ref. [1] section 2.2, items 5 and 6
Leak tests in accordance with requirements in SPEC_CAD-1377 Ref. [1] section 2.3.1, item 2 and section 2.3.3 item 6
The Helium Purifier shall be tested at the Contractor’s facility to demonstrate full compliance with the SOW/Technical Specification. The Helium Purifier shall be fully assembled and be representative of the final as-delivered configuration for Factory Acceptance Test (FAT). The test listed in the SOW/Technical Specification shall be conducted on the Helium Purifier at the Contractor’s facility according to the approved Acceptance Test Procedure (ATP), prior to delivery at BNL.
All test data shall be documented in the Factory Acceptance Test report and sent to BSA prior to the Helium Purifier delivery. Acceptance of the test data is contingent upon data review and written approval by BSA Technical Representative prior to shipment of the Helium Purifier.
BNL shall perform a site acceptance test indicated above upon delivery of Helium Purifier. The Contractor shall be responsible for a repair, if any fail, to comply with the acceptance test requirements.
3.3.3 Program Plan
Within two (2) weeks after award of contract, the Contractor shall deliver a detailed program plan which includes a milestone schedule defining the design validation, manufacturing and testing in sufficient detail to allow regularly scheduled progress monitoring.
3.3.4 Progress Teleconference
Within two (2) weeks after award of contract, bi-weekly program technical and progress teleconferences and/or meetings between the Contractor and BSA shall be held at a mutually scheduled time. The discussions shall include the Contractor’s progress, technical and contractual questions, presentations of analysis of testing results, design reviews, value engineering, troubleshooting, material status, tooling status, resources, and manufacturing issues.
Additional teleconferences and/or meetings shall be held at the request of BSA, as necessary during contract performance.
3.3.5 Manufacturing/Inspection/Test Plan
A Manufacturing/Inspection/Test plan shall identify the manufacturing processes of work required to complete all efforts as indicated in this SOW. A manufacturing plan shall be submitted for review and approval by BSA no later than (2) weeks after the FDR meeting.
The plan may be a single document or may make use of existing travelers or other suitable planning and control documents. It shall address the Material Requirements Planning (MRP), and at a minimum include manufacturing, inspection, and test steps including identification of critical manufacturing operations and parts/subassemblies showing integrated flow into the end item(s). If the Contractor does not have an MRP system in place, then details for purchasing all raw materials, shop loading (by work center), and a schedule for manufacturing all components and assemblies through packaging and shipping shall be provided by the Contractor.
3.3.6 Performance Reporting
Throughout the life of the contract, the Contractor shall supply a written report by the fifth of every month to the BSA technical representative and contractual representative clearly detailing progress through the prior month with respect to the program. This shall include milestone charts, detailed progress, upcoming work, open items, problems, recommended solutions, and risk mitigation. The report shall be sent to BSA electronically in Microsoft Project or PDF format.
3.4 Documentation and Data Management
1. All the documentation provided by the Contractor shall be in English.
2. The Contractor shall provide an electronic copy (email, plus either CD ROM or USB data storage device) and one hardcopy of the End Item documentation package in accordance with the schedule set forth in the contract. The End Item document package shall be considered the property of BSA after contract completion and shall consist of the following documentation:
Production drawings
As-Built Listing (ABL) – mechanical and electrical for each component
Components data sheets that include at minimum but not limited to:
- The pipe flexibility and stress analyses (ASME B31.3)
- Relief devices sizing calculations (ASME BPVC Section XIII – Rules for
Overpressure Protection) and the vacuum vessel drop plate calculations (UG-125 to UG-135, ASME BPVC-VIII Div.1),
- Lifting lug and weld attachment design calculations
- Form U-1 and associated data reports/QA documentation for all items classified as ASME pressure vessels, particularly Form U-1 for adsorbers, and Form U-1P for plate heat exchangers
- Certified Mill Test Reports (material certifications) for materials used for cryogenic components
- Inspection data for inspections performed at incoming inspection
- Inspections in-process during manufacturing
- Completed travelers
- Weld map inspections for weld joints per ASME B31.3 piping code
User/operation manuals and any specific instructions (e.g. startup/shutdown, adsorber media replacement)
Acceptance test procedures and acceptance verification test reports for the Helium Purifier at the Contractor’s site.
Acceptance Test Procedures and final acceptance test reports for the Helium Purifier at the BNL site.
Mapping and labelling of field signals to terminal blocks (for interfacing with
BNL PLC)
Certificate of Conformance including Form U-3 for items classified as ASME pressure vessels
Documents shall be readable with the software Adobe Reader (*.pdf format), Microsoft Office 2010 (*.docx and *.xlsx formats), AutoCAD 2026 (*.dwg or *.dxf format).
3. All engineering drawings shall be formatted in accordance with ASME Y14.5-2024
4. The Contractor shall maintain the capability to receive and send CAD files of all components or assemblies in STP, SAT, IGES, IAM, or IPT file format at the request of BSA.
5. The Contractor shall retain all original data generated under this contract, in good condition, for at least five (5) years, unless otherwise directed by BSA.
3.5 Configuration Management
The Contractor shall establish and maintain a configuration control system to ensure that all end items (including spares) are of the proper configuration, with proper corresponding labeling of each component, and that all approved configuration changes are incorporated at the specified effectivity points. Records shall be maintained verifying the configuration of each item.
3.6 Environment, Safety and Health (ESH)
3.6.1 Pressure Safety
All pressurized components shall be compliant with the SPEC_CAD-1377 Department of Energy (DOE) 10CFR851, Ref. [13], §851.24 “Functional areas,” item (b) with reference to Appendix A to Part 851 — “Worker Safety and Health Functional Areas” in section 4 - “Pressure Safety” with applicable listed documents including ASME Code B31.3 “Process Piping” and ASME Boiler and Pressure Vessel Code (BPVC) sections I through section XII, particularly, section VIII “Rules for Construction of Pressure Vessels” Division 1, or Division 2 “Alternative Rules”. Pressure relief devices shall be certified (stamped) by either both the National Board of Boiler and Pressure Vessel Inspectors (NBBI) or an ASME certified inspector.
3.6.2 Material Handling
Lifting hardware must meet BNL safety requirements, and as such shall be selected and used according to ASME B30.26, “Rigging Hardware.” The Contractor shall submit the lift plan to BSA for review prior to delivery of the Helium Purifier. All Below-the-Hook Lifting Devices in use shall be load tested to 125% of maximum load according to ASME B30.20, and documentation of that test shall be provided to BSA. All component lifting points/brackets shall be designed with the safety factor of 3 (to yield), and calculations provided in the End Item documentation package.
3.7 Warranty
The Contractor shall provide a one-year warranty on all parts and labor commencing with BSA’s acceptance of the Helium Purifier. A recommended spare parts list shall be available from the Contractor. Remote diagnosis and troubleshooting from Contractor shall be available upon request within 24 hours during regular workdays.
3.8 Packaging
1. In preparation for shipping, the Helium Purifier shall be covered or wrapped for protection against weather elements, dust, and damage to projections, shock loads, impacts, and rubbing. It shall be properly braced and cushioned within the packing so that it will not shift during handling and shipment. The method of shipping will be specified by BSA one month prior to delivery. System to be backfilled with dry nitrogen at 5psig and be sub-contained isolated volume.
2. The Components shall be properly supported and contained to prevent damage and contamination during transit. Durable material, such as clean wood, bubble wrap, or similar non-contaminating materials are to be used to support and protect the components from one another during transit and storage. Peanut type material shall not be used for packaging. Packaging for objects weighing over 100 kg shall have the weight and location of the center of gravity clearly identified, and contain tilt, temperature, and G-force indication.
3. All vacuum jacketed piping/area shall be shipped with vacuum less than 10-4 torr.
4 QUALITY ASSURANCE
The Contractor shall maintain and apply an effective Quality Assurance (QA) program for the design, manufacture, and testing of all systems and equipment provided. The system shall meet the requirements of the ISO-9001 Standard, “Quality Management System Requirements.”
4.1 Quality Assurance Requirements
Quality Assurance Requirements are applicable to BSA Form BNL-QA-101, “Brookhaven National Laboratory Supplier Quality Assurance Requirements,” forms a part of this Statement of Work.
4.2 QA Flow Down
The Contractor shall ensure a proper and complete flow-down of all applicable QA requirements to its suppliers and sub-tier suppliers.
4.3 Material Review Board (MRB) Authority
1. Unless, and until, Material Review Board (MRB) authority has been requested and received, the Contractor shall be restricted to dispositions of rework, scrap, and return to Contractor i.e., the Contractor shall not use nonconforming materials via unique or standard repair processes, nor via use-as-is-dispositions.
2. The Contractor shall not delegate MRB authority to suppliers without the prior knowledge and written approval of BSA.
3. BSA may delegate MRB Authority to the Contractor, when requested by the Contractor. Such request shall be accompanied by 1) the Contractor’s procedure for the identification, evaluation, disposition, and control of non-conformances; and 2) the resumes of personnel to be assigned as MRB members.
4. All non-conformances requiring MRB action shall be documented and sent to the BNL technical representative within five (5) working days of the decision.
5 SCHEDULE
The following schedule is for planning purposes only. Schedule requirements set forth in the contract will take precedence.
Milestone Calendar weeks after award
Program Plan (submitting for review and approval) 2 PDR Report (draft for review) 3 Preliminary Design Review (PDR) 5 PDR Report (submitting for approval) 6 FDR Report (draft for review) 10 Final Design Review (FDR) 12 FDR Report (submitting for approval) 13 Manufacturing/Inspection/Test Plan (submitting for review and approval)
Factory Acceptance Test Report at Contractor’s facility prior to shipment
Delivery of Helium Purifier at BNL 28 Site Acceptance Test by BNL 30 Delivery of End Item Documentation Package 30
6 DELIVERABLES
The Contractor shall supply the following:
Item Description Due Approval Required
1 Technical and Progress Teleconferences
2 weeks after award of contract, bi-weekly thereafter No
2 Program Plan 2 weeks after award of contract Yes 3 Performance Reports 5th of every month No 4 Draft PDR Report 2 weeks prior to PDR Yes 5 PDR Report and PDR Minutes 1 week after PDR Yes 6 Draft FDR Report 2 weeks prior to FDR Yes 7 FDR Report and FDR Minutes 1 week after FDR Yes 8 Manufacturing/Inspection/Test Plan 2 weeks after FDR Yes 9 Factory Acceptance Test Report 14 weeks after FDR Yes 10 Delivery of Helium Purifier at BNL 16 weeks after FDR Yes 11 End Item Documentation Package 18 weeks after FDR Yes
7 VALUE ENGINEERING
The Contractor is encouraged to make recommendations for changes that might lead to an improvement in performance, reliability, quality, safety, or reduction in cost. Simplicity in operation, ease of maintenance, and an improvement in the performance and reliability of the specific functions beyond the requirements of the specification are objectives which shall be considered. Where it appears a substantial improvement in simplicity of design, performance, ease of maintenance or reliability will result from the use of materials, parts, and processes other than those specified, it is desirable that their use be investigated.
When investigations point to advantages that may be realized, the recommendation for change shall be presented to BSA for review and, if approved, authorized in writing.
B912 Cryogenic Module Test Facility
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
Helium Purifier for B912 Liquid Helium Refrigeration System
Page 1 of 14 SPEC_CAD-1377 9JUL2026 1
DOCUMENT NUMBER DATE VERSION
ATTACHMENT 2
TECHNICAL SPECIFICATION
80K Helium Purifier for B912 Liquid Helium Refrigeration System
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
Helium Purifier
SPEC_CAD-1377 9JUL2026 1
DOCUMENT NUMBER DATE VERSION
This information is controlled by the U.S. Department of Commerce Export Administration Regulations 15 CFR Parts 730-774 as EAR99 Technology.
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
Helium Purifier for B912 Liquid Helium Refrigeration System
Page 3 of 14 SPEC_CAD-1377 9JUL2026 1
DOCUMENT NUMBER DATE VERSION
CONTENTS
Definitions/Acronyms
1 Introduction
1.1 Scope
1.2 Applicable Documents
2 Technical Requirements
2.1 Layout and Location Requirements
2.2 Performance Requirements
2.3 Component Requirements
2.3.1 Vacuum Vessel(s) of Helium Purifier
2.3.2 Thermal Shield
2.3.3 Piping and Adsorber(s)
2.3.4 Valves
2.3.5 Safety Pressure Relief Valves
2.3.6 Heat Exchangers
2.3.7 Instrumentation
2.3.8 Air Distribution
2.4 Electrical
2.5 Interfaces
2.5.1 Installation of Helium Purifier
2.5.2 LN2 Transfer line
2.5.3 Piping connections
2.5.4 Gas purity analyzer
2.5.5 Control system
BROOKHAVEN SCIENCE ASSOCIATES
UPTON, LONG ISLAND, N.Y. 11973
PROJECT:
Helium Purifier for B912 Liquid Helium Refrigeration System
Page 4 of 14 SPEC_CAD-1377 9JUL2026 1
DOCUMENT NUMBER DATE VERSION
Definitions/Acronyms
ASME American Society of Mechanical Engineers Bara Bar (Absolute) Barg Bar (Gauge Pressure) BNL Brookhaven National Laboratory BPVC Boiler and Pressure Vessel Code BSA Brookhaven Science Associates DOE Department of Energy ESH Environment, Safety, and Health GeV Giga (billion) electron Volt g/s gram per second LHe Liquid Helium LN2 Liquid Nitrogen MeV Mega electron volt NEC National Electric Code NFPA National Fire Protection Association NRTL Nationally Recognized Test Lab NSLS-II National Synchrotron Light Source II P&ID Process and Instrumentation Diagrams PLC Process Logic Controller ppmv Parts per million volume PRV Pressure Relief Valve RF Radio Frequency R/L Refrigeration/Liquefaction SC Superconducting SR Storage Ring
1 INTRODUCTION
This Technical Specification (SPC) is the basis for the procurement of Helium Purifier for the Liquid Helium (LHe) Refrigeration Plant, which exists at the B912 Cryogenic Module Test Facility B912 Cryogenic Module Test Facility at Brookhaven National Laboratory (BNL). The building 912 (hereafter B912) cryogenic system upgrade at Brookhaven National Laboratory is managed by Brookhaven Science Associates (BSA).
The requirements of the purity of Helium in the system are high; an input of 100 ppmv and an output of 1 ppmv. The superficial gas residence time shall be no less than 28 seconds for helium gas at design flow.
1.1 Scope
The Contractor shall be responsible for the Helium Purifier as following:
1. Delivery of Helium Purifier
2. Piping interconnections and other interfaces
3. Terminal box connections to interface with BNL PLC in order to communicate with Purifier field devices and instrumentation.
4. BNL will procure and send PLC hardware to be installed at factory. Contractor will provide instrumentation power supply. Contractor will provide inputs/outputs/interfaces.
NOTE: See section 2.5 for details.
This document specifies the design and operating requirements for the Helium Purifier.
1.2 Applicable Documents
In the event of a conflict between the Technical Specification and the SOW, the Contractor shall immediately notify the Brookhaven Science Associates (BSA) contractual representative, who shall in each instance determine which document takes precedence and advise the Contractor accordingly. Failure to notify BSA of a document conflict shall not relieve the Contractor’s responsibility to ensure full compliance with all requirements.
The following documents form a part of requirements to the extent specified herein. Unless otherwise noted, the issue date or revision level shall be that in effect at the time of award.
Table 1 Applicable Documents
Ref
Document Number
Document Title
1 CA6000023 912 Purifier Process and Instrumentation Diagram (AutoCAD)
CA6000095
(DRAFT)
912, CRYOGENIC SYSTEM, 2D Facility Layout (DRAFT)
3 ASME A13.1 Scheme for the Identification of Piping Systems (2015)
4 ASME B30.20 Below-the-Hook Lifting Devices (2013)
5 ASME B30.26 Rigging Hardware (2015)
6 ASME B31.3 Process Piping (2016)
ASME BPVC
Section VIII Rules for Construction of Pressure Vessels -> Division 1, 2 (2015)
8 ASME BPVC
Section XIII
ASME BPVC Section XIII: Rules for overpressure protection
9 ASME BTH-1 Design of Below-the-Hook Lifting Devices, Design (2014) (Cat. “A”)
10 BNL-8715-2008-
IR
“Vacuum Systems Consensus Guidelines for DOE Accelerator Laboratories”
11 BNL-QA-101 BNL Supplier Quality Assurance Requirements
12 NFPA 70 2020 National Electrical Code (2020)
13 DOE 10CFR851
Code of Federal Regulations - Worker Safety and Health Program http://www.ecfr.gov/cgi-bin/text-idx?SID=74c4c4d0c04074b20d18a31cb047f8e0&mc=true&node=pt10.4.851&rgn= div5
IEC 60529:
1989/AMD2:
2013/COR1:201
Degrees of protection provided by enclosures (IP Code) http://www.ecfr.gov/cgi-bin/text-idx?SID=74c4c4d0c04074b20d18a31cb047f8e0&mc=true&node=pt10.4.851&rgn=div5 http://www.ecfr.gov/cgi-bin/text-idx?SID=74c4c4d0c04074b20d18a31cb047f8e0&mc=true&node=pt10.4.851&rgn=div5 http://www.ecfr.gov/cgi-bin/text-idx?SID=74c4c4d0c04074b20d18a31cb047f8e0&mc=true&node=pt10.4.851&rgn=div5
2 TECHNICAL REQUIREMENTS
2.1 Layout and Location Requirements
1. The Helium Purifier will occupy the B912 Cryomodule Test Facility, see drawing CA6000095 “912 CRYOGENIC SYSTEM 2D Facility Layout”, Table 1, Ref. [2].
CA6000095 is currently in DRAFT and will be released upon Contract award. The overall dimensions of the Helium Purifier in a plan view footprint, not to exceed 12.5 ft length x 6 ft width. The 2D Facility layout drawing is in DRAFT, but the Footprint Zone dimensional limits of the Helium Purifier are known. The Helium Purifier should not exceed the available footprint zone in Ref. [2] without prior written approval from
BSA.
2. There is an overhead fire protection sprinkler system in the 912 building. All components of Helium Purifier shall be installed in a “moisture proof” condition or housed in “moisture proof” cabinets that are capable of withstanding modest exposure to water or other fluids and meeting an IEC IP63 rating, Ref. [14], or equivalent.
3. The Contractor shall ensure the Helium Purifier be able to withstand operating in a non-climate-controlled area with air temperature with the air temperature range of 30 ±2°C (~86 ±4°F) and humidity range from 30% to 60%.
2.2 Performance Requirements
One of the scenarios for use of the Helium Purifier is air contamination of the cryogenic system. With this scenario, the Helium Purifier shall bring the cryogenic system back to the normal operation as quickly as possible without Helium inventory replacement. The intent is to direct all contaminated Helium, after the burst disk replacement on Cavities, through the warm return to the compressor’s oil removal system and further to the Helium Purifier and back to the cryogenic system. With all mentioned above, the Helium Purifier shall comply with the following requirements.
1. The Helium Purifier for the LHe Refrigeration System shall be an in-line Purifier. The operating pressure range shall be between 116 psig (8 barg) and 232 psig (16 barg).
2. The Helium Purifier shall be a continuous operation Purifier of double-bed configuration with the regeneration time of each bed not more than 6 hours.
3. The Helium Purifier shall be capable of handling the inlet impurities level equal to 0.01% (100 ppmv) at the Helium flow rate of 40 g/s for 8 hours or more (when the regeneration is required). The cumulative impurities level of any gasses at the exit of the purifier shall be less than or equal to 1 ppmv, and shall have a superficial gas residence time of no less than 28 seconds at a flow of 40 g/s.
4. The Helium Purifier shall have manual operator capability.
5. The Helium Purifier shall have automatic regeneration and automatic switchover of beds.
6. The pressure drop across the Helium Purifier shall be less than or equal to 300 mBar (4.4 psig) at the upper range of the operating pressure 232 psig and flow of 40 g/s.
The pressure drop across the Helium Purifier shall be less than or equal to 600 mBar (3.4 psig) at the low range of the operating pressure 116 psig and flow of 40 g/s. At lower pressure the pressure drop will be higher for the same flow, 100 mbar needs correcting or 40 g/s needs correcting.
The pressure drop shall not exceed Condition 1 or Condition 2 in Table 2 below without prior written approval from BSA.
Table 2 Operating Pressure Flow Pressure Drop
Condition 1 8 barg 40 g/s </= 600 mBar
Condition 2 16 barg 40 g/s </= 300 mBar
7. The startup time duration between a warm Helium Purifier and its operational condition shall be less than 2 hours.
8. During normal operation when the system is in 2K pumping mode (16 barg and 10 g/s) the Helium Purifier LN2 consumption shall not exceed 30 Gal/hr.
9. All pressurized components shall be compliant with the Department of Energy (DOE) 10CFR851, Table 1 Ref. [13], §851.24 “Functional areas”, item (b) with reference to Appendix A to Part 851 —“Worker Safety and Health Functional Areas” in section 4
- “Pressure Safety” with applicable listed documents including American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (BPVC) sections I through section XIII, particularly, section VIII “Rules for Construction of Pressure
Vessels” Division 1, or Division 2 “Alternative Rules”, and ASME Code B31.3 “Process Piping”.
10. The Helium Purifier shall be capable of operating under integration with BNL automated control system and in manual mode as well. The Helium Purifier configuration shall at minimum include the number of components and instrumentation indicated in 912 PURIFIER PROCESS AND INSTRUMENTATION DIAGRAM, Table 1, drawing number CA6000023, Ref. [1]. Any other configuration is subject to review and approval by BSA in writing upon fulfillment of requirements of this specification.
11. The Helium Purifier shall be designed such that the routine maintenance is required no more than once every twelve (12) months, regardless of whether the system is operated intermittently or continuously. The duration of any routine maintenance activity shall not exceed two (2) days.
12. The Helium Purifier shall be designed and constructed with a minimum operational life of greater than 20 years based on an average of 4,000 operating hours per year average and 24 warm up/cool down temperature cycles per year. The design shall provide for replacement of adsorbents (charcoals, zeolite, alumina or other). Any deviation from this specification shall require prior written approval from BSA and shall be supported by the technical justification.
13. The overall weight of the Helium Purifier, maximum allowable working pressure (MAWP), design and operating temperature ratings, purity specifications, serial number, and manufacturing date shall be indicated on the nameplate.
2.3 Component Requirements
Labeling of all valves, instrumentation and interface points (flanges/ports) on all components is required.
2.3.1 Vacuum Vessel(s) of Helium Purifier
1. All low temperature elements, below 280K range, shall be inside the vacuum vessel of the Helium Purifier.
2. The insulating vacuum operating pressure shall be 10-4 Torr or lower and shall not require dynamic pumping. The total helium leak rate with a mass spectrometer shall be less than 108 std. cc/s.
3. The vacuum vessel(s) shall have DN25 KF port with isolating valves to connect to BSA supplied vacuum pumps.
4. The vacuum vessel shall have an integrated DV-6 series (TCG) gauge for the vacuum pressure monitoring at DN25 KF port, as shown in Ref. [1].
5. The vacuum vessel shall be protected against overpressure by a drop plate or other pressure relief device that shall allow release of the overpressure at 0.1 Barg (1.45 psig). There shall be a holding mechanism preventing the drop plate from flying away in case of overpressure.
6. During operation there shall be no ice or condensation on the exterior surfaces.
2.3.2 Thermal Shield
1. The adsorber(s) heat exchangers and piping inside the vacuum vessel shall be wrapped with Mylar® film superinsulation, 30 layers minimum.
2. The heat load flux density shall be below 0.05 W/ft² (0.54 W/m²).
2.3.3 Piping and Adsorber(s)
1. All process piping in the Helium Purifier shall be made of seamless stainless steel piping ASTM 316L or ASTM 304L.
2. All Helium process lines shall have a minimum design pressure of 19.7 Barg (285 psig). The design and construction shall follow Chapter IX rules of ASME B31.3 Code for High Pressure Fluid Service.
3. All Nitrogen process lines shall have a minimum design pressure of 19.7 Barg (285 psig). The design and construction shall follow Chapter VIII rules of ASME B31.3 Code for Category M Fluid Service.
4. The adsorber(s) of the Helium Purifier shall have a minimum design pressure of
19.7 Barg (285 psig). The design and construction shall follow rules of ASME BPVC Section VIII, Division 1, if the vessel exceeds 6 in (~152 mm) inside diameter, otherwise ASME B31.3 Code. A duplicate of each adsorber vessel U-stamp/nameplate shall be attached to the outside of the Helium Purifier.
5. Pipe diameters and routings shall be selected as to minimize the pressure drop across the Helium Purifier required in Section 2.2, Item 6 of this Technical Specification.
6. All process lines, Helium and Nitrogen, and warm gas (bakeout) lines shall be leak checked after final assembly with a Helium mass spectrometer to the leak rate less than 10-8 std. cc/s.
7. The Nitrogen gas vent goes out the B912 facility. Outgoing N2 gas from the purifier will tap into BNL existing vent header. The Contractor shall specify size and connection type of Nitrogen gas vent line.
2.3.4 Valves
1. The valve sizing shall be adequate to minimize the pressure drop across the Helium Purifier as required in Section 2.2, Item 6 of this Technical Specification.
2. All valves outside the vacuum vessel shall be sliding stem buttwelded globe type valves (no ball valves).
3. All control valves and shut-off valves shall be pneumatic with a valve position sensor. The Power supply for solenoid valves shall be 24 VDC, see section 2.4 below.
4. All positioners used for controlling pneumatic valves shall use a two-wire system having a small electrical load of 300 ohms maximum and respond to 4 to 20 mA signal (4 mA - closed, and 20 mA - 100% open). Minimum pneumatic pressure 80psig.
5. Both, main inlet and main outlet of the Helium Purifier shall have 1” nominal isolation buttwelded globe valves.
6. At each main isolation valve, the pump-out ports shall have an isolation globe valve with a DN25 fitting as shown in the Helium Purifier Piping and Instrumentation Diagram Ref. [1] attached in documentation package.
7. All valve seats shall be field replaceable.
8. All actuated valves shall be fail closed.
9. All control valves, plus inlet/outlet manual valves at the supply and return lines, shall have a provision to be locked out.
2.3.5 Safety Pressure Relief Valves
1. The Contractor shall follow rules of ASME BPVC Section VIII, Division 1, UG–125 through UG–140 for Rules for Construction of Pressure Vessels, Table 1 Ref. [7].
and Section XIII, Table 1 Ref. [8]. Rules for Overpressure Protection.
2. The Helium Purifier shall be designed such that all pressure relief devices have sufficient relieving capacity, the pressure boundary is not ruptured, there is no permanent damage to equipment, and no hazard for personnel injury in the event of a power failure or loss of insulating vacuum.
3. For all trapped volumes in the Helium process lines where the pressure may exceed 313 psig, the pressure relief valves (PRV) shall be provided.
4. For all trapped volumes in the Nitrogen process lines where the pressure may exceed 313 psig, the pressure relief valves shall be provided.
5. All PRVs shall be certified (stamped) by either both the National Board of Boiler and Pressure Vessel Inspectors (NBBI) or an ASME certified inspector Certification Mark in accordance with UG-130, Table 1 Ref. [8].
6. All PRVs shall be installed vertically.
2.3.6 Heat Exchangers
1. The heat exchangers shall be made of either aluminum, copper, or stainless steel.
2. The heat exchangers of the Helium Purifier shall have a minimum design pressure of (285 psig). The design and construction shall follow rules of ASME BPVC Section VIII, Division 1.
3. The channel cross-sections, passages and its routings shall be designed to minimize the pressure drop and achieve the requirement of Item 6 in Section 2.2 of this Technical Specification.
2.3.7 Instrumentation
1. An instrument panel with Input/Output modules, switches, breakers, etc. shall be provided inside “moisture proof” cabinet, see requirements of section 2.1 above, item 4.
2. The wiring shall conform to requirements NFPA 70, Table 1 Ref. [12].
3. The list of instrumentation indicated in Ref. [1] P&ID drawing CA6000023 shall be provided at a minimum. There shall be no other configurations with the instrumentation without prior written approval from BSA.
4. All pressure and temperature sensors monitoring internal conditions shall be patched to a terminal block to the allow the interface of BNL PLC.
2.3.8 Air Distribution
1. Air distribution shall have a provision for interlock.
2.4 Electrical
1. All electrical distribution shall be in accordance with U.S.
This is the start of the file's text. The full file is on GovTribe.