This is a Vendor Questions and Answers document for RFQ 47QSSC27Q0027 concerning an Olsun 300 kVA Pad Mount Transformer, posted on November 13, 2026.
The Government seeks clarification on six key requirements. Regarding delivery, vendors must state their actual Days After Receipt of Order (DARO) with justification, as the standard 8-day policy does not apply to this acquisition; DARO should reflect delivery at destination. For Government approval of specification data sheets with drawings, the standard review period is 14 days, though faster turnaround is anticipated. The delivery location is East Miramar Marine Corps Base storage facility across from the East Miramar Fed Fire Building; additional logistical details including receiving hours, base access requirements, and onsite offloading equipment availability will be provided after award. Testing requirements specify that IEEE/ANSI factory production test reports provided with the unit satisfy the requirement; no witness testing, field testing, installation, or startup services are required, as post-installation testing timeline is uncertain. The transformer configuration requires a Radial Feed-through Design with 6 x 200A Bushing Wells, consisting of an incoming set of three bushings and an outgoing set of three. For existing unit information, vendors should contact the Contracting Officer at cara.fowler@gsa.gov to obtain available photographs of the Olsun 225 kVA Pad Mount Transformer, which shares the same configuration as the required 300 kVA unit with only kVA sizing differences; existing nameplate data and specific footprint constraints at Pad B4-PS4-T64 are not provided in these responses.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Posted 11/13/2026 1
Vendor Questions
RFQ 47QSSC27Q0027 (Olsun 300 kVA Pad Mount
1. The RFQ lists a requested DARO of 8 days and provides a field in Section 2 for an extended lead time and reason. Will a quote stating an extended lead time be evaluated on the same basis as quotes meeting 8 days, and is there a latest acceptable delivery date? Should the stated lead time reflect delivery at destination, including factory testing and transit?
The 8 Day DARO is an office policy that does not work for all acquisitions. Please state your actual DARO and the reason for the extended lead time. DARO should be the date of delivery at destination after the order is placed.
2. Will the Government require submittal or approval drawings before the unit is released for manufacturing? If so, what review time should vendors plan for?
Spec data sheets with drawings are acceptable. Standard approval for Government is 14 days, but we should be able to turn it around quickly.
3. Delivery location (pages 1 and 13): Page 1 lists shipment to Naval Base San Diego, CA 92136, while the amended requirements specify delivery to the East Miramar Marine Corps Base storage facility across from the East Miramar Fed Fire Building. Please confirm the delivery location, receiving hours, any base access requirements for the carrier, and that offloading equipment suitable for the unit's weight will be available on site.
The requirements information on the Amend RFQ "East Miramar Marine Corps Base storage facility across from the East Miramar Fed Fire Building" is the correct updated delivery destination. Additional details will not be available until after award.
4. Testing (page 13): The amended requirements state that factory test results will be required, while the original RFQ and the brand name justification referenced certified testing post shipping. Please confirm that standard IEEE/ANSI factory production test reports provided with the unit satisfy the requirement, and that no witness testing, field testing, installation, or startup services are required.
IEEE/ANSI factory production test reports is what will be required. The Customer is unsure of the timeline for installation so post-installation testing will not be required.
5. Primary configuration (page 13): The amended requirements describe a "Radial Feed-through Design with 6 x 200A Bushing Wells," while the original RFQ and the brand name justification list radial feed with three 200A bushing wells. Please confirm the required configuration and bushing well quantity, and whether bushing well inserts are to be included.
Posted 11/13/2026 2
6 x 200A bushings refer to the radial feed through. An incoming set of three and an outgoing set of three.
6. Existing unit (page 13): The requirements note that a picture of the existing 1998 Olsun transformer can be provided. Please provide the photo, the existing unit's nameplate data (including serial number), and any footprint or conduit-location constraints at Pad B4-PS4-T64 so the replacement fits the existing pad.
Photos are available by emailing the Contracting Officer at cara.fowler@gsa.gov (the available pictures are for the Olsun 225 kVA Pad Mount Transformer, but the configuration is the same with the only difference between the units being the kVA sizing).