This document contains questions and answers regarding a request for proposal for Submarine Workforce and Industrial Base support services. The General Services Administration Federal Acquisition Service Assisted Acquisition Services Federal Systems Integration and Management Center is seeking proposals to provide program management, engineering, and technical support services to help sustain the submarine industrial base workforce. Eligible offerors must have a facility security clearance of at least the Secret level at the time of award. The prime contractor's cost accounting system must be determined adequate by the Defense Contract Audit Agency or Defense Contract Management Agency. The amended solicitation will adjust the page limit for corporate experience submissions to 12 pages and correct inconsistencies in the list of attachments. Subcontractors' facility security clearances or cost accounting systems will not satisfy requirements for the prime contractor.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Version 11/15/18
ATTACHMENT Z
OFFEROR QUESTION AND ANSWER (Q&A)
Procurement Instrument Identifier (PIID): 47QFCA24R0005
Note to offerors: Please provide the specific paragraph reference using the Section/sub-Section numbers in the solicitation.
PART #
PARAGRAPH
PARAGRAPH TITLE QUESTION
GOVERNMENT
RESPONSE
N/A N/A N/A Can the KPQM template be changed to landscape vs. its current portrait orientation?
Yes, the KPQM template can be changed to landscape, the amended RFP will reflect this change.
SECTION C
C.4.1.6
QUARTERLY
PLANNING REVIEWS
Can the government please confirm item numbering on the last item on page C-11?
(Currently reads C.4.1.6, which is the same number as the previous section, suspect it should be C.4.1.7)
The amended RFP will correct the numbering of this section.
SECTION L
L.7 (e)
SUBMISSION OF THE
WRITTEN
TECHNICAL
PROPOSAL (PART II)
Can the government confirm it is 12 pages total for Corporate Experience?
In accordance with
Section L.7 of the RFP the written corporate experience submission is limited to 12 pages.
SECTION J J.1 LIST OF
ATTACHMENTS
The List of Attachments in Section J of the
RFP differs from the list of attachments we received from the Government. Can the
Government please reconcile the Attachment names in Section J and those received? For example, missing attachment in RFP package: Q – OCI Statement, R – Financial
Template GSA Form 527.
The amended RFP will correct the attachment names.
Version 11/15/18
PART #
PARAGRAPH
PARAGRAPH TITLE QUESTION
GOVERNMENT
RESPONSE
Section H H.6 SECURITY
REQUIREMENTS
Given that the DD254 indicates the program is unclassified, will the government confirm an FCL from a teammate contractor, should classified work be required during execution, is acceptable?
The prime offeror/entity is required to have an
FCL at least at the
Secret level. The use of a subcontractor's
FCL would not meet the requirements of the
RFP, the prime offeror is required to have the
FCL.
Section H H.13 ADEQUATE COST
ACCOUNTING
SYSTEM
Will the Government confirm that the use of a subcontractor's cost accounting system, determined to be adequate by DCAA or
DCMA, meets this requirement?
The use of a subcontractor's cost accounting system is not adequate to meet this requirement. The contract type will be
Cost Plus Fixed Fee, which requires the prime offeror to have an adequate accounting system at time of award.