47PL0324R0001 Generated PDF with TOC.pdf
PDF 4 MB Posted
- Solicitation number
- 47PL0324R0001
About this file
This document is a Request for Proposals (RFP) issued by the General Services Administration (GSA) for the Tacoma Union Station (TUS) Limited Electrical Upgrade project in Tacoma, Washington.
The project requires the replacement of the outdated switchboards at the TUS facility while it remains fully occupied. The selected contractor will be responsible for ensuring minimal disruption to tenants, maintaining a fully functional electrical system, and keeping the facility and tenants safe until the new systems are operational. The GSA anticipates a phased installation of the new switchboards and will evaluate proposals based on the contractor's ability to execute this phased approach effectively.
The solicitation is a total small business set-aside with an estimated price range between $1,200,000 and $3,200,000. Proposals are due by June 10, 2024 and must include a technical proposal, price proposal, representations and certifications, bid bond, and financial information. Award will be made to the responsible offeror presenting the lowest priced technically acceptable proposal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA Northwest/Arctic Region
Request For Proposals
(RFP)
General Services Administration Public Building Services
Acquisition Management Division Capital Construction and IDV Branch
Solicitation No:
Project:
Location:
47PL0324R0001
Tacoma Union Station (TUS) Limited Electrical
The Tacoma Union Station Courthouse
1717 Pacific Ave
Tacoma, WA 98402
Solicitation Due Date & Time:
Due To:
Monday, June 10, 2024, at 4:00 PM (Pacific Time)
General Services Administration Attn: Mark A. Mitchell, Senior Contracting Officer email: mark.mitchell@gsa.gov
Table Of Contents
Section Description Page Number Standard Form Standard Form 1 Volume 1 - RFP Volume 1 - RFP 4 Volume 2 - Specifications Volume 2 - Specifications 94 Volume 4 - Other Attachments Volume 4 - Other Attachments 109
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
47PL0324R0001, Standard Form Page 1
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
47PL0324R0001, Standard Form Page 2
PAGE
GENERAL SERVICES ADMINISTRATION
OF
ITEM NO.
(a)
SUPPLIES OR SERVICES
(b)
QUANTITY
ORDERED
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
WIRE AND POWER DISTRIBUTION EQUIPMENT
answering RFIs during solicitation, site visit(s) with
Place of Performance: WA0704ZZ 1717 Pacific Ave Tacoma, WA
PSC: J061 -- MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC
Contractor. Duties Include requirements development, 98402-3234 USA working on this project from procurement through to closeout.
LS
PSC: J061 -- MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC
PoP: 07/11/2024 - 08/01/2024
Deliverable
98402-3234 USA
Deliverable
Place of Performance: WA0704ZZ 1717 Pacific Ave Tacoma, WA
HSPD 12 clearances, badging, etc for personnel who will be duties.
CMa to assist The GSA in the procurement of the DB
Contract Type: Firm Fixed Price and documentation.
Place of Performance: WA0704ZZ 1717 Pacific Ave Tacoma, WA
PoP: 10/22/2024 - 04/11/2026
DB Services Electrical Upgrades
HSPD12 Security Clearances commissioning and closeout of the project, including testing
WIRE AND POWER DISTRIBUTION EQUIPMENT
0002 1
PoP: 08/01/2024 - 10/22/2024 in the source selection process, reports and other related
Contract Type: Firm Fixed Price
All services needed to support the electrical upgrade prospective Offerors, review of Offers, non-voting position
PSC: J061 -- MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC
LS
Contract Type: Firm Fixed Price
98402-3234 USA
WIRE AND POWER DISTRIBUTION EQUIPMENT
DB Services Commissioning and Closeout
Deliverable
LS
47PL0324R0001, Standard Form Page 3
GSA Solicitation No: 47PL0324R0001
Construction Contract for: Tacoma Union Station (TUS) Limited Electrical
The Solicitation
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 4
Table of Contents I. General Information
I.A. The Solicitation and Contract I.B. List of Solicitation Documents
I.C. Authorized Representatives
I.D. Pre-Proposal Conference: N/A
I.E. Estimated Price Range
I.F. FAR 52.228-1 Bid Guarantee (Sep 96) I.G. FAR 52.236-27 Site Visit – Construction (FEB 95)
I.H. Receipt of Offers
II. Proposals
II.A. Proposal Contents
II.B. Proposal Format
II.C. Price Proposal II.D. Technical Proposal
II.E. Other Information to Submit with Proposal
III. General Provisions
III.A. Availability of Funds
III.B. Requests for Clarification or Interpretation
III.C. Notice to Small Business Firms
III.D. Information Concerning the Disclosure of Solicitation Results
III.E. Affirmative Procurement Program
III.F. Notice Concerning Preparation of Proposals
III.G. Bond Requirements
III.H. Contractor Performance Information
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
IV. FAR/GSAR Solicitation Provisions
IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 5
IV.B. FAR 52.216-1 Type of Contract (APR 84)
IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 14)
IV.D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)
IV.E. Buy American Requirements
IV.F. Buy American Exceptions
IV.G. FAR 52.233-2 Service of Protest (SEP 06)
IV.H. FAR 52.252-1 Solicitation Provisions Incorporated by Reference
(FEB 98)
IV.I. GSAR Clause 552.102 Incorporating Provisions and Clauses
IV.J. Additional Provisions
V. Instructions and Clauses
V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (NOV 2021)
V.B. 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)
V.C. Security Requirements -552.204-9 Personal Identity Verification Requirements (Apr 2023)
V.D. Additional Clauses
VI. Method of Award
VI.A. Evaluation of Offers – Lowest Price Technically Acceptable
VI.B. Lowest Price Technically Acceptable Evaluation Process
VI.C. Determination of Responsibility
VI.D. Price Reasonableness
VI.E. Unbalanced Prices
VI.F. Total Evaluated Price
VI.G. Non-Price Factors
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 6
I. General Information I.A. The Solicitation and Contract
(1) This Solicitation is set-aside for Small Businesses in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein.
The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
I.B. List of Solicitation Documents The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) GSA Form 527-Contractor’s Qualifications and Financial Information
(6) GSA Affiliated Custom Account (GACA)
(7) Wage Determination # WA20240013, Mod 2, March 08, 2024
(8) Other Attachments Note: Accessing the following documents requires a
GSA GACA account to view documents that reside on a GSA-controlled Google Drive. Once the GACA account is established, Offerors must email the Contracting Officer to provide account information to gain access to GSA Controlled Google Drive.
a. Statement of Work (SOW)
b. P100 2022 Addendum Final
c. P120_2022
d. TUS Electrical 01
e. TUS Electrical 02
f. TUS Electrical 03
g. TUS Electrical 04
h. TUS Electrical 05
i. Oneline Diagram Tacoma Union Station Signed
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 7
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
Authorized Representative Information:
Contracting Officer’s Information
Name: Mark A. Mitchell
Telephone: 509-279-3891
Email: mark.mitchell@gsa.gov
I.D. Pre-Proposal Conference: N/A
I.E. Estimated Price Range The estimated price range for the Project is between $1,200,000and $3,200,000.
I.F. FAR 52.228-1 Bid Guarantee (Sep 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds, or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids;
and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 8
I.G. FAR 52.236-27 Site Visit – Construction (FEB 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Site visits will be held at the following dates and times:
Date: May 15, 2024
Time: 10:00am PDT
(3) All attendees must pre-register to attend the pre-proposal site visit. Offerors can send up to four (4) representatives to the Site Visit. To register, Offerors must email the Contracting Officer listed below by 10:00 AM Pacific Time on May 13, 2024, providing the names, emails, and business affiliations of all attendees representing their company.
For further information about the site visit or access requirements, please contact:
Name: Mark A. Mitchell
Telephone: 509-279-3891
Email: mark.mitchell@gsa.gov
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm local time on the following date and at the following address.
Date: June 10, 2024 Note: Electronic Submission via email: mark.mitchell@gsa.gov. Hard copies submissions are not acceptable for this requirement.
II. Proposals II.A. Proposal Contents Proposals shall consist of the following documents, completed, and executed in accordance with this Solicitation:
1. Price Proposal
2. Technical Proposal
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 9 https://www.acquisition.gov/far/part-52#FAR_52_236_2 https://www.acquisition.gov/far/part-52#FAR_52_236_3 mailto:mark.mitchell@gsa.gov
6. Proprietary Information Agreement(s)
II.B. Proposal Format
Offerors are responsible for reading and understanding the entire Request for Proposal (RFP) Solicitation and Agreement. Only complete proposals will be evaluated. A complete proposal means that all the data and information required by the solicitation are included in the proposal package.
Unless otherwise specified, Proposals shall be submitted electronically in either MS Word 2010 format or Adobe PDF format. The Technical and Price Proposal shall be submitted as separate electronic volumes, e.g. Volume 1 – Price Proposal and Volume 2 – Technical Proposal. Schedules shall be submitted in an electronic format that can be uploaded into and is fully compatible with Microsoft Office Project 2010 ® (with Service Pack 3). The elements of the schedule shall be able to be copied and manipulated for analysis by the Government (e.g., no locked or protected cells, worksheets, etc.).
1. Pricing information shall be provided in an electronic format, including an importable document format (.pdf) viewable with Adobe Reader® and a secondary format fully compatible with Microsoft Office Excel 2010®. The contents of all cells (e.g., text, numbers, formulas, symbols, etc.) shall be able to be viewed and copied for manipulation/analysis by the Government (e.g., no protected cells, worksheets, or workbooks).
2. Other documents with text shall be provided in a format that can be uploaded into and is fully compatible with MS Office Word 2010®. All text should be able to be copied and manipulated for analysis by the Government (e.g., no text images unless they are manufacturer’s product data or logo).
3. There is no page limitation for Price Proposals. Technical Proposals are limited to 40 pages. The Table of Contents and tabbed dividers shall not be counted as part of the page total. Offerors shall clearly number each page sequentially throughout all sections (i.e., page numbering shall not restart within each tabbed divider/proposal section). The Government shall not consider any pages in excess of the 40-page limit specified herein during evaluation. Proposal text shall be in either Times New Roman, Arial, or Courier font, with a minimum font size of 10 points. Proposal submissions shall be in electronic format only. The cover page is clearly labeled “Proposal for 47PL0324R0001-TUS Limited Electrical Upgrade.
II.C. Price Proposal
(1) Contents:
Volume I - Price Proposal: Provide a price proposal that corresponds to the work divisions specified in the Project Documents, demonstrating a clear understanding of project requirements. The price proposal shall be broken down in Construction Specification Institute (CSI) MasterFormat CSI format at level 3 Medium Scope, Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 10 including labor, material, subcontractor costs, overhead, and profit. Note: all subcontractor quotes shall be provided as backup to the price proposal. Subcontractor quotes should also be broken down in CSI MasterFormat to include labor, material, subcontractor cost, overhead, and profit to allow the government to analyze fair and reasonable pricing.
The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements: N/A
II.D. Technical Proposal The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
Offerors shall submit a Technical proposal as described in this solicitation. Technical proposal shall be word document, pdf, excel or similar. Technical proposal shall address all Evaluation Factors described in this solicitation and is limited to 40 pages total.
II Detailed Evaluation Factor Responses 40 pages
Section A A. Factor 1: Proposed Plan and Management Approach
Section B B. Factor 2: Experience on Comparable Projects and Key Personnel
Section C C. Factor 3: Schedule
Section D D. Factor 4: Past Performance
Proposals will be evaluated using an Acceptable/Unacceptable rating.
Evaluation Standards- Lowest Price, Technical Acceptable Evaluation Rating Definition Acceptable: All of the minimum acceptable criteria are clearly met by the proposal. The offeror’s proposal meets the performance and technical capability requirements defined in the
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 11
Statement of Work (SOW). Note: Once the proposals have been determined to be “technically acceptable” award will be based on price only.
Unacceptable: Not all the minimum acceptable criteria are met by the proposal. An unacceptable proposal contacts one or more deficiencies. Proposal fails to meet specified minimum performance and technical capability requirements in the Statement of Work
(SOW).
Factor 1 – The proposed plan and management approach to provide design-build services for the limited electrical upgrades at Tacoma Union Station are of utmost importance. These upgrades are required to replace the outdated switchboards in accordance with the attached Statement of Work.
The Offeror shall submit a narrative (maximum of five (5) pages) that describes the Offeror's technical approach and management plan for the project. This narrative should demonstrate not just an understanding, but an in-depth comprehension of the job responsibilities and requirements, and a clear strategy for completing the construction within the project limits—in accordance with the Statement of Work.
The narrative shall include the names of key prime contractor employees and the qualifications of each discipline that will be working on this project, including the Design Team. It is important to note that design Team Professionals must be licensed in the State of Washington. The narrative must also include the trades for subcontractors and the names of subcontractors who will be working on this project. Manufacturer product information is to be included as an attachment to the narrative.
The narrative shall demonstrate the Offeror's ability to effectively coordinate trades, manage resources and subcontractors, and complete the project within the approved schedule. It should also highlight the critical phasing of work and the Offeror's ability to ensure the delivery of a quality product and service.
This factor is Acceptable if the Offeror:
Submits a 5-page maximum narrative that describes the offeror’s technical approach and management plan for the project demonstrating an acceptable understanding of the job responsibilities and requirements, and strategy for completing the construction within the project limit in accordance with the
Statement of Work.
If the Proposed plan and Management Approach that do not demonstrate the minimum requirements as stated above, Factor 1 will be rated “UNACCEPTABLE”.
Factor 2: Experience on Comparable Projects:
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 12
The offeror shall submit a minimum of three with a maximum of four project examples demonstrating relevant experience. Each project example shall be no more than two pages. “Relevant” is defined as projects similar to the project described in this RFP in scope, magnitude and complexity and have a logical connection with the requirements of this RFP. Examples shall include Offeror’s ability to effectively coordinate trades, ability to complete projects within the approved schedule, and critical phasing of work. Narrative should demonstrate offerors’ ability to ensure delivery of quality product and service; effectively control costs, manage contract changes; complete projects within the approved schedule; and management of resources/subcontractors.
Offerors shall submit a current Point of Contact (POC) for each project. The POC information shall include the name, phone number, and email address for each project submitted. The Government reserves the right to contact the point of contact provided by the offeror to verify the offeror’s experience on comparable projects. All projects submitted must be at least 75% complete or must have been completed within the last three (3) years from the date proposals are due for this RFP.
Standard of Evaluation:
This factor is Acceptable if the Offeror:
Submits 3 to 4 acceptable comparable projects that demonstrates relevant experience that are similar to the project described in this RFP in scope, magnitude, and complexity with a logical connection with the requirements of this RFP. The offeror’s submission narrative explains the offeror’s ability to ensure delivery of a quality product and service that highlights cost controls, management of contract changes, project completion within approved schedules and management of resources/subcontractors will be rated
“ACCEPTABLE”.
If Experience on Comparable Projects that do no demonstrate minimum requirements as stated above in Factor 2 will be rated “UNACCEPTABLE”.
Factor 3 – Schedule:
The offeror shall submit a fully developed Critical Path Method (CPM) project schedule showing the order in which the Offeror proposes to perform the work. The schedule shall include the dates on which the Offeror anticipates starting and completing the work (including design time, acquiring materials, mobilization, labor, equipment, construction, commissioning, demobilization). The schedule shall be in the form of a progress chart of suitable scale to indicate the percentage of work scheduled for completion by any given date during the construction period. In addition to the schedule, Offeror is to provide a
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 13 narrative not to exceed three (3) pages describing scheduling and coordination. The narrative shall identify milestones critical to the project, schedule coordination to meet construction time frame, inspection and testing, submittals, long lead items. The Narrative should clearly define the offerors’ understanding of the project and ability to meet the construction period of performance requirements as described in the RFP Statement of Work.
Standard of Evaluation:
This factor is Acceptable if the Offeror:
Submits an acceptable fully developed Critical Path Method (CPM) project schedule with a narrative not to exceed 3 pages that shows the order the Offeror proposed to perform the work with dates of anticipated start and completion of the work (including design time, acquiring materials, mobilization, labor, equipment, construction, commissioning, and demobilization). The narrative clearly defines the offeror’s understanding of the project and demonstrates ability to meet the construction period of performances as described in the RFP Statement of Work.
If the Schedule does not show the minimum requirements as stated above, Factor 3 will be rated “UNACCEPTABLE”.
Factor 4: Past Performance of Offeror:
Provide a minimum of two references (i.e., name, title, telephone phone number, and project title/description) who can verify that YOUR company provided recent devices and required attachments of similar scope and complexity as required herein. "Recent" is defined as "within the past three years.” Past Performance references may be contacted. The Government may also consider any additional past performance information that is available. Offerors are reminded that, while the Government may elect to consider data obtained from other sources, the burden of providing thorough and complete performance information rests with the Offeror.
The present/past performance assessment will also be evaluated using information gleaned from the references provided by the Offeror, as well as any other information available to the Government to include, but not limited to the Past Performance Information Retrieval System (PPIRS) and Federal Awardee Performance and Integrity Information System (FAPIIS). If an Offeror receives/received below a ‘satisfactory’ from any references, Provided Reference, PPIRS, and/or FAPIIS, the Offeror will receive and ‘unacceptable’ rating and will no longer be considered for award. Note: Offerors are reminded that, while the Government may elect to consider data obtained from other sources, the burden of providing thorough and complete performance information rests with the Offeror.
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 14
Standard of Evaluation:
This factor is Acceptable if the Offeror:
Submits past performance information that provides the Government with a reasonable expectation that the offeror will successfully perform the required effort or the offeror’s past performance is unknown; this factor will be rated as ACCEPTABLE.
If based on the offeror’s past performance, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort, this factor will be rated as UNACCEPTABLE.
In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”
II.E. Other Information to Submit with Proposal
(1) Representations and Certifications
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management.
Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).
(2) Qualifications of Offerors
Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.
Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.
(3) Proprietary Information Agreement(s)
Offerors are advised that employees of the firm(s) identified below may require access to your firm’s proprietary information in performing advisory and assistance services for the Government under separate contract. These individuals will be authorized access only to such information that is necessary to enable them to perform their respective duties. Such firm(s) are expressly prohibited from competing on the subject acquisition.
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 15 https://www.sam.gov/
Company: Turner & Townsend Heery, LLC Address: 3550 Lenox RD NE STE 2300. Atlanta, GA 30326-4333 Email: carlolyn.norwood@cbre.com or scott.martin@turntown.com Phone: 404-946-2432 or 443-690-5873
Pursuant to FAR Part 9.505-4(b), these firms must execute an agreement with each offeror that states that they will (1) protect the offerors’ information from unauthorized use or disclosure for as long as it remains proprietary and (2) refrain from using the information for any purpose other than that for which it was furnished.
To expedite the evaluation process, each offeror must contact the above-listed firm(s) to effect execution of such an agreement prior to the submission of proposals. Each offeror must submit copies of any such agreement(s) with their proposal.
III. General Provisions III.A. Availability of Funds Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 15 calendar days. Prospective Offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 16 http://www.sba.gov/ http://www.sba.gov/
III.D. Information Concerning the Disclosure of Solicitation Results This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement.
Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
III.H. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment Completed CPARS evaluations may then be used by Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 17 http://www.cpars.gov/ http://www.cpars.gov/ well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
IV. FAR/GSAR Solicitation Provisions IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101–29, and copies of Federal specifications, standards, and product descriptions can be downloaded from the ASSIST website at https://assist.dla.mil.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a copy of specifications, standards, and
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 18 https://www.cpars.gov/lc.htm https://assist.dla.mil https://assist.dla.mil commercial item descriptions cited in this solicitation may be obtained from the ASSIST website identified in paragraph (a) of this provision.
(End of provision)
IV.B. FAR 52.216-1 Type of Contract (APR 84) The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 14)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
IV.D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999) (Applicable to solicitations resulting in construction contracts in excess of $10,000.)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade
Goals for Female Participation for Each Trade
6.2% 6.9%
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 19 the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade.
The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Washington State, Pierce County, City of Tacoma.
IV.E. Buy American Requirements
FAR 52.225-10 Notice of Buy American Requirement-Construction Materials (MAY
2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 20 https://www.acquisition.gov/far/part-52#FAR_52_225_9 response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
IV.F. Buy American Exceptions For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement
IV.G. FAR 52.233-2 Service of Protest (SEP 06)
(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 21 https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.acquisition.gov/far/part-52#FAR_52_225_9 https://www.gsa.gov/forms-library/solicitation-offer-and-award-construction-alteration-or-repair the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
IV.H. FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 98) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:
Federal Acquisition Regulation
NUMBER TITLE DATE
52.204-22 Alternative Line Item Proposal JAN 17
52.214-34 Submission of Offers in the English Language
APR 91
52.215-16 Facilities Capital Cost of Money JUN 03 52.236-28 Preparation of Proposals - Construction OCT 97
IV.I. GSAR Clause 552.102 Incorporating Provisions and Clauses This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
IV.J. Additional Provisions
i. FAR 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain
Federal Transactions (Sept 2007)
ii. FAR 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than
Certified Cost or Pricing Data (Nov 2021)
iii. FAR 52.252-3 Alterations in Solicitation (Apr 1984)
V. Instructions and Clauses V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (NOV 2021)
(a) Definitions. As used in this provision-
Document: C201-SB LPTA/April 2024 (The Solicitation)
47PL0324R0001, Volume 1 - RFP Page 22 https://www.acquisition.gov/browse/index/far
Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
In writing, "writing," or "written" means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
Proposal modification is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
Time, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include…