Questions and Answers 47PK0224R0007 AMENDMENT 0001 PB VTE SVCS.xlsx

XLSX spreadsheet 9 KB Posted

Attached to
FULL ELEVATOR MAINTENANCE, REPAIR, AND REPLACEMENT SERVICES
Solicitation number
47PK0224R0007
Issued by

About this file

This document contains Questions and Answers from Solicitation 47PK022R0007 for Full Elevator Maintenance, Repair, and Replacement Services at the Phillip Burton Federal Building and U.S. Courthouse. The incumbent contractor is Star Elevator, who was awarded a $229,518 bridge contract for 6 months. The solicitation allows the use of subcontractor or joint venture partner experience and past performance to fulfill the experience requirements. The equipment was modernized to iControl with AC Imperial Gearless. The solicitation is for full elevator maintenance, repair, and replacement services at the Phillip Burton Federal Building and U.S. Courthouse in San Francisco, CA. The contracting agency is the General Services Administration's Public Buildings Service Region 9.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Questions and Answers from Solicitation 47PK022R0007, Full Elevator Maintenance, Repair, and Replacement Services at the Phillip Burton Federal Building and U.S. Courthouse

Question 1: What is the name of the incumbent contractor and amount of award?

Answer: Star Elevator $229, 518 for a 6-month bridge contract.

Question 2: Can we use the experience and past performance of our hired mechanic and/or subcontractor to fulfill the experience requirements?

Answer: Reference M.4.1 of the solicitation, for Prime Contractor/Subcontractor and Joint Venture partnerships, the Experience and Past Performance will be evaluated based on both the Prime/Sub. The Joint Venture will be evaluated based on the Experience and Past Performance of each party to the joint venture. In M.5 of the solicitation, in the case of a Prime/Sub partnership, the past performance of the Prime and Subcontractor will be evaluated.
Question 3: What type of equipment was this modernized to?

Answer: iControl with AC Imperial Gearless