4_CMc_Agreement_-_Greenville_MS.pdf

PDF 313 KB Posted

Attached to
Construction Manager as Constructor (CMc) Contract for the New US Courthouse in Greenville, MS. Federal contract opportunity
Solicitation number
47PH0819R0003
Issued by
General Services Administration Public Buildings Service

About this file

This selection-step request for proposal is for a construction manager as constructor contract to build a new United States Courthouse in Greenville, Mississippi. The General Services Administration Public Buildings Service will award the contract for design phase services and a guaranteed maximum price construction option. Five construction firms will receive the RFP and are invited to participate in the selection step: Caddell Construction Corp, LLC; Hoar Construction; Roy Anderson Corp Contractors; WG Yates & Sons Construction Company; and White Construction Company. An industry outreach meeting will be held on October 9, 2019 for representatives from large and small businesses to discuss subcontracting opportunities for the project.

The Agreement

View the file

Other files for this federal contract opportunity

Other files attached to Construction Manager as Constructor (CMc) Contract for the New US Courthouse in Greenville, MS., newest first.
File Type Posted
Greenville_MS_Solicitation_Amendment_No._1.pdf PDF
8_GSA527.pdf PDF
1_CMc_Solicitation_-_Greenville_MS.pdf PDF
7_Greenville_CMc_Solicitation_Bus_Util_Form_11022018.pdf PDF
6_Appendix_A_-_PPQ_Form_-_Greenville_MS.pdf PDF
3_SF1442.pdf PDF
9_Wage_Rates_-_MS180137_-_2018_08_31.pdf PDF
2_Reps_&_Certs_Greenville_MS_Cthse_CMc.pdf PDF
5_CMc_SOW_Greenville,_MS_(r1)_2018.12.11.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sol. Reference No. 47PH0819R0003

Document: CMc101/May 2018 (The Agreement)

Construction Manager as Constructor (CMc) Contract for the New U.S.

Courthouse in Greenville, Mississippi The Agreement

Table of Contents

I. Project Information A. Project Summary B. The Contract C. Period Of Performance D. Work Conditions/Site Requirements E. Authorized Representatives F. Contract Liquidated Damages Rate G. Buy American Exceptions H. Statement of Work, Specifications, Drawings, Exhibits and Other Attachments

II. Prices

A. Basis of Pricing B. Contract Price Form

III. Terms and Conditions

A. Definitions B. Contractor Responsibilities C. Contractor Management and Personnel D. Project Schedule E. Extensions of Time F. Interpretation of Specifications and Drawings G. Submittals H. Substantial Completion and Contract Completions I. Use and Possession Prior to Substantial Completion J. Finality of Contract Modifications K. Liquidated Damages L. Insurance Requirements M. Performance and Payment Bonds N. Order of Precedence O. Administrative Matters P. Non-Compliance with Contract Requirements Q. Safeguarding Sensitive Data and Information Technology Resources R. Apprenticeship Plans S. Equal Employment Opportunity Plan

IV. Contract Clauses

A. Public Building Services Contract Clauses B. Clauses Incorporated in Full Text C. Additional Clauses D. Clauses Incorporated by Reference E. Subcontract Requirements

I. Project Information

I.A. Project Summary

This is a Construction Manager as Constructor (CMc) Contract, and includes requirements for the Design Phase Services and the option(s) for Construction Services at a Guaranteed Maximum Price (GMP) Option.

The General Services Administration (GSA), Public Buildings Service (PBS) intends to construct a new U.S. Courthouse, located at 200 Washington Avenue in Greenville, MS. The new building will be approximately 62,000 gross square feet containing 2 courtrooms (1 District and 1 Magistrate), 3 judicial chambers, prisoner detention areas, and 17 secure, interior parking spaces. Tenant agencies will consist of the U.S. District Court, U.S. Probation Office, U.S.

Department of Justice – Marshals Service, and a GSA PBS Field Office. GSA will design and construct the courthouse in accordance with the PBS Facilities Standards (GSA P100), U.S.

Courts Design Guide, U.S Marshals Service Publication 64 and all other applicable Federal standards/requirements. The new courthouse will meet the 10-year space needs of the court and court-related agencies and the site will accommodate the 30-year needs of the court.

I.B. The Contract

(1) The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.

(2) The Construction Documents, as that term is defined in this Agreement, shall be deemed incorporated into the Contract Documents upon acceptance of all deliverables described in the Design Phase Services Statement of Work, and shall supersede and replace all Specifications and Drawings contained in the Contract Documents at award of the Contract.

(3) In consideration for, and upon condition of, the Contractor's completion of the Design Phase Services, GSA shall pay the Contractor the firm-fixed-price for Design Phase Services, subject to the terms and conditions set forth in this Contract. If the GMP Option is exercised, then the Contractor shall be required to complete the Construction Services. In consideration for completion of the Construction Services under the GMP Option, the Contractor shall be entitled to the allowable cost of performance not to exceed the GMP, subject to the terms and conditions set forth in this Contract.

(4) The construction work includes all construction work on the project, including the Work performed under the GMP Option, any firm-fixed-price options, or any Contract modifications for construction work. Any construction work performed under this Contract includes all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the construction work described in and reasonably inferable from the Contract Documents, whether temporary or permanent.

I.C. Period of Performance

(1) Design Phase Services

(a) Commencement of Design Phase Services. The Contractor shall commence performance of the Design Phase Services within 10 days after the Contractor receives the Notice to Proceed (NTP).

(b) Completion of Design Phase Services. Design Phase Services shall be complete upon acceptance of all deliverables required by the Design Phase Services Statement of Work.

(2) Construction Services (the Work)

(a) Commencement of the Work. If the Government exercises the GMP Option, the Contractor shall commence performance of the construction within 10 days after the Contractor receives the Notice to Proceed (NTP) for the Work.

(b) Substantial Completion. If the Government exercises the GMP Option, the Contractor shall achieve Substantial Completion of the Construction Phase Work, as that term is defined in this Agreement, no later than 700 calendar days from issuance of Notice to Proceed (NTP)) for the Work.

(3) Contract Completion.-Construction Services. If the Government exercises the GMP Option, the Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 90 calendar days of Substantial Completion.

I.D. Work Conditions/Site Requirements

The work under this requirement is for new construction at a vacant site.

I.E. Authorized Representatives

(1) This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties). References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:

Authorized Representative Information:

Contracting Officer’s Information

Name: Carrie Haman

Address: 819 Taylor Street, Rm 12B-371, Fort Worth, TX 76102

Telephone: 817-978-6163

Email: carrie.haman@gsa.gov

(2) GSAR 552.236-71, Authorities and Limitations, is incorporated by reference in this Contract.

I.F. Contract Liquidated Damages Rate In accordance with “Liquidated Damages” clause in Section III (Terms and Conditions), liquidated damages shall be calculated at the rate of $5,000.00 per calendar day.

I.G. Buy American Exceptions For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.

I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments

The following documents are incorporated by reference into this Contract.

(1) Statement of Work for GSA Solicitation No. 47PH0819R0003

(2) Specifications for GSA Solicitation No. 47PH0819R0003

(3) Construction Drawings for GSA Solicitation No. 47PH0819R0003

(4) David-Bacon Wage Determination

(5) Small Business Subcontracting Plan, if required

II. Prices

II.A. Basis of Pricing

(1) Contract Prices. All Contract prices set forth in this Section include all costs, including, but not limited to the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit, necessary to complete the Design Phase Services (Base Contract), and firm-fixed-price options for construction work, if any, in accordance with the Contract Documents. For pricing information regarding the GMP Option, see Paragraph IV.A., Construction Manager as Constructor (CMc) Guaranteed Maximum Price with CMc Contingency Allowance and Shared Savings.

(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract. The Contractor is presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.

(3) Unit Prices and Allowances. If any portion of the construction work is to be performed on a unit price basis (Unit Priced Work), the unit price established in the Contract shall include all costs of coordinating and incorporating the Unit Price Work into the construction work. The Contractor shall only be obligated to perform Unit Priced Work to the extent that an allowance has been established in an amount sufficient to compensate the Contractor for such Unit Priced Work at the established unit prices. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is sufficient only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.

(4) Firm-fixed-price Options. If any portion of the construction work is to be performed upon the timely exercise of a firm-fixed-price option, the option price shall include all costs of coordinating and incorporating such work into the remaining construction work. An adjustment to the Contract price for such additional work shall be computed solely on the basis of the option price or prices set forth herein.

(5) Work Packages. The Contractor and the Government may agree to develop firm-fixed-price early work packages for construction work that stand alone from the remainder of the Work.

The Parties must agree bilaterally to the scope, schedule and pricing for any such work package, and Contract must be modified accordingly. If such work package reduces the scope of the Construction Services under the GMP Option, the Estimated Cost of the Work (ECW) shall be reduced, and the CMc Contingency Allowance (CCA), Fee and GMP shall be adjusted accordingly. These early work packages become definitive firm-fixed-price line items in the Contract, and they shall include specific completion milestones.

(6) Bid Rates. If this Contract includes Bid Rates to be used in determination of equitable adjustments (e.g., overhead, profit, daily rates for time-related costs), such rates shall be deemed to include all costs recoverable as components of an equitable adjustment consistent with the requirements, definitions, and exclusions applicable to equitable adjustments set forth in this Contract, and consistent with the Contractor's cost accounting practices. Unless otherwise specified, the bid rates shall be deemed to include only the Contractor's costs, and not the costs of any subcontractors.

(7) Shared Savings. The Contractor shall be entitled to 30% of any Shared Savings (see Paragraph IV.A., Construction Manager as Constructor (CMc) Guaranteed Maximum Price with CMc Contingency Allowance and Shared Savings.

II.B. Contract Price Form

Standard Form (SF) 1442, Solicitation, Offer, and Award

III. Terms and Conditions III.A. Definitions

(1) "Design Phase" means the phase of the Project during which the design is developed and completed.

(2) "Design Phase Services" means design phase construction management services, constructability reviews and other related services as described in the Statement of Work.

(3) "Construction Documents" mean the 100% complete specifications and construction drawings developed during the Design Phase.

(4) "Work" means the Construction Services under the GMP Option

III.B. Contractor Responsibilities

(1) During the Design Phase Services, it is the Contractor's responsibility to familiarize itself with all design information (e.g., draft specifications, drawings, etc.) provided for its review. The Contractor shall be responsible for satisfying itself that the Project as described in the design information is constructible using commercially practicable means and methods; that the construction work is described in the design documents with sufficient completeness to enable pricing of a complete Project within the GMP; and that the manner of presentation and organization of information in the design documents enables accurate estimation of the Cost of the Work. Prior to establishment of the final ECW, the Contractor shall bring to the Contracting Officer's attention all instances that it has discovered or has been made aware of where omission of design information affects the Contractor's ability to accurately estimate the Cost of the Work.

(2) The Contractor is responsible for performing the Design Phase Services in accordance with the Statement of Work, and the Contractor shall submit to the Contracting Officer all deliverables and reports in accordance with the Statement of Work.

(3) The Contracting Officer has sole discretion to accept or reject all or part of any proposal by the Contractor related to design.

(4) Within 30 days after award, the Contractor shall provide a schedule for the Design Phase Services in Gantt chart format indicating tasks and milestones for deliverables.

(5) Commencement, Prosecution, and Completion of Work

FAR 52-211-10, Commencement, Prosecution, and Completion of Work, is supplemented as follows:

Upon exercise of the GMP Option or issuance of a modification commencing construction work, the Contractor shall not commence performance until the Contracting Officer has issued NTP for the Work. The Contractor shall diligently prosecute the construction work so as to achieve Substantial Completion within the time specified in Paragraph I.C. of the Agreement. If this Contract specifies different completion dates for different phases or portions of the construction work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.

(6) For the purposes of FAR 52.236-1, Performance of Work by the Contractor, the Contractor shall perform at least 12 percent of the construction work. The Contractor shall furnish the Contracting Officer within 10 days after the award of the construction option, a letter outlining the items of work he will perform with his own forces

(7) Unless otherwise expressly stated in the Contract, the Contractor shall be responsible for all means and methods employed in the performance of the Contract.

(8) The Contractor shall be responsible for coordinating all activities of subcontractors. This responsibility includes coordination of: preparation of shop drawings produced by different subcontractors where their work interfaces or may potentially conflict or interfere and the installation of such work; scheduling of work by subcontractors; and use of the Project site for staging and logistics.

(9) Where installation of separate construction work components as shown in the Contract Documents will result in conflict or interference between such components or with existing conditions, including allowable tolerances, it is the Contractor's responsibility to bring such conflict or interference to the attention of the Contracting Officer and seek direction before fabrication, construction, or installation of any affected construction work. If the Contractor fabricates, constructs, or installs any work prior to receiving such direction, the Contractor shall be responsible for all cost and time incurred to resolve or mitigate such conflict or interference.

(10) The Contractor must submit a project specific safety plan before commencing construction work.

(11) Where Drawings show construction work without specific routing, dimensions, locations, or position relative to other work or existing conditions, and such information is not specifically defined by reference to Specifications or other information supplied in the Contract Documents, the Contractor is responsible for routing, dimensioning, and locating such work in coordination with other work or existing conditions in a manner consistent with Contract requirements.

(12) It is not the Contractor's responsibility to ensure that the Contract Documents comply with applicable laws, statutes, building codes and regulations. If it comes to the attention of the Contractor that any of the Contract Documents do not comply with such requirements, the Contractor shall promptly notify the Contracting Officer in writing. If the Contractor performs any of the construction work prior to notifying and receiving direction from the Contracting Officer, the Contractor shall assume full responsibility for correction of such work, and any fees or penalties that may be assessed for non-compliance.

(13) The Contractor shall immediately bring to the Contracting Officer's attention any hazardous materials or conditions not disclosed in the Contract Documents discovered by or made known to the Contractor during the performance of the Contract

(14) The Contractor shall be liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance of services furnished under this Contract. Neither the Government’s review or acceptance of, nor payment for, the design services required under this Contact shall be construed as a waiver of any rights under this Contract or of any cause of action arising out of the performance of this Contract.

III.C. Contractor Management and Personnel

(1) The Contractor shall designate a principal of the firm or other senior management official to provide executive oversight and problem resolution resources to the Project for the entire life of the Contract, including the GMP Option.

(2) FAR 52.236-6, Superintendence by the Contractor, is supplemented as follows:

(a) The Contractor shall employ sufficient management and contract administration resources, including personnel responsible for project management, field superintendence, change order administration, estimating, coordination, inspection, and quality control, to ensure the proper execution and timely completion of the construction work.

(b) The Contractor shall employ, and require its subcontractors to employ, qualified personnel to perform the construction work. The Government reserves the right, at no additional cost to the Government, to exclude, or remove from the site or building, any personnel for reasons of incompetence, carelessness, or insubordination, who violate rules and regulations concerning conduct on federal property, or whose continued employment on the site is otherwise deemed by the Government to be contrary to the public interest.

(c) Repeated failure or excessive delay by the Contractor to provide qualified personnel shall be deemed a default for the purposes of the Termination for Default clause.

III.D. Project Schedule

(1) The Contractor shall develop a Design Phase Project Schedule to plan, coordinate, and perform the services during the design phase. This schedule shall be produced using widely used, commercially available computer software such as Microsoft Project,®. The schedule will be coordinated with the Architect's schedule of design submissions and show milestones for completion of Design Reviews and cost reconciliation. It will also include a milestone for establishing the ECW for the construction option.

(2) Within 30 days after establishing the final ECW, the Contractor shall submit its Construction Phase Project Schedule (hereinafter, the Project Schedule) to the Contracting Officer, together with a written narrative describing the major work activities, activities on the critical path, and major constraints underlying the sequence and logic of the Project Schedule.

The Contractor shall use a Critical Path Method ("CPM") Project Schedule to plan, coordinate, and perform the Work under the GMP Option. The Project Schedule shall be produced using widely used, commercially available computer software that is capable of generating and monitoring a CPM schedule and is compatible with Meridian Proliance.® For example, compatible software includes Microsoft Project,® Primavera P6. The contractor shall submit the Project Schedule in both electronic and hardcopy print format.

The Project Schedule shall depict all activities necessary to complete the Construction Phase, including, as applicable, all submittal and submittal review activities, all procurement activities, and all field activities, including mobilization, construction, start-up, testing, balancing, commissioning and punchlist.

All activities identified in the Project Schedule’s work breakdown structure (WBS) shall be resource-loaded and cost-loaded to facilitate Earned Value (EV) analysis over the course of the project. The Contractor should anticipate that the Project Schedule will be subject to review and revision and the Contractor shall devote sufficient resources for meetings, revisions, and resubmissions of the Project Schedule to address exceptions taken by the Contracting Officer.

III.E. Extensions of Time FAR 52.211-13, Time Extensions, is supplemented as follows:

(1) If the Contractor requests an extension of the time for Substantial Completion, the Contractor shall base its request on analysis of time impact using the Project Schedule as its baseline, and the new Substantial Completion date projected by the Project Schedule as revised to account for the impact. The Contractor's request must be submitted to the Contracting Officer in writing, and set forth facts and analysis in sufficient detail to enable the Contracting Officer to evaluate the Contractor's entitlement to an extension of time.

(2) The Contractor shall only be entitled to an extension of time to the extent that Substantial Completion of the Work is delayed by causes for which the Contractor is not responsible under this Contract and to the extent that the actual or projected Substantial Completion date is later than the date required by this Contract for Substantial Completion.

(3) The Contractor shall not be entitled to an extension of time if the Contractor has not updated the Project Schedule in accordance with this Contract.

(4) The Government shall not be liable for any costs, incurred by the Contractor, to mitigate time impacts that occur within 30 calendar days after the date the Contractor submits a request for extension of time complying with this clause.

III.F. Interpretation of Specifications and Drawings FAR 52.236-21, Specifications and Drawings for Construction, and GSAR 552.236-77, Specifications and Drawings, are supplemented as follows:

(1) For the purposes of FAR 52.236-21, GSAR 552.236-77 and this section (“Interpretation of Specifications and Drawings”), specifications and drawings refer only to the Construction Documents.

(2) Different requirements within the Contract Documents shall be deemed inconsistent only if compliance with both cannot be achieved.

(3) Unless otherwise noted, the drawings shall be interpreted to provide for a complete construction, assembly, or installation of the Work, without regard to the detail with which material components are shown in the drawings.

III.G. Submittals FAR 52.236-21, Specifications and Drawings for Construction, GSAR 552.236-78, Shop Drawings, Coordination Drawings, and Schedules, and GSAR 552.236-79, Samples are supplemented as follows:

(1) During performance of the construction work, the Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all work components as specified elsewhere in this Contract. If particular submittal requirements are not specified for a component of the work, the Contractor shall prepare submittals for such work as directed by the Contracting Officer.

(2) The Contractor shall not proceed with construction work or procure products or materials described or shown in submittals until the Contracting Officer has indicated approval of the submittal. Any work or activity undertaken prior to approval shall be at the Contractor’s risk;

should the Contracting Officer subsequently determine that the work or activity does not comply with the Contract, the Contractor shall be responsible for all cost and time required to comply with the Contracting Officer's determination. The Contracting Officer shall have the right to order the Contractor to cease execution of construction work for which submittals have not been approved. The Government shall not be liable for any cost or delay incurred by the Contractor attributable to the proper exercise of this right.

(3) The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule; provided, that the Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty (20) business days.

III.H. Substantial Completion and Contract Completion FAR 52.211-10, Commencement, Prosecution, and Completion of Work, FAR 52.211-12, Liquidated Damages (Construction), and GSAR 552.246-72, Final Inspection and Tests, are supplemented as follows:

(1) For the purposes of FAR 52.211-10, Commencement, Prosecution and Completion of Work, and FAR 52.211-12, Liquidated Damages (Construction) the "Work" is the Work under the GMP Option. The Work shall be deemed complete when it is “Substantially Complete.” For phased construction, each phase is subject to a separate Substantial Completion date, as established in this Contract. The Work shall be deemed "Substantially Complete" if and only if the Contractor has completed the Work and related Contract obligations in accordance with the Contract Documents, such that the Government may enjoy the intended access, occupancy, possession, and use of the entire Work without impairment due to incomplete or deficient work, and without interference from the Contractor's completion of remaining work or correction of deficiencies in completed work. In no event shall the Work be deemed Substantially Complete if all fire and life safety systems are not tested and accepted by GSA, where such acceptance is required under the Contract.

(2) With reasonable advance notice, the Contractor shall submit to the Contracting Officer a written proposal recommending a Substantial Completion date (Notice of Substantial Completion). The Contracting Officer shall conduct inspections and make a determination of Substantial Completion within a reasonable time. If the Contracting Officer takes exception to the Notice of Substantial Completion, the Contractor shall be entitled to a written notice of conditions precluding determination of Substantial Completion.

(3) The Contractor shall only be entitled to an extension of time to address such conditions if, and to the extent that, the Contracting Officer provides notice of such conditions more than thirty

(30) calendar days after receipt of the Notice of Substantial Completion.

(4) Substantial Completion shall be established by the Contracting Officer's issuance of a written determination specifying the date upon which the Work is Substantially Complete.

(5) The Contract is complete (Contract Completion) if and only if the Contractor has completed all Work and related Contract obligations, corrected all deficiencies and all punch list items, and complied with all conditions for final payment.

(6) The Contractor shall not be entitled to final payment or release of any retainage held by the Government until after Contract Completion. If the Contractor does not achieve Contract Completion within the time required by this Contract, the Government shall be entitled, after providing notice to the Contractor, to complete any work remaining unfinished. The Contractor shall be liable to the Government for all costs incurred by the Government to complete such work.

III.I. Use and Possession Prior to Substantial Completion FAR 52.236-11, Use and Possession Prior to Completion, is supplemented as follows:

Exercise by the Government of the right conferred by FAR 52.236-11 shall not relieve the Contractor of responsibility for completing any unfinished components of the Work.

III.J. Finality of Contract Modifications It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing for such an adjustment, adjustments to the ECW or GMP or period of performance agreed upon therein shall be deemed to provide all adjustment to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to adjustment on account of the change or other condition giving rise to the modification.

III.K. Liquidated Damages FAR 52.211-12, Liquidated Damages is supplemented as follows:

(1) The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work within the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Section I (Project Information), paragraph entitled, “Liquidated Damages Rate,” for each calendar day following the required completion date that the Work is not Substantially Complete.

(2) If the Contract requires different completion dates for different phases or portions of the Work, the Contractor shall be liable for liquidated damages at the specified rate for each calendar day following the required completion date that the phase or portion of Work is not Substantially Complete. If a single rate is specified, the specified rate shall be apportioned between the different phases or portions of the Work.

(3) If the Government elects to accept any portion of the Work not specifically designated as a phase or portion of Work with its own required completion date, the liquidated damage rate shall be apportioned between accepted work and uncompleted work, and the Contractor's liability for liquidated damages shall be computed accordingly.

III.L. Insurance Requirements

(1) The Contractor shall obtain and maintain for the entire life of the Contract, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, and GSAR 552.228-5, Government as Additional Insured.

(a) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $2,000,000. If occupational diseases are not covered by workers' compensation insurance, Employers' liability coverage shall include occupational diseases.

(b) Broad form comprehensive commercial general liability insurance in the amount of at least $5,000,000 per occurrence. Such insurance shall include, but not be limited to, contractual liability, bodily injury and property damage.

(c) Comprehensive automobile liability covering the operation of all automobiles used in connection with performing the Contract in the amount of at least $1,000,000 per person and

$2,500,000 per occurrence for bodily injury and $1,000,000 per occurrence for property damage.

(2) The Contractor shall promptly provide to the Contracting Officer proof that it has obtained insurance required by the Contract in the form of certificates of insurance. The Contractor shall submit to the Contracting Officer all renewal certificates issued during the life of this Contract immediately upon issuance.

III.M. Performance and Payment Bonds FAR 52.228-15, Performance and Payment Bonds – Construction, is supplemented as follows:

(1) "Original Contract Price" means the GMP established at award of this Contract.

(2) The Contractor shall furnish required performance and payment bonds within 14 days of exercise of the GMP Option.

(3) Receipt by the Government of required performance and payment bonds is a condition precedent to issuance of the NTP.

III.N. Order of Precedence Different requirements within this Contract shall be deemed inconsistent only if compliance with both cannot be achieved. In case of inconsistency between Contract Documents, the following order of precedence shall apply:

(1) Section IV of the Agreement

(2) Sections I, II, and III of the Agreement

(3) The Statement of Work

(4) The Specifications

(5) The Drawings

(6) Exhibits and Other Attachments

III.O. Administrative Matters

(1) Project Meetings. The Contractor shall attend and participate in regularly scheduled Project meetings.

(2) Design Phase Services Payments. Within 30 days of award, the CMc will submit a payment schedule for design phase services which reflect the design reviews and various deliverables in the Design Phase schedule for approval. Progress Payments during the design phase will be based on the approved schedule.

(3) Schedule of Values. Within 30 days after the Contract is modified to incorporate a final ECW, and in addition to any other requirements set forth in the Contract Documents (e.g., cost loaded schedule), the Contractor shall prepare and submit for approval a Schedule of Values, which shall be derived from the cost loaded schedule. The Contractor may bundle individual cost loaded schedule activities to simplify major work activities. The Contractor shall establish a separate value for bonds, mobilization, insurance, and as otherwise approved by the Contracting Officer. The schedule of values must be reconciled monthly with the open books for actual costs allocated.

(4) Payments. The Government shall make progress payments based upon the Design Phase Services Payment Plan and the Schedule of Values for the Work, as applicable. All payments will be credited to the Government in the establishment of the Final Settlement. Requirements for invoices are supplemented as follows:

(a) Before submitting a request for payment, the Contractor shall attend preinvoice payment meetings each month, as scheduled, with the designated Government representative for the purpose of facilitating review and approval of payment requests. Payment meetings may be conducted in person or by telephone. The Contractor shall provide documentation to support the prospective payment request.

(b) The Contractor shall submit its invoices to the Contracting Officer. Separate payment requests shall be submitted for progress payments, payments of retainage, and partial or final payments.

(c) If the invoice does not meet the requirements of FAR Clause 52.232-27 (a)(2) and the requirements specified in Subparagraphs (4)(a),(d),(e), and (f) of this Payments provision, or the requirements for a Critical Path Method (CPM) Project Schedule, the Contracting Officer may return the invoice to the Contractor without payment for correction. If the Contracting Officer disputes the requested payment amount, the Government may pay the portion of the requested payment that is undisputed.

(d) Invoices shall be submitted in an original and two (2) copies to the designated billing office specified in this Contract or in individual delivery/work orders.

(e) Invoices must include the Account Document Number (ADN) assigned at award.

(f) The Contractor shall submit the following information or documentation with each invoice:

(i) For construction payments, GSA Form 184 - Construction Progress Report (construction work Only) or AIA Form G702, including the updated Schedule of Values upon which the payment request is based;

(ii) For construction payments, GSA Form 2419 - Certification of Progress Payments Under Fixed-Price Construction Contract;

(iii) For other payments including design phase payments, the invoice must identify deliverables and services rendered for that progress payment in accordance with the contract;

(iv) The payment terms that apply for the particular services rendered;

(v) CPM Project schedule that complies with the Contract Documents

(vi) Additional documentation: Not applicable

(g) GSA will not be obligated to issue final payment unless the Contractor has furnished to the Contracting Officer a release of claims against the Government relating to this Contract, and submitted all required product warranties, as-built drawings, operating manuals, and other items as specified in the Contract. The Contractor may reserve from the release specific claims only if such claims are explicitly identified with stated claim amounts. All release forms must bear the original signature of the signer and must be affixed with the Contractor’s corporate seal or the seal of a Notary Public.

(5) Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:

(a) Progress Payments: 14 days

(b) Subsequent Subcontractor Payments: 7 days

(6) Payment Information. The General Services Administration (GSA) makes information on contract payments available electronically at http://www.finance.gsa.gov. The Contractor may register at the site and review its record of payments. This site provides information only on payments made by GSA, not by other agencies.

(7) Security Clearances. Contractor shall comply with the following requirements pertaining to security clearances.

(a) All personnel performing work under the Contract on the Project site must obtain an Enter on Duty (EOD) determination before they will be granted access to the site.

(b) To obtain an EOD determination, Contractor shall submit for all such personnel fingerprints on Form SF87 and a completed Contractor Information Worksheet (CIW). Detailed information is available at Detailed information is available at GSA Access Card . USAccess Credentialing Centers can be located at US Access Centers.

(c) In addition, all such personnel who will be on site 6 months or longer must apply for and receive clearance in accordance with Homeland Security Presidential Directive 12 (HSPD- 12). See Section IV, Contract Clauses, GSAR 552.204-9.

(8) Safeguarding and Dissemination of Sensitive But Unclassified (SBU) Building Information.

This clause applies to all recipients of SBU building information, including offerors, bidders, awardees, contractors, subcontractors, lessors, suppliers and manufacturers.

(a) Marking SBU. Contractor-generated documents that contain building information must be reviewed by GSA to identify any SBU content, before the original or any copies are disseminated to any other parties. If SBU content is identified, the Contracting Officer (CO) may direct the contractor, as specified elsewhere in this contract, to imprint or affix SBU document markings to the original documents and all copies, before any dissemination.

(b) Authorized recipients.

(i) Building information designated SBU must be protected with access strictly controlled and limited to those individuals having a legitimate business need to know such information.

Those with a need to know may include Federal, State and local government entities, and nongovernment entities engaged in the conduct of business on behalf of or with GSA.

Nongovernment entities may include architects, engineers, consultants, contractors, subcontractors, suppliers, utilities, and others submitting an offer or bid to GSA, or performing work under a GSA contract or subcontract. Recipient contractors must be registered as “active” in the System for Award Management (SAM) database at www.sam.gov and have a legitimate business need to know such information. If a subcontractor is not registered in the SAM and has a need to possess SBU building information, the subcontractor shall provide to the contractor its DUNS number or its tax ID number and a copy of its business license. The contractor shall keep this information related to the subcontractor for the duration of the contract and subcontract.

(ii) All GSA personnel and Contractors must be provided SBU building information when needed for the performance of official Federal, State, and local government functions, such as http://www.finance.gsa.gov/ http://www.gsa.gov/portal/category/107203 http://www.fedidcard.gov/centerlist.aspx for code compliance reviews and for the issuance of building permits. Public safety entities such as fire and utility departments may require access to SBU building information on a need to know basis. This clause must not prevent or encumber the dissemination of SBU building information to public safety entities.

c. Dissemination of SBU building information:

(i) By electronic transmission. Electronic transmission of SBU information outside of the

GSA network must use session encryption (or alternatively, file encryption). Encryption must be via an approved NIST algorithm with a valid certification, such as Advanced Encryption Standard (AES) or Triple Data Encryption Standard (3DES), in accordance with Federal Information Processing Standards Publication (FIPS PUB) 140-2, Security Requirements for Cryptographic Modules per GSA policy.

(ii) By nonelectronic form or on portable electronic data storage devices. Portable electronic data storage devices include, but are not limited to CDs, DVDs, and USB drives.

Nonelectronic forms of SBU building information include paper documents, among other formats.

1) By mail. Contractors must utilize only methods of shipping that provide services for monitoring receipt such as track and confirm, proof of delivery, signature confirmation, or return receipt.

2) In person. Contractors must provide SBU building information only to authorized recipients with a need to know such information. Further information on authorized recipients is found in Section 2 of this clause.

d. Record keeping. Contractors must maintain a list of all entities to which SBU is disseminated, in accordance with sections 2 and 3 of this clause. This list must include at a minimum: (1) the name of the State, Federal, or local government entity, utility, or firm to which SBU has been disseminated; (2) the name of the individual at the entity or firm who is responsible for protecting the SBU building information, with access strictly controlled and limited to those individuals having a legitimate business need to know such information; (3) contact information for the named individual; and (4) a description of the SBU building information provided. Once “as built” drawings are submitted, the contractor must collect all lists maintained in accordance with this clause, including those maintained by any subcontractors and/or suppliers, and submit them to the CO. For Federal buildings, final payment may be withheld until the lists are received.

e. Safeguarding SBU documents. SBU building information (both electronic and paper formats) must be protected, with access strictly controlled and limited to those individuals having a legitimate business need to know such information. GSA contractors and subcontractors must not take SBU building information outside of GSA or their own facilities or network, except as necessary for the performance of that contract. Access to the information must be limited to those with a legitimate business need to know.

f. Destroying SBU building information. When no longer needed, SBU building information must be destroyed so that marked information is rendered unreadable and incapable of being restored, in accordance with guidelines provided for media sanitization within GSA CIO IT Security 06-32, Media Sanitization Guide and Appendix A of NIST Special Publication 800-88, Guidelines for Media Sanitization. Alternatively, SBU building information may be returned to the CO.

g. Notice of disposal. The contractor must notify the CO that all SBU building information has been returned or destroyed by the contractor and its subcontractors or suppliers in accordance with paragraphs 4 and 6 of this clause, with the exception of the contractor's record copy. This notice must be submitted to the CO at the completion of the contract to receive final payment. For leases, this notice must be submitted to the CO at the completion of the lease term. The contractor may return the SBU documents to the CO rather than destroying them.

h. Incidents. All improper disclosures of SBU building information must be immediately reported to the CO at <insert address and contact information> . If the contract provides for progress payments, the CO may withhold approval of progress payments until the contractor provides a corrective action plan explaining how the contractor will prevent future improper disclosures of SBU building information. Progress payments may also be withheld for failure to comply with any provision in this clause until the contractor provides a corrective action plan explaining how the contractor will rectify any noncompliance and comply with the clause in the future.

i. Subcontracts. The contractor and subcontractors must insert the substance of this clause in all subcontracts.

III.P. Non-Compliance with Contract Requirements

In the event the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this Contract, fails to initiate promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the Contracting Officer shall have the right to order the Contractor to stop any or all work under the Contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of Contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.

III.Q. Safeguarding Sensitive Data and Information Technology Resources In accordance with FAR 39.105, this section is included in the contract. This section applies to all users of sensitive data and information technology (IT) resources, including awardees, contractors, subcontractors, lessors, suppliers and manufacturers. The following GSA policies must be followed.

These policies can be found at Directives Library.

1. CIO P 2100.1K GSA Information Technology (IT) Security Policy

2. CIO P 2100.2B GSA Wireless Local Area Network (LAN) Security

3. CIO 2100.3C Mandatory Information Technology (IT) Security Training Requirement for

Agency and Contractor Employees with Significant Security Responsibilities

4. CIO 2104.1A CIO CHGE 1 GSA Information Technology IT General Rules of Behavior

5. CIO 2105.1 C CHGE 1 GSA Section 508: Managing Electronic and Information

Technology for Individuals with Disabilities

6. CIO 2106.1 GSA Social Media Policy

7. CIO 2107.1 Implementation of the Online Resource Reservation Software

8. CIO 2160.4A Provisioning of Information Technology (IT) Devices

9. CIO 2162.1 Digital Signatures

10. CIO P 2165.2 GSA Telecommunications Policy

11. CIO P 2180.1 GSA Rules of Behavior for Handling Personally Identifiable Information

(Pll)

12. CIO 2182.2 Mandatory Use of Personal Identity Verification (PIV) Credentials

13. CIO P 1878.2A Conducting Privacy Impact Assessments (PIAs) in GSA

14. CIO IL-13-01 Mobile Devices and Applications

15. CIO 2102 Information Technology (IT) Integration Policy

16. HCO 9297.1 GSA Data Release Policy http://www.gsa.gov/directives

17. HCO 9297.2B GSA Information Breach Notification Policy

18. ADM P 9732.1 D Suitability and Personnel Security

The contractor and subcontractors must insert the substance of this section in all subcontracts.

III.R. Apprenticeship Plans

(1) Within 30 days following the exercise of the GMP Option, the Contractor shall furnish the Contracting Officer with an Apprenticeship Plan. The plan shall include the following:

(a) Trades to be subcontracted and those to be self performed. Indicate if a trade is to be performed using approved registered apprenticeship programs. A registered apprenticeship program is defined as a program that is registered with the U.S. Department of Labor or a State Apprenticeship Agency, under 29 CFR Part 29.

(b) The percentage of trades (subcontractors) to be awarded using registered apprenticeship programs. (If self-performing trades, identify this information as it applies to such trades).

(c) The target number of apprentices to be employed under this Contract.

(d) New registered apprenticeship programs to be initiated as a part of this

Contract.

(e) A description of the means used to recruit and employ apprentice labor under registered programs.

(f) A Training Plan that includes a complete list of specific training courses, including safety requirements, to be used by the Contractor and major trade subcontractors. Identify the number of hours and the method used to provide apprenticeship training (on the job training, classroom training, etc.). Provide the following information regarding safety training provided for supervision and craft labor employees:

(i) The amount of time (approximately) that each contractor or subcontractor devotes to safety training by craft and

(ii) The steps taken to ensure that safety training is conducted in an effective manner.

(2) During the performance of this Contract, the Contractor shall submit to the Contracting Officer a quarterly Labor/Trade Apprenticeship and Training Program Report containing the following:

(a) List of awarded subcontractors by trade

(b) Name of subcontractors with registered Apprenticeship Programs

(c) Total number of apprentices used to date on Contract

(d) New approved registered apprenticeship programs (if any) established as a result of this Contract

(e) Total number of on-the job training hours

(f) Total number of classroom training hours

(g) Brief description of effort to meet Labor/Trade Plan goals.

(3) The…