This document contains the agenda and sign-in sheet from a pre-proposal conference for a design-build solicitation. The solicitation is for design and construction services to modernize elevators and escalators at the Diana E. Murphy United States Courthouse in Minneapolis, Minnesota.
The General Services Administration is conducting a two-phase, best value procurement to select a contractor. Phase 1 involves evaluating technical qualifications, design-build approach, the lead designer's portfolio, and past performance. A maximum of three firms will be shortlisted to submit proposals in Phase 2. Phase 2 will evaluate design concept quality, key personnel qualifications and experience, management approach, and price. Questions are due by October 20th, and Phase 1 proposals are due November 6th. The shortlist will be announced in mid-December. Phase 2 will include concept reviews and interviews, with an intended award date of June 2024 and notice to proceed for design and construction in 2024-2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Murphy Amendment 001.pdf | ||
| DRAFT Murphy SBSA_DB_Agreement_September 2023.pdf | ||
| Murphy Reps and Certs March 2023.pdf | ||
| Instructions for Questionnaire.docx | DOCX document | |
| 47PF0023R0074 Form.pdf | ||
| Murphy SBSA_DB_Solicitation_2_Phase_Part_I_Sol_September_2023.pdf | ||
| PBS_Past_Performance_Form_Rev_6_12_15.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Amendment 002 is issued to provide the pre-proposal agenda and list of invitees.
R5 AMD Capital & Customer Projects Contracting Branch Capital Construction Team 230 S Dearborn St Chicago, IL 60604 USA
47PF0023R0074
1 5
10/27/2023
10/06/2023
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
PreProposal Conference Agenda GSA Solicitation No. RFP 47PF0023R0074 Time/Date: 10:00 AM CST, Oct 16, 2023 Location: Virtual
The purpose of this Pre-Proposal Conference is to discuss the Phase I Request for Proposal (RFP), issued on October 6, 2023, for Design Build Services for the Diana E Murphy US Courthouse Elevator & Escalator Modernization Project in Minneapolis, Minnesota.
The goal of this Conference is to answer any questions regarding Phase I of the RFP, provide an understanding of the proposal structure, as well as a brief overview of the proposal submission requirements, evaluation criteria, and present the scope of work for the Diana E.
Murphy US Courthouse Elevator & Escalator Modernization Project.
A copy of the agenda and sign in sheet will be emailed following the discussion. The agenda and sign in sheet are not intended to reiterate everything discussed in the meeting, but identify those points that may affect an offerors’ understanding of the solicitation.
Please be aware that no oral statement made by the Government Representatives during the conference will have the effect of amending the solicitation. In the event that discussions during the conference indicate a need to change the solicitation, an amendment to the RFP will be issued in writing. All amendments must be acknowledged by the time/date proposals are due.
Currently, there are no amendments to the solicitation.
AGENDA
Introductions
● Contracting Officer: Jennifer Styzek
● Project Manager:
● COR:
Dan Kammann Brad Taplick
● Property Manager: Julie Nowak
Project Background & Overview of the Scope of Work
This project includes all labor and materials required to provide design, engineering, construction, and other related services necessary to modernize the existing escalators, as well as the passenger and freight elevators in a fully occupied federal building.
Overview & Logistics of Design Build Procurement Process
● Best value/trade-off procurement
● Two Phases
○ Phase 1 is qualifications based. Objective is to identify a shortlist of most qualified firms. (Technical Qualifications of Firms, Approach to Design Build, Lead Designer’s Portfolio, Past Performance). A maximum of 3 firms will be selected to submit Phase 2 proposals. Only those selected offerors are authorized to submit Phase 2 proposals.
○ Phase 2 is the request for Proposal. Only shortlisted teams will be engaged in Phase 2; includes technical and price proposals. (Quality of Design Concept;
Qualifications, Experience and Past Performance of Key Personnel; Management and Technical Approach; and Price Proposal)
● General Timeframe/Milestones
○ Questions are due by October 20, 2023
○ Phase 1 Proposals Due November 6, 2023
○ Shortlist will be announced in mid December 2023
○ Phase 2 will consist of concept reviews and interviews
○ Award is planned for June 2024, NTP for design is June 2024, and NTP for
Construction Spring 2025
● Amendments, clarifications, attendance information, etc will be issued via SAM.gov.
● Questions
Phase I Submittal Requirements:
■ Technical Proposal - electronic/proposal to be sent to jennifer.styzek@gsa.gov - 35 pages
● Technical Qualifications of Firms
● Approach to Design Build
● Lead Designer’s Portfolio
● Past Performance of the offeror’s team
● Acknowledgement of any Amendments
● SAM registration
● Verification of firm’s VETS-4212 compliance
Questions on Process and Logistics:
Any/all communication, including RFIs, Questions, or Comments following the pre-proposal conference and prior to receipt of proposals should be directed at the Contracting Officer, Jennifer Styzek at jennifer.styzek@gsa.gov.
jennifer.styzek@gsa.gov
Diana E. Murphy US Courthouse Elevator & Escalator Modernization Project Pre-Proposal Conference Created by: Jennifer Styzek - 5P2QEB · Your response: Yes, I'm going
Time
10am - 11am (Central Time - Chicago)
Date
Mon Oct 16, 2023
My Notes
Guests aelliott@versaconinc.com bdinger@versaconinc.com Brad Taplick - 5P2DA czierhut@versaconinc.com Dan Kammann - 5P2DA Elizabeth Madison - 5P1FA jcalantonio@nicholscontracting.com Jennifer Styzek - 5P2QEB kzellmer@urbanelevator.com paul@m2federal.com sam@m2federal.com scott.schumaker@crutcho.com Julie Nowak - 5P1NBB brandon@ucs-now.com lee@hamlineconstruction.com