20210414_GSA Seiberling__Pre Bid Meeting Minutes (2).pdf
PDF 121 KB Posted
- Attached to
- Akron Replace Judges-Prisoners Elevator
- Solicitation number
- 47PF0021R0045
About this file
This document contains minutes from a pre-bid meeting and information about a related federal contract opportunity. The pre-bid meeting minutes outline the project scope to demolish and replace the judges elevator at the Seiberling Federal Building in Akron, Ohio, including installation of new elevator equipment and controls as well as additional openings and doors. Interested contractors are required to submit questions by a deadline of five business days before bids are due on May 4, 2021. The federal contract opportunity posting specifies this as a small business set-aside for elevator demolition and installation services with an estimated cost between $500,000 and $1,000,000 and a one-year maintenance agreement. The General Services Administration seeks to award the contract in May 2021 for work to be completed within 100 calendar days of notice to proceed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1 47PF0021R0045 w attachment.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEETING MINUTES MTG. DATE: 04.14.21
PRE BID MEETING #01 ISSUE DATE: 04.14.21
LOCATION: John F Seiberling Federal Building, Akron, OH
BY: Mathangi Raghupathy, AECOM
PROJECT: Replace Judges Elevator
ATTENDEES:
Brendan Grady, AECOM
Jim Gerger, AECOM
Mathangi Raghupathy, AECOM
Hung Le, GSA
Laura Brown, GSA
James Stewart, GSA
Martin Harris, GSA
Rebecca Lane, GSA
Ken Mulbach, US Courts
Ashley Midock, US Marshalls
Contractors:
John Francis
Tom Connor
Andrew Campagne
Bob Kerr
Michael Daniels
Scott Boling
Vickie Guy
COPIES: Brian Mihalcin, AECOM
Attendees
File
A pre-bid site meeting was held as a conference call on Wednesday, April 14th, 2021 at 2:00 pm.
GENERAL ITEMS OF DISCUSSION:
1.1 Reviewed the Preconstruction Meeting Agenda which includes the following items.
1.2 Introduced attendees, distributed contact information. GSA points of contact and the roles were established. Contracting Officer: Martin Harris, Point of Contact: Hung Le, Building Manager:
Rebecca Lane, SME for Elevator is Jim Stewart.
1.3 Contractors to give the GSA 2 full business days notices in advance for requesting building access.
1.4 Proposal is due on May 4 2021. All questions regarding project scope to be submitted to GSA no later than 5 business days before bids are due. Answers will be issued via amendment by the GSA within 3 business days before bids are due.
1.5 Questions to be sent to Hung Le, GSA, Roger Schulte CO Specialist.
1.6 Jim Gerger AECOM reviewed overall project scope and the drawings. All floors to receive new access controls. Hung Le, GSA stated they have posted the drawings to the contractors.
1.7 The following items were discussed by Hung Le, GSA:
a. Interim NTP to be expected upon award, with approximately 60 days between interim NTP and on-site NTP. Substantial completion is required 100 days after the on-site NTP.
b. All submittals to be approved prior to NTP.
c. Any staging at the GSA building to be secured.
d. Photo documentation – Contractor is expected to document the entire space prior to beginning work.
e. Working hours will be after building working hours.
f. Dumpster location was discussed. Building manager Rebecca Lane GSA stated to have closed dumpster. Location to be given after bids are chosen.
g. Parking – Ample parking in the garage for the afterhours in the dock.
h. All questions to be sent to Rodger Schulte, GSA.
1.8 Site walk to be held on April 16 Friday. Contractors to RSVP to Hung Le, GSA for building access. All
Covid protocols to be followed on site, which includes wearing a mask.
If any of the above is in conflict with your recollection of the meeting, or if any important points have been omitted, please contact the writer within five (5) working days of the issuance of this memo, or its contents will be assumed to be complete and correct.
File details come from the government source that posted it. Updated .