This document contains responses to contractor questions on a solicitation for construction management services. The solicitation is for a CFTC consolidation project being conducted by the General Services Administration Region 5. Key details include that the solicitation requires pricing for target estimated costs of work to be provided at the proposal stage and finalized at the 90% design stage, with the GSA contracting officer determining the appropriate time for conversion to firm fixed price. Davis-Bacon prevailing wage rates apply. Bidders must submit resumes and past performance examples with their proposals, as well as a 20% bid guarantee bond. The document provides clarification on a range of topics including specifications for ceiling and door components, the project schedule and meeting requirements, and confirmation that the agency rather than the construction manager will procure furniture.

View the file

Other files for this federal contract opportunity

Other files attached to CFTC Consolidation Project – CMc Services Award, newest first.
File Type Posted
beta.SAM Award Public Notice.pdf PDF
47PF0020R0097 Amendment 001.pdf PDF
Pre-Proposal RSVP Form CFTC 2020 11 02.pdf PDF
SF1442 and Pricing Sheet CFTC 2020 11 02 .pdf PDF
CMc Agreement CFTC 2020 11 02.pdf PDF
CMc Solicitation CFTC 2020 11 02.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

5P1QAB

This Amendment is for the following purposes:

1. Extending the proposal due date from December 3rd to December 8th 2020 no later than 11:00AM CST.

2. Issuance of responses to RFIs received, Amendment 002 Document.

5P1QAB

Programs/ Quality Assurance Branch 230 S. Dearborn St.

Chicago, IL 60604 USA

Programs/ Quality Assurance Branch 230 S. Dearborn St.

Chicago, IL 60604 USA

47PF0020R0097

47PF0020R0097

12/01/2020

11/03/2020

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

GSA Great Lakes Region

Solicitation 47PF0020R0026 Amendment 002 RFI List

1. I made an appointment for a walk through and the documents say the walk throughs will be on the 18 th . According to Jermaine no one will be in the office tomorrow and the office is only open one day a week. The next available time is the 24 th . With Thanksgiving that week and the bid due at 11 am that Monday morning I was wondering if there can be a week extension since the walk throughs were pushed a week from what the solicitation states. I do know that I am not the only GC walking that day. According to Jermaine there are 4 scheduled for that day as of last night. An extension would be greatly appreciated.

a. Due to a change in office schedule and holiday, I was not scheduled to be on-site Nov 18th. The revised dates were discussed during the virtual pre-proposal meeting held Monday, Nov 9th. Dates were

Thurs Nov 12th and Tues Nov 24th for walkthroughs made by appt only, adhering to CDC social distancing guidelines.

2. Can the solicitation be emailed to you on the due date? The solicitation states a sealed original, but does not state how many. In the past emailing a solicitation has been deemed acceptable.

a. The RFP states only electronic proposals will be accepted. Attachment limitations are included within the

RFP

3. Is #2 on the pricing sheet an estimate/budget? I ask because the drawings are 65% and we are only allowed to have 1 other person attend the walk through with us. I assume if it is a budget/estimate once the drawings are at

100% the pricing will be finalized.

a. Refer to the SOW section for more details: “III.A.11.e. Cost Estimating, Reconciliation, and Proposed

Alternatives (CERPA)”. The cost that is to be provided by the bidders is: “Target Estimated Cost of Work” or

“ECW”. The FINAL ECW shall be established at 90% CD stage. Also, GSA CO will decide when GMP conversion to FFP is appropriate.

4. Is this budget to be priced with Union labor?

a. Proposed pricing is to reflect applicable LOCAL PREVAILING LABOR RATES. The Davis-Bacon and

Related Acts, apply to contractors and subcontractors performing on federally funded or assisted contracts in excess of $2,000 for the construction, alteration, or repair (including painting and decorating) of public buildings or public works. Davis-Bacon Act and Related Act contractors and subcontractors must pay their laborers and mechanics employed under the contract no less than the locally prevailing wages and fringe benefits for corresponding work on similar projects in the area. The Davis-Bacon Act directs the Department of Labor to determine such locally prevailing wage rates.

5. Is there a Fire Alarm contractor that is assigned to the existing space that I should reach out to for pricing?

a. No. All subcontractors services are to be part of this contract/proposal.

6. Is there a telecom contractor that is assigned to the existing space that I should reach out to for pricing?

a. No. All subcontractors services are to be part of this contract/proposal.

7. Is there an electrical contractor that is assigned to the existing space that I should reach out to for pricing?

a. No. All subcontractors services are to be part of this contract/proposal.

8. Is there a Mechanical contractor that is assigned to the existing space that I should reach out to for pricing?

a. No. All subcontractors services are to be part of this contract/proposal.

9. Is there a Plumbing contractor that is assigned to the existing space that I should reach out to for pricing?

a. No. All subcontractors services are to be part of this contract/proposal.

10. Are we responsible for furniture and other FFE items?

a. No. The agency will be procuring their FF&E separately, with the exception of any appliances specifically identified in the design specifications.

11. Pages 48-51 of the CMc asks for examples of QCP, LEED strategies, personnel resumes and past performance descriptions. The solicitation offer form does not mention or have areas to submit these resumes and examples. Are the resumes and examples described on pages 48-51 to be submitted after the initial solicitation and would be required if we are selected for this project?

a. Personal resumes and past performance are to be submitted at this time.

12. Is a bid bond required to be submitted with the proposal? If so, what is the amount?

a. A bid guarantee in the amount of 20% is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Per FAR 52.228-1, failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

13. What does the following abbreviation mean in regards to the door and frame schedule; Door “FL”

a. Full Lite – large glass panel.

14. Are the aluminum frames knock down or welded?

a. The frame will be welded

15. There is no description of new acoustical ceiling tile and new suspension grid system shown on the Reflected

Ceiling Plans IN4-07 & IN4-08. The aforementioned drawings only show a 2' x 2' new acoustical ceiling tile and new suspension grid with no manufacturer or model number. Also, the Specifications for this project do not include the material requirements for the new acoustical ceiling tile and new suspension grid. Can you clarify the ACT spec?

a. For ceilings, use the following:

C1 BUILDING STANDARD CEILING TILE AT ALL T5 AND T6 OFFICES, TEAMING ROOMS

USG 2 x 2 Frost fineline (FL) beveled tegular panels (Item 418, Color White, NRC .70, CAC 40)

C2 CAC 50 SOUND ATTENUATING CEILING TILE,

AT ALL T4 OFFICES

Armstrong 2 x 2 Calla PrivAssure-50 square tegular panels (Item 8881, Color White, NRC .80, CAC 50)

16. The Door & Frame Schedule on IN9-01 does not match the 7th and 8th Floors Construction Plans on IN3-07 and

IN3-08. The Door Mark Numbers do not correctly match with the correct Room Names at the end of the Door &

Frame Schedule. Also, several of the Door Mark Numbers listed at the end of the Door & Frame Schedule are not shown on IN3-07 and IN3-08 Construction Plans.

a. Typical Office doors and frames are aluminum with glass double glazed lites - demountable partitions –

Infinium Refine double glazed is basis of design.

17. There are no interior elevations in the set of drawings and therefore, millwork cabinets and countertops/backsplashes cannot be verified.There are drawing references at the Pantry Rooms on IN3-07 and

IN3-08 to millwork details on Drawing IN11-00 however, Drawing IN11-00 is missing from the set of drawings although Drawing IN11-00, titled: "Millwork Details" is listed in the Drawings Sheet Index G0-01.

a. Locations of casework shown would typically have base cabinets, wall cabinets and countertops with Plastic

Laminate finishes. Backsplash will be typically tile.

18. What is the estimated number of meetings that your team envisions for the design phase of this project?

a. Please refer to the spec sections III.A.3-10 for the list of required meetings. The exact number of meetings are to be calculated based on planned design duration given in the solicitation.

19. Is the architect planning to issue any additional specification sections beyond Division #1, prior to the bid submittal date?

a. No additional spec sections will be issued prior to the bids due date.

20. Should we provide a written proposal with our bid package in order to clarify the scope of work we have included for this project?

a. Please follow the SOLICITATION requirements for the format and content of the submission.