Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
6/12/2023
Number
Drawing/
Spec.
Number
(RFI) Request for Information. GSA Response
S105, various
Cornice: please clarify whether cornice repair is included in this Phase II project. If so, what is extent of this scope. Does this include entire cornice all the way around the building, or just outlined areas per note 10?
Cornice repair is limited to the areas outlined per Note 10.
2 Various
Lightwell floor system: please clarify whether moat floor waterproofing system is included in this project and does this include membrane and complete roofing-type system.
That work is not included in this project.
A1.1, various
Limits of work: dashed lines on various drawing sheets indicates limits of work.
Please clarify what scope is included in this Phase II project.The drawings are not clear and some of the drawing sheets show inconsistent dashed lines locations.
Scope of work consists of the East elevation, South elevation, West elevation, existing stone balustrade repair and stone floor at the existing portico balcony to be restored, and painting of handrails. Areas within dashed lines showing work completed in a separate project are partially correct. The moat areas within the dashed lines are not correct. Slab and wall repairs in the moat areas are in this project. See also Sheet G0.1 for additional information.
4 03 31 10
Slab repair: 03 31 10 unit pricing indicated in specifications; however, this is a firm fixed price contract. Please confirm what should be included in the proposal.
See Item 22 in Estimate Repair Quantities on S001. Increase quantity for slab repairs to 13 CF for your proposal.
S201, various
Moat wall spall repairs: please confirm what quantity is required for moat wall repairs on this phase 2 project.
See Item 19 in Estimate Repair Quantities on S001. Increase quantity for wall repairs to 2 CF for your proposal.
6 Various Portico: scope of repair was discussed at site visit. Should this include clean and restore in place, or remove tiles down to slab, etc., as indicated on drawings?
Scope of this repair should only include clean and restore in place.
7 Various Bid options: should bid option items on drawings be priced into CLIN 1? Yes. All bid options should be included in the base price under CLIN 1
Request For Information
Historic U.S. Bankruptcy Courthouse, Building Enclosure Repairs - Phase 2 Tallahassee, FL
Pre-proposal RFI Responses
Solicitation 47PE0723R0008 Amendment 0001
6/12/2023 3:59 PM
| topmostSubform[0]: |
| Page1[0]: |
| Code[0]: 4P1QB |
| Copies[0]: 1 |
| CheckBox9[0]: 1 |
| Code[2]: 4P1QB |
| NameandTitleOfficer[0]: Rania Sanders, Contracting Officer |
| Is[0]: Off |
| CheckBox10[0]: Off |
| NameandAddress[0]: |
| DateSigned[1]: |
| Pages[0]: 2 |
| AmendmentNo[0]: 0001 |
| Dated10B[0]: |
| ModificationNo[0]: |
| AdministeredBy[0]: Gulf Coast Branch |
Gulf Coast Branch 501 E POLK ST Room: 805
TAMPA, FL 33602-3949
| FacilityCode[0]: |
| CheckBox13B[0]: Off |
| CheckBox13D[0]: Off |
| ReqNumber[0]: EQ4P1PB-23-0012 |
| Dated9B[0]: 5/11/2023 |
| C13[0]: |
| Description[0]: The purpose of this solicitation amendment is to incorporate responses to Requests for Information (RFI) and to extend the offer due date. |
1. See attached RFI responses, 1 page (7 RFIs)
2. SF1442, block 13a and wherever referenced, offer due date is extended from 6/14/23 to 6/28/23. The time is unchanged (5:00PM EDT).
| NotExtended[0]: Off |
| Code[1]: |
| AmendmentNo[1]: 47PE0723R0008 |
| ContractIDCode[0]: |
| DateSigned[0]: |
| CheckBox11[0]: 1 |
| Page[0]: 1 |
| AccountingData[0]: |
| CopiesReturned[0]: |
| CheckBox13A[0]: Off |
| IsNot[0]: Off |
| EffectiveDate[0]: 6/12/2023 |
| A13[0]: |
| ProjectNo[0]: RFL11475, RFL11483 |
| CheckBox13C[0]: Off |
| Extended[0]: 1 |
| D13[0]: |
| IssuedBy[0]: Gulf Coast Branch |
Gulf Coast Branch 501 E POLK ST Room: 805
TAMPA, FL 33602-3949