This is Amendment 0002 to Solicitation 47PB5126R0030 for a General Contractor for the Seismic Retrofit at the Clemente Ruiz Nazario U.S. Courthouse in San Juan, Puerto Rico. The amendment is issued by the PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division, Capital Contracting Branch - Northeast, with an effective date of November 10, 2026. The amendment incorporates four key additions to the solicitation: Pre-Proposal Conference presentation slides containing project drawings (controlled materials requiring access authorization), the Pre-Proposal Conference Attendance Sign-In Sheet documenting prospective offerors and their representatives, 65% design drawings, specifications, and report materials provided for informational and reference purposes only (with a disclaimer that these draft materials do not constitute final construction documents and are subject to change), and official responses to all vendor Requests for Information submitted to date. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation by completing items 8 and 15 of Standard Form 30 and returning copies, by acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication referencing the solicitation and amendment numbers.
The document also includes a Questions and Answers section addressing three vendor inquiries regarding technical evaluation criteria. The responses clarify that offerors may only use projects completed within the last ten years (not ongoing projects), that offerors must submit either a PBS Past Performance Questionnaire completed by the applicable client or FINAL CPARS for each project proposed in Factor 1 (and cannot incorporate previously submitted PPQs by reference), and that Phase I evaluations are expected to be completed by March 2027, subject to change. All other terms, conditions, and specifications of Solicitation 47PB5126R0030 remain unchanged and in full force and effect.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
PQAA
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
General Contractor for the Seismic Retrofit at the Clemente Ruiz Nazario U.S. Courthouse, San Juan, Puerto Rico
Please see attached.
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1900 E Street NW Washington, DC 20415 USA
9A. AMENDMENT OF SOLICITATION NUMBER
47PB5126R0030
5. PROJECT NUMBER (If applicable) 1 4
11/10/2026
9B. DATED (SEE ITEM 11)
11/03/2026
Natalia Lugo-Vina Cruz
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
General Contractor for the Seismic Retrofit at the Clemente Ruiz Nazario U.S.
Courthouse, San Juan, Puerto Rico
Amendment 0002 to Solicitation 47PB5126R0030 (General Contractor for the Seismic Retrofit at the Clemente Ruiz Nazario U.S. Courthouse, San Juan, Puerto Rico) is issued as follows:
1. Incorporate and attach the Pre-Proposal Conference presentation slides. The slides are available under the attachments section. Please note that because they contain project drawings, these presentation materials are controlled and require access authorization.
2. Include and attach the Pre-Proposal Conference Attendance Sign-In Sheet, providing the official record of all attending prospective offerors and representatives.
3. Provide and attach the 65% design drawings, specifications, and report strictly for informational and reference purposes. These draft materials are provided solely to enhance understanding and context of the project scope and do not constitute final construction documents and the information contained therein is subject to change.
4. Incorporate and issue official responses to all vendor Requests for Information submitted to date.
All other terms, conditions, and specifications of Solicitation 47PB5126R0030 remain unchanged and in full force and effect.
No. Question Response
Reference: Solicitation - A. Phase I Technical Evaluation Factors, FACTOR 1 – EXPERIENCE ON SIMILAR PROJECTS (40%), (Page 10 of 58).
Questions:
a. Please confirm whether offerors can use projects older than 10 years.
b. Please advise whether offerors may submit ongoing projects.
Responses to Questions A and B are provided below:
Refer to page 10 of the Solicitation.
No-- please refer to the Solicitation (Page 10) "Projects completed within the last ten (10) years"
Reference: Solicitation - A. Phase I Technical Evaluation Factors, FACTOR 2 – PAST PERFORMANCE ON RELEVANT PROJECTS (15%), (Page 11 of 58)
Questions:
The Submittal Requirements state that “offerors must not incorporate by reference PPQs previously submitted for other Solicitations.”
a. Please advise whether offerors may submit previously completed PPQs in their entirety in lieu of requesting new PPQs. We have several projects that experienced significant turnover, and the Government project personnel are no longer able to complete PPQs.
b. Please clarify whether we may submit interim CPARs for projects that were recently completed and do not yet have a FINAL CPAR posted. Or for projects that are complete but the Government never completed the final CPAR.
Responses to Questions A and B are provided below:
Refer to page 11 of the Solicitation.
The Offeror must submit a PBS Past Performance Questionnaire (PPQ) (Attachment 3), completed by the applicable client, or FINAL CPARS for each project proposed in Factor 1.
3 How long does the Government anticipate Phase I evaluations to take? We expect Phase I to be completed by March 2027. Please note that the date is subject to change.