47PB0023R0029 Exhibit 01 Deliverables.pdf

PDF 109 KB Posted

Attached to
Contracted Building Automation System Support Services IDIQ Contract Federal contract opportunity
Solicitation number
47PB0023R0029
Issued by
General Services Administration Public Buildings Service Region 1

About this file

This exhibit outlines deliverables and deadlines for a building automation system support services contract with the General Services Administration Public Buildings Service Region 1. Key deliverables include transition plans, communications plans, emergency response plans, building automation system reviews, progress reports, and responses to work orders. Deadlines range from immediate notification for security breaches to 90 days for final documentation on completed work orders. The contractor must also conduct preventative maintenance in accordance with an approved schedule and provide technicians, building recovery plans, and responses to additional service requests within specified timeframes.

View the file

Other files for this federal contract opportunity

Other files attached to Contracted Building Automation System Support Services IDIQ Contract, newest first.
File Type Posted
Exhibit 06 Niagara Supervisor Information.pdf PDF
SF30 Solicitation Amentmend 0001 47PB0023R0029.pdf PDF
Exhibit 05 Niagara JACE Information.pdf PDF
RFP 47PB0023R0029 Consolidated BAS Support Services (revised 08 01 2023).pdf PDF
RFP 47PB0023R0029 Amendment 0001 Questions and Answers.pdf PDF
15-4009.txt TXT text file
15-4005.txt TXT text file
15-4021.txt TXT text file
15-4047.txt TXT text file
15-4007.txt TXT text file
15-4141.txt TXT text file
15-4019.txt TXT text file
15-4095.txt TXT text file
15-4137.txt TXT text file
15-4087.txt TXT text file
47PB0023R0029 Exhibit 04 Wage Determinations.pdf PDF
RFP 47PB0023R0029 Consolidated BAS Support Services.pdf PDF
RFP Attachment 1- Offeror Representations and Certifications .docx DOCX document
RFP Attachment 2- Pricing Sheet.xlsx XLSX spreadsheet
RFP Attachment 3 - PPQ.pdf PDF
Performance Work Statement (PWS) Contracted Building Automation Systems Support Services.pdf PDF
47PB0023R0029 Exhibit 02 BMC Systems and R1 Buildings.pdf PDF
47PB0023R0029 Exhibit 03 QASP.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 1 - DELIVERABLES

SUBMITTAL OR

ACTION

CONTRACT

SECTION

DEADLINE

Initiate HSPD-12 clearances as needed

9.0 Within 10 days of contract award.

Kickoff meeting N/A Between award and work start; submit minutes within 2 working days of meeting.

Proposed Transition Plan

4.1 Within 15 calendar days after contract award.

Complete NCMMS Transition Activities

4.1 Within 60 calendar days of contract award.

Draft Communications Plan

4.1 Within 15 calendar days of award.

Final Communications Plan

4.1 Within 60 calendar days of contract award.

Draft Emergency Response Plan

4.1 Within 15 calendar days of award.

Final Emergency Response Plan

4.1 Within 60 calendar days of contract award.

BAS Technical “Interviews”

4.1 Completed within the Transition Period.

Distribution of any approved changes to Communications Plan

6.0 Within 5 working days of approval.

Contractor Quality Control Plan

17.1 Within 10 working days of contract award.

Progress meetings 6.1 Weekly; submit minutes within 2 working days of meeting.

Notice of security breach or attack

9.0 Immediately notify the COR and the GSA IT

Service Desk.

Scheduling of prolonged disruptive activities

11 Schedule at least 5 calendar days in advance.

Building Automation System Monthly Review reports

4.4.1 Within 5 working days following the

performance month.

Monthly Progress reports

6.2 Within 5 working days following the

performance month.

Resolve BAS application problems

4.3 Respond to, triage, and complete work in line

with the requirements of Section 4.7.

Assign or delete user accounts

4.3.1 2 working days of request.

PBS application failure alarms

4.3.3 Respond to, triage, and complete work in line

with the requirements of Section 4.7.

PBS server patching application checking

4.3.5 Perform the weekend of server patching.

Attend web-meeting training

N/A As needed, follow the schedule as approved by

COR.

Respond to control log RFIs

4.3.7 & 4.3.8 Respond to, triage, and complete work in line with the requirements of Section 4.7.

Project team conference calls

6.1 As scheduled with the project team and COR.

PDF library 4.3.9 Add documents with clear structure and labeling within 5 working days of receipt.

BAS alarm response 4.4.2 & 4.5.2.3 Depending on the nature of the alarm, triage and correct within the timeframe established in Section 4.7. Notify O&M, OCIO and / or COR as applicable.

Review Spark Top Ten report

4.4.1 & 4.4.3 5 working days of receipt

Advice on BAS matters 4.4.4 As needed, in accordance with the timeframes and requirements established in Section 4.6.

Proposal for Additional Service Work Requests (ASWR)

4.9.1 Within 2 working days of request.

Cost and closeout documentation for

ASWR

4.9.8 30 working days after completion of ASWR.

Utility hour requests-emergency

4.6.2 Start immediately, continue to resolution

Utility hour requests-small

4.6.2 3 working days of request

Utility hour requests-large

4.6.2 10 working days of request

Emergency work order 4.7 Respond as soon as feasible, and complete the work order within 24 hours.

Urgent work order 4.7 Respond within 1 hour, and complete the work order within 48 hours.

Routine work order 4.7 Begin work within 24 hours, and complete work within 72 hours.

Preventive Maintenance

Complete Preventive Maintenance work in accordance with the approved schedule.

Final documentation for work orders

5 90 days of status change to complete, or 10 days of completion status of quality control passed inspection status.

Seasonal Review Report

4.5.2.5 & GSA Best Practices for

Building Automation System

5 working days after the performance month.

Technicians (current edition)

Building Recovery Plans & plan updates

4.4.1 5 working days after end of performance month

EXHIBIT 1 - DELIVERABLES

File details come from the government source that posted it. Updated .