Solicitation #: 47PB0020Q0001 USCG N. Kingstown, RI ACM Abatement
U.S. General Services Administration Public Buildings Service
Office of Real Property Utilization and Disposal
Attachment 2
47PB0020Q0001
Scope of Work (SOW)
Abatement of Damaged Friable Asbestos-Containing Materials (ACM) for
USCG North Kingstown Housing Units 216, 264, and 296 Signal Road
North Kingstown, Rhode Island 02852 (GSA Case #:1-X-RI-0524-AA)
February 03, 2020
1.0 Introduction
1.1 Purpose
The U.S. General Services Administration (GSA) Region 1 Real Property Utilization & Disposal Division (1PZ) on behalf of the United States Coast Guard (USCG) seeks to procure Abatement of Damaged Friable Asbestos-Containing Materials (ACM) services in support of the divestiture of the USCG N. Kingstown Housing site. The impacted vacant residential buildings are located at 216, 264, and 296 Signal Rock Road, North Kingstown, Rhode Island 02852 (the “Property”).
1.2 Objective
The objective of this scope of work (SOW) is to procure abatement services for damaged friable ACMs as identified in the ACM Condition/Risk Assessment report dated December 19, 2019.
1.3 Background
Property Description:
The USCG owns the vacant multi-family residences at 210, 216, 224, 232, 240, 256, 264, 272, 280, 288, and 296 Signal Rock Road, North Kingstown, Rhode Island 02852. The Site consists of eleven 1,512 square-foot, single-story, wood frame, vinyl siding, shingle roof, slab-on-grade, residential housing units with an attached garage and asphalt driveways.
In preparation for divestiture of the property, the Government contracted environmental services which included Asbestos-Containing Material (ACM) Condition/Risk Assessments reports in October 2014 and in December 2019. The assessments of condition and evaluations were conducted in accordance with practices provided in the Rhode Island Department of Health (RIDOH) asbestos regulations R23-24.5-ASB, and the federal Asbestos Hazard Emergency Response Act (AHERA) regulations 40 CFR 763.
As provided in the ACM Condition/Risk Assessment Report of 2019, in the 1970s, certain friable ACMs were banned in the United States, although many asbestos products were manufactured more recently. Non-friable ACMs such as floor tiles, mastic, and roofing products are found in more recent construction. A thorough inspection of all buildings regardless of age is required prior to renovation/demolition under the federal National Emission Standard for Hazardous Air Pollutants (NESHAP) regulation, 40 CFR 61. The NESHAP regulation refers to the inspection and sampling protocol in the Asbestos Hazard Emergency Response Act (AHERA) 40 CFR 763. Rhode Island Department of Health (RIDOH) also regulates ACM in renovation and demolition. Prior to undertaking a renovation or demolition project, ACMs identified during the inspection must be abated in accordance with RIDOH Rules and Regulations for Asbestos Control (R23-24.5-ASB) and Occupational Safety and Health Administration (OSHA) Asbestos Standard for the Construction Industry (29 CFR 1926.1101).
Although it is not the intention of the USCG to renovate or demolish any structures at the property, friable asbestos is being abated according to the USCG policy in the Real Property Manual Section 4.6.4 B that states:
Friable and Non friable ACM. Friable ACM contains more than one percent (1%) asbestos by weight and can, by hand pressure, be crumbled, pulverized or reduced to powder. It is Coast Guard policy that damaged friable asbestos, that is, ACM that has in fact been crumbled, pulverized or reduced to powder, allowing for the release of fibers into the air, shall be abated prior to disposal of the property. Non friable and undamaged friable ACM shall remain undisturbed.
In the final Tetra Tech ACM Condition/Risk Assessment Report dated December 19, 2019, the contractor identified Damaged Friable ACM in various locations at 216, 264, and 296 Signal Rock Road. The report is attached for reference.
2.0 Scope of Work (SOW)
2.1 This section specifies the damaged friable ACM abatement requirements and the Contractor's applicable asbestos procedures to be used during the project. This includes removal or encapsulation of materials containing damaged friable asbestos, transportation, disposal, storage, containment of, and housekeeping activities involving asbestos or products containing asbestos, on the site or location where activities are performed.
2.2 The locations are listed in the ACM Condition/Risk Assessment report dated December 2019 and in Table 1-1 (See below). Please note: Quantities of asbestos containing materials to be abated should be determined from the drawings. The contractor is the sole responsible party for validating all dimensions and quantities of asbestos that requires abatement.
2.3 Table 1-1
Building Friable Asbestos Sampl e Code Approx.
Quantity
Location Damage
216 Signal Rock Road
Joint Compound 7-A 360 SF Interior Walls- Kitchen
Minor Isolated
264 Signal Rock Road
Joint Compound 5-A 360 SF Interior Walls- Furnace Room
Minor Isolated
296 Signal Rock Road
Joint Compound 8-B 360 SF Interior Walls- Bedroom
Moderate
Ceiling Plaster 11-A 1,200 SF Interior Ceiling- Bedroom
Minor Isolated
Pipe Insulation 12-A 6 LF Furnace Room High
3.0 Specific Requirements and Tasks
3.1 Contractor shall develop, and execute a detailed Asbestos Abatement Project Management Plan (PMP) in the best interest of the Government facility, employees, management, and the general public that includes the following Requirements and Tasks:
a) Prior to commencement of the work, the Contractor shall carefully examine the site where work is proposed in Table 1-1.
Contractor must develop, submit and receive Government approval of the Asbestos Abatement PMP. PMP must include, but not limited to, methods for abatement (i.e.
removal/encapsulation, air monitoring plan and hazard mitigation in accordance with the Federal, State and Local Asbestos Abatement safety requirements); proposed procedures and work practices to be used in the abatement of the asbestos and in complying with the requirements of this specification; sequence of asbestos abatement work; disposal plan including location of approved disposal site for solid waste and wastewater; and a detailed work schedule.
Contractor shall provide a quantity of construction personnel, equipment, materials, tools and supervision as needed to complete the services and technical requirements in the SOW.
b) Contractor’s personnel must be trained and certified by applicable authorities to provide abatement services in the state of Rhode Island. Contractor must demonstrate a working knowledge of the laws, regulations, and policies governing the removal and disposal of friable ACM in accordance with applicable requirement of 29 CFR 1910.
c) PMP shall include quality assurance/quality control mechanisms and means of communication, level of involvement and coordination with the public, client, and other stakeholders shall be identified.
d) PMP shall include all clean-up of work area including HEPA (High Efficiency
Particulate Air) vacuuming and wet cleaning of asbestos contaminated surfaces (decontamination) as needed.
e) Contractor shall provide all labor, material and equipment necessary to perform abatement of the materials listed in Table 1-1, in accordance with the approved PMP.
f) Contractor shall clean the worksite at the end of each day and be responsible for all waste removal associated with their work.
g) PMP shall include the work schedules indicating the work days and hours and the number of workers per shift. Include a chart that identifies the milestones for the completion of the project (i.e. number of days to complete work site preparation, number of days to complete ACM abatement, number of days to complete final cleaning and lockdown, etc.)
h) The Contractor shall submit a copy of all required Air Monitoring notifications as part of the PMP:
1. Air Monitoring Reports shall include, the following information for each sample: Sample identification, Employee Name, Social Security Number, Sample location, Description of task being monitored, Exposure level results in (flee), Monitoring instrument identification number, Pre-calibration, post calibration and average flow rate of each sample, Sample date, start and stop times, Type of protective devices worn (if any), Project identification number, Facility number and name, Sampling and Analytical Methods used, Contact name and company, and name of individual performing the sampling.
2. Work site Entry Logs of all personnel entering and leaving the regulated work area shall be maintained by the on-site competent person indicating the date and time of entry and egress.
3. Daily Site Inspection Logs shall be maintained by the on-site competent person indicating the date, time and results of the work area daily site inspections.
4. Waste Container/Wastewater Inventory of all generated waste containers shall be maintained indicating the location and approximate quantity of material in each container. Submission shall include waste disposal permit, tickets and all disposal manifest.
5. Contractors are required to inspect the site prior to submitting a proposal.
GSA will coordinate access to the site.
6. The Air Monitor Reports. Entry Logs, Daily Site Inspection Logs, and Waste
Drum Inventory shall be updated daily, maintained at the work site in an accessible location for regulator review.
i) The property is vacant and has no utilities services at the site. The contractor shall provide utilities necessary to complete the work.
3.2 The contractor shall review and analyze the following Government Furnished Information (GFI) provided at award:
a) Environmental Reports
b) Photographs and Drawings
3.3 The contractor shall arrange, coordinate and conduct a final inspection of the Property with GSA Project Manager (PM) after the work has been completed.
3.4 Submission of documents: The Contractor shall secure all necessary registrations, certification, and permits associated with asbestos removal, transportation, and disposal, including wastewater, as may be required by the Federal, State, and local regulations. A copy of notifications and any written approval or waivers from the state of Rhode Island shall be submitted to the COR.
4.0 Labor Requirements
4.1 All workers shall be trained in accordance with applicable requirements of 29 CFR 1910.
5.0 Deliverables:
5.1 Within 10 days after the completion of work, the Contractor shall submit to the
COR a certificate of final abatement of the property including but not limited to the following items:
a) Waste Disposal Permit and all Disposal Shipping Manifests and Tickets.
b) Air Monitor Reports conducted during the abatement.
c) Entry Logs and Waste Container Inventory maintained during the abatement task.
d) Records of Wastewater discharge to Publicly Owned Treatment Works (POTW)
6.0 Pre Construction Requirements
6.1 Submission of PMP: Site inspection will be held during the solicitation phase. The PMP shall be submitted within 14 calendar days of contract award.6.2 Post-Award/Kickoff Meeting:
The Post-Award/Kickoff Meeting will be held within_21 calendar_days of contract award
7.0 Place and Period of Performance
7.1 Place of Performance: USCG property referenced above, located in North Kingstown, Rhode
Island.
7.2 Period of Performance: Contractor shall commence the work upon contract award. The period of performance shall not exceed three (3) months.
8.0 Travel
8.1 All Travel, if any, shall be approved by COR and reimbursed in accordance with Government travel regulations (FAR 31.205-46 (a)(2)(i)).
9.0 Government Furnished Equipment (GFE)
9.1 Government Furnished Equipment: None.
10.0 Security and Inspection
10.1 Contractors are required to inspect the site prior to submitting a proposal. GSA will coordinate access to the site.
10.2 Contractor shall coordinate all property visits with GSA PM, including entering, leaving and securing property at the end of the day.
10.3 This contract does not directly affect national security and security clearances are not required. However, work is sensitive and may be considered confidential as it can impact relations between the Federal government and state or local governments, or with the public. No information, including proposals shall be released to the general public or to any agency or organization without prior written approval from GSA. Nondisclosure Agreements may be required.
11.0 Administration and Points of Contact
On behalf of the GSA Contracting Officer (CO), the Contracting Officer’s Representative (COR) is responsible for the general administration of this contract. The COR is responsible for the review/acceptance of all deliverables. This individual will serve as the GSA point of contact (“POC”) concerning information exchange, submission review, and payment of fees. Nothing said by the COR shall be construed to change contract requirements unless supported in writing by the CO.
GSA CO:
Huy Le, Supervisory Contracting Officer U.S. General Services Administration (GSA) Acquisition Management Division (1PQB)-Special Programs Team Public Buildings Service E-Mail: Huy.Le@gsa.gov
GSA CS:
David Mark U.S. General Services Administration (GSA) Office Phone: 617-531-9092 E-Mail: David.Mark@gsa.gov mailto:Huy.Le@gsa.gov mailto:David.Mark@gsa.gov
GSA COR:
Giselle E. Rubiera, Realty Specialist/COR
U.S. General Services Administration (GSA) Federal Real Property Utilization and Disposal Division (1PZ) Office Phone: 617-565-5841 E-Mail: Giselle.Rubiera@gsa.gov
The GSA Project Manager (PM) will provide assistance with property visits, property information, deliverables submission reviews, and acceptance of the tasks in conjunction with the COR.
Project Manager (PM):
Sonia Allon-Singh, Realty Specialist U.S. General Services Administration (GSA) Federal Real Property Utilization and Disposal Division (1PZ) E-Mail: Sonia.Allon-singh@gsa.gov
12.0 Invoicing
Send Invoices to:
Giselle E. Rubiera, Realty Specialist/COR U.S. General Services Administration (GSA) Federal Real Property Utilization and Disposal Division (1PZ) Office Phone: 617-565-5841 Fax: 617-565-5720 E-Mail: Giselle.Rubiera@gsa.gov
AND
Submitted electronically The website to submit electronic invoices is: https://finance3.gsa.gov/
For help submitting electronic invoices, the Contractor may contact fw-customersupport@gsa.gov, call 1-800-676-3690.
a) All invoicing shall be done electronically in accordance with the instructions detailed below. Password and electronic invoice access shall be obtained through GSA web site http://www.finance.gsa.gov.
b) The contractor shall invoice twice: once at 505 completion of the work aand once for remaining full payment of this task after GSA written approval and acceptance of the final completion report. The Contractor shall first submit a draft invoice to the COR, mailto:Giselle.Rubiera@gsa.gov mailto:Sonia.Allon-singh@gsa.gov mailto:Giselle.Rubiera@gsa.gov https://finance3.gsa.gov/ mailto:fw-customersupport@gsa.gov mailto:fw-customersupport@gsa.gov mailto:fw-customersupport@gsa.gov
CS, and CO. The contract number and the PDN number (to be provided at award) must be included on all invoices.
c) After internal review by the CS and COR, the CO/CS will notify the contractor that they are approved to submit a final invoice through the Electronic Funds Transfer (EFT) system. All final payments will be made electronically via the EFT system.
The invoice shall only be submitted for payment upon the GSA Contracting Officer’s Representative’s concurrence with the final report. Invoicing for work not authorized by the COR shall not be approved or paid for.
d) Invoices must include the following information:
• Contractor Information
• Tax ID number (EIN number)
• Contract number /Purchase Order Number
• Invoice date
• Payment Address
• Summary describing the work performed
• Contact person with phone number
e) The Contractor shall submit a GSA Form 1142- Release of Claims with submission of the final invoice at the completion and acceptance of all work under this BPA Call. A copy of the form should be sent via email to the Contracting Officer, Contract Specialist and COR, identified above.
f) Failure to comply with the procedures outlined above shall result in the Contractor’s delay of payment.
13.0 Terms and Conditions
13.1 This acquisition is being issued in accordance with the terms, conditions, and clauses set forth in the Request for Quotations (RFQ).
14.0 Regulations References:
a) 29 CFR 1910.1001, Occupational Safety and Health Act (OSHA) Asbestos Standard for General Industry Respirator Requirements.
b) 29 CFR 1926.1101, Asbestos. Safety and Health Regulations for Construction.
c) 40 CFR Part 61, U.S. Environmental Protection Agency, National Emission Standards for
Hazardous Air Pollutants (NESHAP) Asbestos.
d) 40 CFR 763 Asbestos Hazard Emergency Response Act (AHERA).
e) Rhode Island Department of Health (RIDOH) asbestos regulations R23-24.5-ASB.
File details come from the government source that posted it. Updated .